Action Tracker

Agreed Finance 1 paper

AI summaryLiverpool City Council Audit Committee notes progress on 13 outstanding actions covering disposals, cyber security, declarations of interest and council assets.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCommittee reviewed 13 outstanding actions
MoneyNot stated
What happens nextSeveral items return next meetingCouncil assets and declarations ongoing
Who it affectsAudit Committee and officersMembers and officers responsible for actions

What was decided

The action tracker was noted by the committee.

The committee received updates on 13 actions from earlier meetings, with several marked completed. Report P1, P2, P3, P4

Why

To track progress on actions agreed at previous meetings of the committee. Report P1, P2, P3, P4

What happens next

Officers will compile and circulate a detailed breakdown of internal audit recommendations and blockages to members. Report P4

The Property and Legal Teams are working together on a timeline for the publication of assets held by the council, to be shared at or before the next meeting. Report P4

Information on the contract for issuing littering fines will be provided as part of internal monitoring. Report P4

Implications

  • Governance: Several transparency and assurance items remain in progress, including officer declarations of interest, the Local Code of Corporate Governance and the publication of council assets. Report P3, P4
  • Risk: Information on the last cyber security penetration test, breach detection and recovery time, and phishing simulation failure rates was circulated to members. Report P3
  • Staffing: The committee was told the vacancy rate in ICT is being monitored, alongside consideration of whether the council risks falling behind on AI. Report P3

Who and where

  • Members of the Audit Committee Report P1, P2, P3, P4
  • Council officers responsible for declarations of interest Report P3, P4
  • The Property and Legal Teams handling council assets Report P4
  • The Council's biggest debtors, whose list may change frequently Report P2

Timeline

  • 17-Jul-25: Original date for action on disposals list Report P1
  • 06-Nov-25: Original date for actions on Neighbourhood Model and FOI routes Report P2
  • 29-Jan-26: Original date for actions on Local Code and debtors Report P2, P3
  • 19-Mar-26: Original date for actions on cyber security, health and safety, declarations, internal audit, external audit plan Report P3, P4
  • 04-Mar-26: Disposals summary issued to members by email Report P1
  • 07-Apr-26: Neighbourhood Model post investment report completed Report P2
  • 09-Mar-26: FOI briefing note issued to all members Report P2
  • 19-Mar-26: Debtors summary emailed to members Report P2
  • 14-Apr-26: Cyber security and internal audit resource information emailed to members Report P3, P4
  • April 2026: Local Code of Corporate Governance due to be reported to Constitution and Governance Committee Report P3

Plain English for the jargon

  • FOI: Freedom of Information
  • ICT: Information and Communications Technology
  • QAIP: Quality Assurance and Improvement Programme, used in internal audit
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item73

Resolved

It was agreed that the be noted.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Audit Committee

Meeting Agenda Completion Action ID Action Description Owner Status Update/Comments Date Reference Date For Unique Date action traceability to Person responsible for Actual date Clear, concise summary of the action item Drop down Progress notes or decisions identifier agreed meeting completing the action completed papers AC-2025/26 17-Jul-25 142(7) Annual External Audit Plan 2024/25. David Lord In Progress Summary information on disposals 002 Asset Register - Members to be provided with a list provided to the Audit Committee via of disposals in the last 12/18 months. email on 4 March 2026. Since this was issued, a further comment was raised by the Chair, and further work is to be completed to provide additional information.

AC-2025/26 06-Nov-25 31 Customer Annual Assurance Report Jo Richmond Completed A post investment report was 07-Apr-26 014 Members requested assurance regarding the produced, summarised and shared Neighbourhood Model – if it is successful and value with the Chair. A summary of the for money? stocktake has also been provided. The Neighbourhood model is a whole organisations shift in delivery and continues to develop. The reports evidence on the ongoing review of practice and delivery across the system. AC-2025/26 06-Nov-25 32 Update and Assurance on Response to Iolanda Puzio Completed A briefing note on member access 09-Mar-26 015 Enforcement Response to Enforcement Notice - to information was issued to all Freedom of Information Requests. members in March 26. Members not using FOI route for their queries. How can Members be informed of better routes to take to request information. AC-2025/26 29-Jan-26 43 Action Tracker Jude Green Completed Email sent on 19 March 2026 19-Mar-26 018 The Committee requested a list of the Council’s biggest debtors. The Committee were informed that a summary of this would be provided to Members prior to the next meeting, but Members should bear in mind that the list could change frequently.

AC-2025/26 29-Jan-26 52 Local Code of Corporate Governance. Karen McIlwaine In Progress Information as to dates will, where 021 The Committee suggested that dates and links to available, be provided when the documents should be provided in the Code. The Local Code is reported to the Deputy Director of Law and Governance stated that Constitution and Governance dates could be incorporated, but there is hesitation Committee in April 2026. with links as documents become outdated quite quickly. AC-2025/26 29-Jan-26 52 Local Code of Corporate Governance Karen McIlwaine Completed Report to be provided to the Audit 19-Mar-26 022 The Committee were informed that the Officer Committee as part of the agenda. Declarations of Interest will be brought back to Committee. AC-2025/26 19-Mar-26 62 ICT Assurance Report 2026 Darren Gill Completed The information was provided to 14-Apr-26 023 Members were informed that they will be provided members via email. with information on what the last penetration test on cyber security found, how quickly can we detect and contain a breach, the last time a full recovery test took place, what is the recovery time and the percentage of staff who have failed phishing simulations. Also, the vacancy rate in ICT, AI and if the Council will fall behind if we don’t use it.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Action TrackerReport 200 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 14 attended
RC
Councillor Richard CleinChair, present
JJ
Councillor John JenningsDeputy Chair, present
DC
Councillor Debbie CookeMember, present
HT
Councillor Hayley ToddMember, apologies
SE
Councillor Sam EastMember, present
JC
Councillor Jane CorbettMember, present
TO
Councillor Tricia O'BrienMember, apologies
BP
Councillor Bernard PackenhamMember, present
JM
Councillor Josie MullenMember, present
AG
Councillor Alan GibbonsMember, present
TC
Councillor Thomas CroneMember, present
PM
Paul McLoughlinIndependent Member, present

All 14 on the meeting page

On this subject at Liverpool

Search all
  1. Action TrackerThis decision
  2. Work Plan Action TrackerNoted
  3. Work Plan Action TrackerDecided
  4. Work Plan Action TrackerDecided
  5. Work Plan Action TrackerDecided
  6. Work Plan Action TrackerNoted

More from Liverpool Audit Committee

All decisions
MeetingDecisionOutcome
2 Jul 2026 Minutes of the Last MeetingIt was agreed that the minutes of the last meeting held on 23 rd April 2026, be approved as a true record. There were... Agreed Open
2 Jul 2026 Action TrackerIt was agreed that the action tracker be noted. Agreed Open
2 Jul 2026 Grants Governance Improvement Assurance ReportIt was agreed that the Assurance Report and the systems, process, controls and governance in place to ensure the effe... Agreed Open
2 Jul 2026 Significant Partnerships Assurance ReportIt was agreed that the contents of the assurance report and the areas for improvement, be noted. Agreed Open
2 Jul 2026 Internal Audit Progress ReportIt was agreed that the Annual Report and Opinion for 2025/26 be approved Agreed Open