Risk Management Update

Noted Finance 2 papers

AI summaryThe Audit and Risk Management Committee received and noted the risk update [D]. It records 12 corporate risks and 15 unchanged departmental red risks, with quarterly oversight continuing [P18] [P27] [P12].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedRisk Management Update [P1]
MoneyNot stated
What happens nextQuarterly risk reporting [P12]Corporate and red departmental risks [P12]
Who it affectsCouncil risk oversight [P1]Audit and Risk Management Committee [P1]

What was decided

The Audit and Risk Management Committee received the Risk Management Update and noted its contents.

The corporate risk register remained at 12 risks, with four Red and eight Amber. One risk increased in score, and all corporate risks had a risk appetite set. Report P4, P18

Two corporate risks had been drafted pending confirmation. The 15 departmental red risks had no new entries or changes in level or score. Report P4, P27

Why

The update supports delivery of all six Corporate Plan outcomes and statutory obligations by identifying and managing risks in line with business objectives. Report P2

Quarterly reporting gives the committee information to monitor and oversee the council's risk management. Report P12

The report and appendices are intended to assure the committee that the council's risks are being handled effectively. Report P29

What happens next

People Change Readiness and Organisational Effectiveness will be finalised after feedback, added to the corporate risk register and given a risk appetite. Report P25

The Executive Leadership Board will receive an update, followed by quarterly reporting to Policy and Resources Committee and Corporate Services Committee. Report P25

A review of the Chief Officer Risk Management Group's terms of reference is under way. Senior leaders will undertake risk management training in Q1 2026/27. Report P7, P8

Implications

  • Other: Strategic implications: reporting is in line with the CoLC Corporate Risk Management Strategy. Report P28
  • Financial: Transformation fund investment has been received for Gartner support over two years to advance the council's Risk Culture work. Report P28
  • Staffing: Resource implications: none applicable. Report P28
  • Legal: Legal implications: none applicable. Report P28
  • Risk: Risk implications: none applicable. Report P28
  • Equalities: Equalities implications: none applicable. Report P28
  • Climate: Climate implications: none applicable. Report P28
  • Other: Security implications: none applicable. Report P28

Who and where

  • Audit and Risk Management Committee Report P12
  • City of London Corporation Report P18
  • Council staff and senior leaders Report P8, P25
  • Departments and risk coordinators Report P11
  • Chief Officer Risk Management Group Report P7, P13
  • Executive Leadership Board Report P8, P25
  • Policy and Resources Committee and Corporate Services Committee Report P25
  • Gartner, for Risk Culture support Report P28

Timeline

  • 17 February 2026: The Chief Officer Risk Management Group reviewed the risk registers and considered two proposed corporate risks. Report P13, P25
  • 3 March 2026: The corporate risk summary recorded the current position of 12 risks. Report P25
  • Q1 2026/27: Senior leaders will undertake risk management training. Report P8
  • ongoing quarterly basis: Policy and Resources Committee and Corporate Services Committee will receive reports on the proposed risks. Report P25
  • 30-Mar-2026: Target date for the Housing Revenue Account risk. Report P26
  • 31-Jul-2026: Target date for the Protective Security risk. Report P26
  • 31-Oct-2026: Target date for the Information Security risk. Report P26
  • 23/03/2026: The Audit and Risk Management Committee considered the Risk Management Update and resolved to receive it. Report P1

Plain English for the jargon

  • CORMG: Chief Officer Risk Management Group, which oversees risk management actions, decisions and outcomes [P13].
  • ELB: Executive Leadership Board, which receives risk updates and reporting [P8] [P25].
  • RMF: Risk Management Forum, which supports the sharing of risk management practice [P9].
  • RAG rating: Red, Amber and Green categories used in the risk tables [P14].
  • Risk appetite: A committee setting for each proposed corporate risk [P25].
  • Ideagen: The risk management software used to record and report risk [P11].
  • Corporate risk register: The register of 12 corporate risks [P18].
  • Departmental red risks: Departmental risks rated Red, of which there are 15 [P27].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

RESOLVED, That the report be received and its contents noted. ... view the full minutes text for item 8.
Word for word from the decision London Corporation published for this meeting. Source: democracy.cityoflondon.gov.uk

Follow this further

Built from London Corporation's papers

What the report saysPro

Report to Audit and Risk Management Committee, 7 pages

City of London Corporation Committee Report Committee(s): Dated: Audit and Risk Management Committee – For 23/03/2026 Information Subject: Public report: Risk Management Update For Information

This report supports the successful delivery of all Corporate Risk Management six Corporate Plan outcomes and our statutory obligations through identifying and managing risks in line with our business objectives. Does this proposal require extra revenue and/or No capital spending? If so, how much? N/A What is the source of Funding? N/A Has this Funding Source been agreed with the N/A Chamberlain’s Department? Report of: Dionne Corradine, Chief Strategy Officer Report author: Olivia Plunkett, Corporate Strategy Officer

Summary Since the last report to Committee in January 2025, the City Corporation has continued to strengthen its internal risk governance and organisational understanding of risk. This includes reinforcing the role of the Chief Officer Risk Management Group (CORMG) and building senior-level capability through the design of bespoke risk management training for the Executive Leadership Board. Work also continues to ensure the corporate risk register reflects organisational priorities, with two new corporate risks considered at an extraordinary CORMG session in February. The summary corporate and top red departmental risk register are available at para 14 and appendix 1 respectively. Risk appetite for corporate risks is outlined in Appendix 2.

Recommendation(s) Members are asked to note: • This report and the corporate risk summary at para 14 and the top red departmental risk register summary attached at Appendices 1. Risk appetite for corporate risks is outlined in Appendix 2. • That since the previous update: o The number of corporate risks has remained at 12 with one score change. o Two new corporate risks have been drafted, once confirmed these will be added to the register and go to have risk appetite set o The number of departmental red risks has remained at 15 with no score changes. o All corporate risks have a set risk appetite.

Main Report Risk Activity – Process and Culture

1. Active engagement has commenced to assess the evolving geopolitical environment and to anticipate its implications and ensure these are reflected within our risk landscape.

2. Work continues to improve our risk governance arrangements, with a particular focus on ensuring that Chief Officer Risk Management Group (CORMG) operates as a robust advisory and challenge function. To support this, a comprehensive review of the Group’s Terms of Reference is underway, including strengthening the Group’s decision-making focus and reinforcing the alignment with the Executive Leadership Board (ELB) and the Risk Management Forum (RMF). We are further working with Committees (e.g., Corporate Services Committee) to ensure risk is appropriately reflected in Committee Terms of Reference.

3. To ensure a strong understanding of risk at the top of the organisation, Senior Leaders across ELB, CORMG, and Heads of Profession will undertake risk management training in Q1 2026/27, with a focus on improving risk-based decision-making, collective ownership of mitigation delivery, and the interaction between risk appetite and prioritisation. Risk updates will also be incorporated into the regular ELB reporting that brings together key data sets across the organisation to present a comprehensive overview, reinforcing risk as a key driver in corporate planning and performance.

4. Our commitment to sharing best practice and fostering a learning mindset in risk management continues. This is being supported at the upcoming RFM where Independent Deputy Chair Gail Le Coz will share insights on risk management, giving coordinators exposure to external perspectives.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
20260323_Appendix 1_Top Red Departmental RisksAppendix 5 pages Download
PDF
Risk Management UpdateReport 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at London Corporation

Search all
  1. Risk Management UpdateThis decision
  2. Annual Report of the Audit and Risk Management CommitteeAgreed
  3. Risk Management UpdateNoted
  4. Risk Management Strategy 2024-2029 - Annual Review (Year 2)Noted
  5. Audit and Risk Management CommitteeApproved
  6. Recruiting External Representatives to the Audit & Risk Management CommitteeDecided

More from London Corporation Audit and Risk Management Committee

All decisions
MeetingDecisionOutcome
6 Jul 2026 MinutesThat the public minutes and non-public summary of the previous meeting held on 11 May 2026 be agreed as a correct rec... Agreed Open
6 Jul 2026 Outstanding Actions of the CommitteeThat the report be received, and its contents noted. ... view the full minutes text for item 4. Noted Open
6 Jul 2026 Committee Work ProgrammeThat the report be received, and its contents noted. ... view the full minutes text for item 5. Noted Open
6 Jul 2026 Annual Report of the Audit and Risk Management CommitteeAgreed the 2025/26 Annual Report of the Audit and Risk Management Committee (Appendix 1) for onward submission to the... Agreed Open
6 Jul 2026 Risk Management UpdateNoted this report and the corporate and red departmental risk registers summaries contained within this report and at... Noted Open