CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Liverpool City Council
Cabinet 2010/21, Friday 24 January 2020

Capital Programme Monitor 2019/20 - Month 8 (November 2019)

Decided Executive 1 paper

Cabinet 2010/21 decided this item on Friday 24 January 2020. Below is the council's own wording, with the papers it was decided on.

Item236b

Resolved

Financial monitoring reports are produced on a monthly basis throughout the financial year.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 17 pages

Recommendations

That Cabinet

(i) approve the revised Five Year Capital Programme of £950.75M for 2019/20 to 2023/24; this being an amount of £274.54M for 2019/20, £201.45M for 2020/21, £183.75M for 2021/22, £150.58M for 2022/23 and £140.43M for 2023/24;

(ii) approve the revised in-year Capital Programme for 2019/20 of £274.54M, noting the increase in forecast expenditure of £8.39M compared to the Month 7 approved budget; (iii) note that the forecast of borrowing required to fund the Five Year Capital Programme is £679.47M; an increase of £5.71M compared to the Month 7 forecast;

(iv) note spend to date of £135.08M, representing 47.20% of the revised total capital budget for 2019/20 with 8/12ths of the year having elapsed;

(v) note the position regarding the prudential indicators approved as part of the Capital Strategy Statement approved by City Council on 6th March 2019; and

(vi) note the actual amount of City Council borrowing of £853M as at 30th November 2019.

Background

In March of each year the City Council approves a Capital Programme budget for the forthcoming financial year plus four additional years. The Capital Programme that was approved on 6 March 2019 set out capital spending proposals of £885M over the years 2019/20 to 2023/24 having regard to the over-arching principles set out in the City Council’s Capital Strategy Statement (DFR/07/19) and the priorities identified in the Mayoral Inclusive Growth Plan. This included borrowing of £662M over the period, including £260M for 2019/20. The cost of financing this borrowing was incorporated into the Medium Term Financial Strategy (DFR/06/19) assumptions and the approved General Fund Budget for 2019/20.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Monitor 2019/20: Month 8 (November 2019)Report 17 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Capital Programme Monitor 2019/20 - Month 8 (November 2019)This decision
  2. Corporate Risk Register Deep Dive - CR2 Capital ProgrammesAgreed
  3. Capital Programme 2019/20 - Final Outturn PositionDecided
  4. Capital Programme Monitor 2019/20 - Month 11 (February 2020)Agreed
  5. Capital Programme Monitor 2019/20 - Month 10 (January 2020)Decided
  6. Capital Programme Monitor 2019/20 - Month 9 (December 2019)Decided

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies