Liverpool City Council
Audit Committee, Thursday 23 April 2026

Procurement Assurance Report

Agreed Finance 2 papers

AI summaryLiverpool City Council's Audit Committee noted assurance that procurement arrangements are up to date and fit for purpose, with third party spend of approximately £924m in 2025/26 and 62% of that spent within the Liverpool City Region.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedProcurement arrangements deemed fit for purpose
Moneyapproximately £924mThird party spend in 2025/26 to date
What happens nextProcurement Improvement Programme continuesIncluding contract management and social value roll out
Who it affectsSuppliers and directoratesAll procurement activity over £25,000

What was decided

The committee noted the assurance from the Head of Procurement and Contracts that procurement arrangements, including process and procedures, are up to date, fit for purpose and effectively communicated. Report 2.1, 4.1

Why

To give assurance that the council's procurement activity, underpinned by sound governance and procedures, is fit for purpose. Report 4.1

What happens next

Continued progress on the Procurement Improvement Programme, which sits within the Finance Improvement Programme, across workstreams including planning, the Procurement Act 2023, reporting and governance, social value, contract management, target operating model and communications. Report P3, P4, P5, P6, P7, P8, P9

Further development of social value monitoring during the roll out of the new Social Value Policy, aligned to improved contract management performance. Report P16

The money

  • £924m Third party spend in 2025/26 to date Report P11
  • £568m Spend with suppliers within the Liverpool City Region, 62% of total third party spend Report P16
  • £10m Total value of 162 exemption requests approved since 1 April 2025 Report P14
  • £14m Total value of 206 exemptions in 2024/25, for comparison Report P14
  • 10% Weighting currently applied to Social Value criteria in procurement Report P16

Options considered

  • Rejected: Not applicable, annual report Report 3.1

Implications

  • Legal: Arrangements put in place meet all legal requirements, and all procurement processes are conducted in line with Public Procurement Legislation. Report 6.1, 7.1
  • Equalities: Procurement processes are conducted in a fair, open and transparent manner. A new Sustainable Procurement Strategy approved by Cabinet in November 2025 includes Fairness and Equality as a key theme. Report 6.1, P15
  • Climate: Environment and Sustainability considerations are made in relevant procurement activity, and Environment is a key theme of the new Sustainable Procurement Strategy. Report 6.2, P15
  • Other: Social value is considered in procurement activity where relevant and proportionate, using the National TOMs Framework, and aims to leverage economic, social and environmental benefits to Liverpool. Report P16
  • Financial: No specific financial implications identified in the report. Report 6.1

Who and where

  • Council directorates responsible for procurements they need to secure their outcomes Report P3
  • The Procurement and Contracts Service, which supports all procurement activity over £25,000 Report P3
  • Suppliers within the Liverpool City Region, who received 62% of third party spend Report P16
  • Residents and communities, as social value delivery and contract performance are monitored Report P16

Timeline

  • 1 April 2025: Start of the reporting period for exemption request figures Report P14
  • July 2025: Contract Standing Orders updated to include references to the Procurement Act 2023 and Provider Select Regime Report P10
  • November 2025: New Sustainable Procurement Strategy approved by Cabinet Report P15
  • February: New Social Value Policy approved by Cabinet Report P16
  • 2025/26 to date: Third party spend of approximately £924m Report P11

Plain English for the jargon

  • CSOs: Contract Standing Orders, the council's rules governing procurement
  • TOMs Framework: Themes, Outputs and Measures, a social value measurement standard developed by the Social Value Portal and used in UK procurement
  • Procurement Act 2023: New UK legislation governing public procurement, referenced in the updated Contract Standing Orders
  • Target Operating Model: A workstream of the Procurement Improvement Programme covering how procurement operates
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item86

Resolved

It was agreed that the assurance provided that procurement arrangements, including process and procedures, are up to date, fit for purpose and effectively communicated, be noted.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Audit Committee

Recommendations

For the reasons set out in this report, Committee is recommended to:

2.1Note the assurance provided in this report that the Head of Procurement and Contracts has provided that procurement arrangements, including process and procedures, are up to date, fit for purpose and effectively communicated.

1. Background and Context 3.1 The annual Procurement Statement provides assurance as to the effectiveness of the Council’s procurement arrangements. Of note: 3.1.1 Each Directorate is accountable for the procurements that they need to secure the outcomes they are responsible for. The Procurement & Contracts Service is accountable for the provision of professional support for all procurement activity with a contract value more than £25,000. 3.1.2 The Council has continued to progress the Procurement Improvement Programme which is a part of the Finance Improvement Programme. The workstreams included are:

• Procurement Planning

• Procurement Act 2023 • Reporting & Governance

• Social Value

• Contract Management

• Target Operating Model

• Communications

3.1.3 The Council’s Contract standing Orders (CSO’s) were updated in July 2025 to include references to the Procurement Act 2023 and Provider Select Regime. The guidance documentation that was developed to help service areas better understand the CSO’s and in-particular roles and responsibilities have also been.

3.1.4 Third party spend in 2025/26 to date was approximately £924m.

3.1.5 Regarding compliance:

i. There have been no successful procurement challenges in the period to which this report relates.

ii. Since 1 April 2025, 162 exemption requests have been approved, with a total value of £10m, compared with 206 exemptions totalling £14m in 2024/25. This represents a relatively low proportion of the overall contracted spend.

3.1.6 In November 2025 a new Sustainable Procurement Strategy was approved by cabinet. Key themes captured in the new strategy include: i. Fairness & Equality ii. Environment iii. Society and Economic Growth iv. Compliance & Improved Service v. Leadership

3.1.7 A new Social Value Policy was approved by Cabinet in February. The policy provides a clear, consistent and mandatory framework for embedding social value across commissioning and procurement activity. Social value is considered in all the Council’s procurement activity where relevant and proportionate. Currently a 10% weighting is applied to Social Value criteria. The council currently measure social value commitments against the National TOMs Framework (Themes, Outputs & Measures) developed by the Social Value Portal. The Framework started as a solution for the Social Value Act and has evolved into a social value measurement standard across the UK. Monitoring delivery remains a key area of improvement that will be developed during the roll out of the social value policy aligned to improved contract management performance. 3.1.8 Spend with suppliers within the Liverpool City Region was £568m which is 62% of total third party spend. This is an increase of 4% on 2024/25.

Reasons for the recommendations

4.1To give assurance that the Council’s procurement activity, underpinned by sound governance and procedures, is fit for purpose.

Alternative options

3.1Not applicable this is an annual report.

4. Impact of the Decision

Equality and Diversity

6.1All the Council’s procurement processes are conducted in a fair, open, and transparent manner in line with Public Procurement Legislation.

Environment and Sustainability

6.2Considerations are made in relevant procurement activity.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
for Procurement Assurance ReportAppendix 1 263 KB Download
PDF
Procurement Assurance ReportReport 155 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 14 attended
RC
Councillor Richard CleinChair, present
JJ
Councillor John JenningsDeputy Chair, present
DC
Councillor Debbie CookeMember, present
HT
Councillor Hayley ToddMember, apologies
SE
Councillor Sam EastMember, present
JC
Councillor Jane CorbettMember, present
TO
Councillor Tricia O'BrienMember, apologies
BP
Councillor Bernard PackenhamMember, present
JM
Councillor Josie MullenMember, present
AG
Councillor Alan GibbonsMember, present
TC
Councillor Thomas CroneMember, present
PM
Paul McLoughlinIndependent Member, present

All 14 on the meeting page

More from Liverpool Audit Committee

All decisions
MeetingDecisionOutcome
2 Jul 2026 Minutes of the Last MeetingIt was agreed that the minutes of the last meeting held on 23 rd April 2026, be approved as a true record. There were... Agreed Open
2 Jul 2026 Action TrackerIt was agreed that the action tracker be noted. Agreed Open
2 Jul 2026 Grants Governance Improvement Assurance ReportIt was agreed that the Assurance Report and the systems, process, controls and governance in place to ensure the effe... Agreed Open
2 Jul 2026 Significant Partnerships Assurance ReportIt was agreed that the contents of the assurance report and the areas for improvement, be noted. Agreed Open