AI summaryLiverpool City Council Cabinet has agreed to award a £2,177,000 contract for highway improvement works on Wavertree High Street to the highest scoring bidder, with construction planned for 26 weeks from 18 May 2026.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedNEC4 ECC terms, 26 weeks, to highest scoring bidder
Money£2,177,000 excluding VATEstimated contract value
What happens next18th May 2026Planned construction start date
Who it affectsFour Liverpool wardsChurch, Edge Hill, Smithdown, Wavertree Village
What was decided
Cabinet agreed to award the contract to the highest scoring successful bidder named in exempt Appendix 2. Report P2, 1.16
The contract runs for 26 weeks on NEC4 ECC terms, with construction planned to commence on 18th May 2026. Report P2
The decision was identified as a key decision because the contract value exceeds £500,000. Report P4
Why
The Council has a statutory duty to maintain and improve its highways under the Highways Act 1980, and the works will help discharge that duty.
Liverpool City Region Combined Authority funding is time limited; not delivering would risk losing the grant and the Council's net zero ambitions. Report 2.2, P28
The scheme supports the Key Route Network objectives of improved reliability, accessibility, reduced congestion and decarbonisation. Report 1.3, 1.4
What happens next
The successful bidder will attend a Local Community Event hosted by Love Wavertree to explain the scheme and programme, supported by a public liaison officer. Report 5.3
Council officers will monitor delivery and budget position, with risks managed through the NEC4 ECC contract terms and a contingency allowance within the approved budget. Report 6.4, 6.5
The Council must ensure compliance with detailed grant conditions from LCRCA to avoid claw back of the funding. Report 7.7
The money
£2,177,000 (excluding VAT) Estimated value of the construction contract Report P2
£3,851,000 Current approved budget for this project (BPTFT51), funded by CRSTS KRN Levelling Up Grant Report 6.2, 6.3
£13,630,000 Total CRSTS KRN Levelling Up grant awarded by LCRCA in September 2022 Report P13, 6.3
Options considered
Rejected: Do nothing. Would lead to continued highway deterioration, loss of grant funding, more costly future interventions, and failure to meet net zero and sustainable transport objectives Report P28
Implications
Legal: Contract awarded under the Council's Highways Planned Works Framework, continuing to be governed by Public Contracts Regulations 2015 under transitional provisions of the Procurement Act 2023. Report 7.3, 7.4, 7.6
Equalities: An Equality Impact Assessment identified positive impacts from improved pedestrian crossing facilities, with some potential negative impacts on those with reduced mobility due to retained street furniture and construction phase disruption. Mitigations include letter drops and adherence to Chapter 8 standards. Report 4.2, 4.3, 4.4, 4.5
Climate: Works support the Council's ambition to become a net zero carbon city in 2030 by promoting walking, cycling and wheeling, and reducing reliance on cars for shorter journeys. Report 4.7
Financial: Forecast costs will be subject to regular review to maintain effective control of overall budget position, with a contingency allowance held within the approved budget. Report 6.4, 6.5
Risk: Highway construction contracts of this nature are subject to potential cost increases from complexity and unforeseen circumstances; risks were considered during design development. Report 6.4
Other: Social value commitments from the successful bidder include apprentice training, local SME spend, a donation in kind to a local community interest company to tackle food poverty, and STEM activities in local schools and colleges. Report P35, P36
Who and where
Residents and users in Church, Edge Hill, Smithdown and Wavertree Village wards Report P8
Pedestrians and public transport users, including those with protected characteristics Report P6, 4.2
Bus passengers and bus service operators using Wavertree High Street as a key strategic route Report P7
Local community group Love Wavertree and the wider Wavertree community Report 5.3
Local SMEs and supply chain, through the successful bidder's local spend commitment Report P35
Timeline
September 2022: Council awarded £13,630,000 CRSTS KRN Levelling Up grant by LCRCA Report P13
December 2022: Cabinet approved acceptance of the grant funding (paper CCE.18.22.23) Report P13, 6.3
November 2024: AECOM Limited appointed to develop preliminary and detailed design Report 1.10
September 2025: Briefing delivered to local community group during design development
30th September 2025: Gateway Review Group endorsed procurement strategy at Gate 2
October 2025: Design completed; construction contract issued through HPWF Lot 2 Report 1.11
20th January 2026: GRG endorsed contract award recommendation Report 1.17
17th March 2026: Cabinet decision to award the contract
18th May 2026: Planned commencement of construction works Report P2
March 2027: Revised deadline for full expenditure of the grant, agreed with LCRCA Report 1.6
Plain English for the jargon
NEC4 ECC: New Engineering Contract, Engineering and Construction Contract, a standard form of contract for construction projects
CRSTS: City Region Sustainability Settlement, a transport funding programme
GRG: Gateway Review Group, the Council's procurement governance checkpoint
HPWF: Highways Planned Works Framework, the Council's framework used to procure this contract
EqIA: Equality Impact Assessment, carried out under the Equality Act 2010
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item163
Resolved
It was resolved that Cabinet agreed to award a contract for ‘Wavertree High Street Highway Improvement Works’ construction works on NEC4 ECC terms to the highest scoring successful bidder, details of whom are contained within exempt Appendix 2 of the report for a period of 26 weeks planned to commence on 18 th May 2026. The estimated value of the contract is £2,177,000 (excluding VAT).
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
For the reasons set out in this report, Cabinet is recommended to:
1) Award a contract for ‘Wavertree High Street Highway Improvement Works’ construction works on NEC4 ECC terms to the highest scoring successful bidder, details of whom are contained within exempt Appendix 2 for a period of 26 weeks planned to commence on 18th May 2026. The estimated value of the contract is £2,177,000 (excluding VAT).
Decision Status
This is a key decision by virtue of incurring financial obligations or expenditure above £500,000.
The proposed decision will contribute to delivery of the following Council Plan pillars:
• Pillar 3 (Thriving communities): – The improvement works will enhance facilities for pedestrians and public transport users by upgrading carriageways, footways and crossing facilities. These improvements will make travel safer, accessible and more reliable whilst promoting healthier and sustainable modes of travel.
• Pillar 5 (A well-connected, sustainable and accessible city): - With Wavertree High Street serving as a key strategic route, the improvements will enhance journey time reliability and bus service efficiency, supporting better access to employment, education and essential services.
The proposed decision impacts four wards, including Church, Edge Hill, Smithdown and Wavertree Village. 1. Background and Context
1.1The Liverpool City Region Combined Authority (LCRCA) have set out three main objectives within their City Region Sustainability Settlement (CRSTS) programme for funding transport improvements, those being growth and productivity, levelling up and decarbonisation.
1.2The Key Route Network (KRN) Levelling Up project was commissioned by the LCRCA in March 2021 and forms an integral part of delivering on CRSTS objectives.
1.3Within the KRN programme, the four priority objectives to have been identified include improved reliability and resilience, improved accessibility, reduction in journey times and congestion for all users and decarbonisation through promoting sustainable modes of travel.
1.4The aim is to provide a fit-for-purpose, resilient, high quality highway network for travel by bus, walk and cycle, and to improve air quality for local communities.
Wavertree High Street Highway Improvement Works 1.5 In September 2022, the Council was awarded a grant of £13,630,000 through the CRSTS KRN Levelling Up Fund to deliver highway improvements at multiple sites. Acceptance of this funding was recorded in paper KRN Highway Maintenance Capital Funding Grant – Expenditure (CCE.18.22.23) approved by Cabinet in December 2022.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and PublicThat in the absence of any questions raised by Cabinet Members in relation to the exempt appendices, it was agreed th...
Physiotherapy Services ContractDecision – a) An award is required to maintain continuity of employee physiotherapy and Blue Badge mobility assessmen...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.