This report seeks authority to accept a grant of £1.3m from the Government Joint Air Quality Unit (JAQU) for further development of the Liverpool Clean Air Plan and in addition authority to procure expert advice to complete the Outline Business Case (OBC) and commence and complete the Full Business Case (FBC), were that advice may come to over the £500k delegated authority limit.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Key Officer Decisions (Key DARS), 6 pages
CABINET
CITY PUBLIC ECC/4
Cabinet Member: Cabinet Member – Environment & Sustainability
Director: Director of Community Services
Report Title: Acceptance of Grant Funding to support the Liverpool Clean Air Plan (LCAP) and Procurement of Expert Services
Date: Report No: 9 April 2020 CS/08/20
Decision Type: Cabinet Key Decision
Executive Summary: This reports seeks approval to accept a grant of £1.3m from the Government Joint Air Quality Unit (JAQU) for further development of the Liverpool Clean Air Plan and to procure expert advice to complete the Outline Business Case (OBC) and commence and complete the Full Business Case (FBC), were that advice may come to over the £500k delegated authority limit.
Information: Background The development and completion of an Outline Business Case and the development of the Full Business Case for the Liverpool Clean Air Plan work is a mandatory requirement. The work is 100% funded by Central Government and comprises of the identification of any interventions necessary to ensure that the City is compliant with the relevant EU standard for Nitrogen Dioxide in the shortest possible time.
This direction is given under Section 85 of the Environment Act 1995. It is mandatory for the Council to comply with all the associated DEFRA requirements and timescales. JAQU is a formally established joint unit working between DEFRA and the Department for Transport.
V1.1/060919 – 170919 onwards This report is with regard to a fourth tranche of funding. An initial £850k grant was accepted by Cabinet in December 2018 to commence the work. A further £150k was awarded in July 2019 for additional works. And £650k was awarded in September 2019 to support development work on the OBC.
The scale of funding reflects the complexity and extent of the work required. The funding provides for external expert advice, transportation monitoring and air quality modelling; for short-term cover to backfill roles dedicated to this work and for additional staffing capacity, for example programme management, to deliver this work.
CURRENT POSITION AND WORK REQUIRED The previous report to Cabinet, September 2019, anticipated that the provision of OBC information to JAQU and the completion of any negotiation points with JAQU by March 2020. There is however further evidence required to complete a full options analysis, including additional options as required to be modelled by JAQU.
The current programme anticipates that there will be a set of firm options which Cabinet could agree on to go out to public consultation before the end of 2020. This consultation stage would lead directly into the work for the Full Business Case (FBC). The FBC to be completed for Q4 2020/21.
The current funding award has been made in recognition of the large amount of complex data to analyse and process to find options that bring compliance to all exceedances across the City.
The specialist works to date to complete the final OBC have been carried out by AECOM consultancy engaged through the ESPO Framework and there current contract is completing. It is now recommended that the City Council test the value for money of this work by now running an open procurement for an expert contractor to:
a) deliver the remaining works to complete OBC b) deliver the analysis and design work required to complete the FBC
It is likely , though not yet certain, that either or both of these commissions will be over the £500k delegated threshold and this report requests that, to maintain the speed of working, that the decisions to go to procurement and to appoint are delegated to Directors. Recommendation: That –
(i) authority be granted to the Director of Community Services, in consultation with the S151 Officer and the City Solicitor, be authorised to accept up to £1.3m of funding from DEFRA and enter into the necessary funding agreements to do so;
(ii) the revenue budgets for 2020/21 be amended to reflect the additional income and expenditure;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.