Festival Gardens represents a significant regeneration opportunity with far reaching socio-economic benefits for the City and City Region. Delivery of this significant City region priority project will see development of housing on a site which has been derelict for over 30 years and create a sustainable new waterfront neighbourhood for South Liverpool with 1,500 new homes, supporting commercial and community uses, and high-quality areas of new and enhanced public open space. The new homes will generate circa £1.4m a year in council tax income, and bring in additional business rates. This report provides an update to Cabinet in relation to infrastructure works
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Key Officer Decisions (Key DARS), 16 pages
Background
A number of previous Cabinet Reports outline the background to the project, the most recent of which is EDR/16/19 on 6th December 2019 which gave authorisation for:
(i) Negotiation and completion of the MLA and form of Phase Lease with IMGF Developments Limited; (ii) Negotiation and completion of a GFA with Homes England (HE) and LCR CA to accept grant funding for site remediation; and (iii) Commitment of expenditure to procure a detailed remediation design, and to undertake a tender for a specialist remediation contractor.
2. Progress
To date significant progress has been made on (i) – (iii).
The Strategic Investment Fund (SIF) grant funding offer from LCR CA has been increased by £8.5m (from £18.4m to £26.94m) in order to cover site infrastructure costs in addition to remediation. This work will provide a platform for development and increased certainty of accelerated housing delivery. The MLA is drafted to ensure the conditions relating to disposals, funding and land buy-back are cognisant of the terms of the GFA.
The detailed remediation design has been instructed with procurement of a remediation sub-contractor by the Principal Contractor scheduled for April 2020, subject to completion of the GFA (which is subject to this Cabinet Authority).
3. Progress by area
Site Investigation
Cabinet Report EDR/63/19 gave details of site investigations undertaken at Festival Gardens. Since then, results of the pre-remediation trials undertaken in the Development Zone have been received, which help to reduce cost risk by providing greater certainty on material composition and quantities. The trials have also presented the opportunity to test innovative material processing techniques that would minimise off-site disposal and costs. These trials will directly inform the detailed remediation design.
Funding for the field trials was supported by pre-development SIF grant funding of £150,000 from LCR CA, acceptance of which was authorised at Cabinet EDR/95/19 on 21st February 2019. Remediation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.