AI summaryCabinet approved a £4,221,542 capital budget and awarded a contract for asbestos remediation works at Redbridge and Bankview Schools in Fazakerley, to be carried out in the 2026 school summer holidays.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedTo highest scoring bidder, max £3,837,765.48 excluding VAT
Money£4,221,542 excluding VATTotal capital budget for the remediation scheme
What happens nextContract execution early April 2026Works to run during 2026 summer holiday period
Who it affectsRedbridge and Bankview Schools, Fazakerley wardPupils may come from across the city
What was decided
Cabinet approved a capital budget of £4,221,542 excluding VAT for remediation works at Redbridge and Bankview Schools. Report P2
Cabinet awarded the remediation contract to the highest scoring bidder identified in Appendix 1, at a maximum cost of £3,837,765.48 excluding VAT. Report P2, 1.13
Why
Asbestos cement material, pottery, bricks and glass were found in surface soils of the school grounds, including landscaping, playing fields and boundary bunds, posing a risk to site users. Report 1.3, 3.1
The site requires a long-term remediation solution so that children can access external play areas safely, and specialist licensed contractors are needed for asbestos work. Report 2.1, P43
What happens next
The contract is to be executed in early April 2026 so that the contractor's held tender prices and required HSE notification lead-in are maintained. Report 1.10
Works will take place during the 2026 school summer holidays and must be completed within six months, with a start by August 2026 under planning conditions. Report P55, 1.10
Further engagement with the school, local community and ward members will be undertaken by the contractor, supported by council project officers. Report 5.1
The money
£4,221,542 Total capital budget for remediation scheme (excluding VAT) Report P2
£3,837,765.48 Maximum contract cost to highest scoring bidder (excluding VAT) Report P2, P59
£383,776.55 LCC contingency at 10% of contractor cost Report P59
£2,306,213.28 Removal and disposal of hazardous materials Report P59
£755,997.67 Importation of new materials including subbases and geotextile Report P59
£495,263.19 Further associated scope items such as landscaping, fencing and drainage Report P59
£245,989.28 Preliminaries Report P59
£34,302.06 Design fees, surveys and verification works Report P59
£0.263m Residual funds available on scheme code BEERB50, to be used first
Options considered
Rejected: Do nothing. Long-term solution needed; asbestos risk to site users; sunk cost in maturing the scheme would not be realised Report P41, 3.1
Rejected: In-house provision. Asbestos remediation requires specialist licensed contractors which the council does not have in-house Report P43
Implications
Legal: The council has a statutory duty under section 22 of the School Standards and Framework Act 1998 to make premises available and defray maintenance expenses for community schools. Report 7.1
Legal: The contract is below the Procurement Act 2023 works threshold of approximately £4,477,174.17 exclusive of VAT, so the process is governed by the council's contract standing orders. Report 7.5, 7.6
Financial: The project is funded mainly through borrowing on scheme code BEERB51, with a residual £0.263m grant-funded balance on BEERB50 to be used first.
Financial: Construction market volatility is noted, with a 10% contingency factored in to allow for cost increases.
Equalities: Works take place outside term time when schools are unoccupied, so no equality impacts are anticipated and no equality impact assessment is needed at this stage. Report 4.1, P47
Other: The decision supports Pillar 2 of the Council Plan on access to inclusive, high-quality education. Report P5
Who and where
Pupils and staff of Redbridge and Bankview Schools Report P5, 4.1
Local community projects (via social value commitments from the winning bidder) Report 4.6
Local supply chain (via social value commitments) Report 4.6
Timeline
July 2015: Redbridge and Bankview schools completed under the Priority Schools Building Programme Report 1.2
Four years after Practical Completion: Asbestos cement material and other contamination discovered in surface soils Report 1.3
25/02/2025: Revised planning application for remediation approved Report 1.5
October 2025: Delegated Authority Report approved to commence procurement of a remediation contractor Report 1.8
Early April 2026: Contract execution required to maintain programme and tender prices Report 1.10
By August 2026: Works must commence under planning conditions Report P55
6 months from commencement: Remediation works to be completed Report P55
Plain English for the jargon
ACM: Asbestos Cement Material, found contaminating surface soils at the school sites
JCT Design and Build Form of Contract, 2024 Edition: Standard UK construction contract placing design development risk with the contractor
Priority Schools Building Programme: Education and Skills Funding Agency programme under which the schools were rebuilt
CLAIRE Waste Protocols: Industry protocols governing the management of contaminated waste
HSE notification: Health and Safety Executive notification required before licensed asbestos work begins
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item161
Resolved
It was resolved that Cabinet agreed to – 1. Approve the allocation of a capital budget for the sum of £4,221,542 excluding VAT, to undertake remediation works at Redbridge & Bankview Schools; and 2. Award a contract for the provision of the remediation works at Redbridge and Bankview Schools to the highest scoring bidder identified in Appendix 1 of the report, in order to facilitate the provision of physical execution of asbestos removal and disposal works at a maximum cost of £3,837,765.48 excluding VAT.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
For the reasons set out in this report, Cabinet is recommended to:
1) Approve the allocation of a capital budget for the sum of £4,221,542 excluding VAT, to undertake remediation works at Redbridge & Bankview Schools. 2) Award a contract for the provision of the remediation works at Redbridge & Bankview Schools to the highest scoring bidder identified in Appendix 1 of this report, in order to facilitate the provision of physical execution of asbestos removal and disposal works at a maximum cost of £3,837,765.48 excluding VAT.
Decision Status
This is a key decision by virtue of financial requirements as it involves incurring expenditure over £500,000.
The proposed decision impacts the Fazakerley ward within the city although pupils may come from across the city. The proposals support Pillar 2 of the Council Plan which states that ‘Everyone has access to an inclusive, high-quality education that enables them to live fulfilled, happy and productive lives’.
1. Background and Context
1.1As set out in the summary of this report, the Redbridge & Bankview school sites have been found to contain asbestos contamination in outdoor areas. Liverpool City Council (LCC) has now determined the requirements for remedial works to be undertaken in order to rectify the condition of the sites and seeks approval of Cabinet to award a contract to a supplier following the outcome of a competitive procurement exercise.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and PublicThat in the absence of any questions raised by Cabinet Members in relation to the exempt appendices, it was agreed th...
Physiotherapy Services ContractDecision – a) An award is required to maintain continuity of employee physiotherapy and Blue Badge mobility assessmen...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.