Risk Management Strategy 2024-2029 - Annual Review (Year 2)

Noted Finance 2 papers

AI summaryCity of London Corporation's Audit and Risk Management Committee noted the Year 2 review and FY2026-2027 priorities, which focus on stronger risk culture, earlier identification of emerging risks and regular reports for senior leaders. No extra revenue or capital spending was required.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedYear 2 review and updated FY2026-2027 action plan
MoneyNo extra spendingFunding source recorded as N/A
What happens nextFour FY2026-2027 priority activitiesWork shifts from development towards risk management maturity
Who it affectsCity of London CorporationRisk management supports all corporate risks and core strategies

What was decided

The Audit and Risk Management Committee noted the report, which included the FY2026-2027 strategic priorities and updated strategy action plan. Report P9

Why

Findings drew on officer engagement, a survey made available to all officers, corporate risk deep dives with Chief Officers, sessions with departmental risk coordinators, Internal Audit findings and learning events. Report P10

Overall risk management improved through stronger engagement, more regular committee reporting and greater integration into daily business. Report P11

Risk maturity varied across the organisation. More proactive management was needed to identify emerging risks earlier and improve horizon scanning. Report P11

What happens next

Carry out the four priority activities identified for FY2026-2027. These include strengthening risk culture and anticipating operating changes and unforeseeable events. Report P6, P12

Use an enhanced engagement model to deepen partnership and create clear ownership across the risk landscape. Provide regular, insight-led reports to the Senior Leadership Team (SLT) and Executive Leadership Board (ELB) to support decisions and prioritisation. Report P12

Continue the annual review so progress remains aligned with the strategy's objectives. Report P5

Options considered

  • Chosen: Note the report, FY2026-2027 strategic priorities and updated strategy action plan Report P9

Implications

  • Risk: The strategy, Risk Management Policy and Risk Appetite Statement are key elements of the corporate governance and internal control framework. They ensure appropriate and comprehensive management of all City Corporation risks. Report P13
  • Financial: The proposal required no extra revenue or capital spending. Its funding source was recorded as N/A. Transformation Fund investment was received to engage Gartner over two years to advance risk culture work. Report P3, P4, P13
  • Legal: Legal implications were recorded as none. Report P13
  • Staffing: Resource implications were recorded as none. Report P13
  • Equalities: Equalities implications were recorded as none. Report P14
  • Climate: Climate implications were recorded as none. Report P14
  • Other: Security implications were recorded as none. Report P14
  • Other: The strategy supports the Corporate Plan 2024-2029 and statutory Management obligations. It aligns with the People Strategy 2024-2029, Digital, Data and Technology Strategy 2024-2029 and corporate transformation. Report P2, P13

Who and where

  • City of London Corporation Report P2, P13
  • Audit and Risk Management Committee Report P1, P9
  • Officers across the organisation Report P10, P12
  • Senior Leadership Team and Executive Leadership Board Report P12
  • Chief Officers and departmental risk coordinators Report P10

Timeline

  • 13 May 2024: The Audit and Risk Management Committee endorsed the strategy. Report P5, P17
  • FY2025- 2026: Appendix 1 presented the Year 2 annual review. Report P16
  • 11 May 2026: The committee considered the annual review and noted the report. Report P1
  • FY2026-2027: Four priority activities were identified and the strategy action plan was updated. Report P6, P9

Plain English for the jargon

  • Risk management: Identifying and managing risks in line with business objectives.
  • Risk maturity: How developed core risk practices are, which differs across the organisation.
  • Risk deep dives: Reviews of corporate risk undertaken with Chief Officers.
  • Horizon scanning: Looking earlier for changes in the operating environment and emerging risks.
  • Insight-led reporting: Regular reporting used to inform leadership decisions and prioritisation.
  • Risk Appetite Statement: A key part of the organisation's approach to taking and managing risks.
  • SLT: Senior Leadership Team.
  • ELB: Executive Leadership Board.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16

Resolved

RESOLVED , that the report be noted. ... view the full minutes text for item 16.
Word for word from the decision London Corporation published for this meeting. Source: democracy.cityoflondon.gov.uk

Follow this further

Built from London Corporation's papers

What the report saysPro

Report to Audit and Risk Management Committee, 3 pages

City of London Corporation Committee Report Committee(s): Dated: Audit and Risk Management Committee 11 May 2026

Subject: Public report: Risk Management Strategy 2024-2029 – Annual Review For Information (Year 2) This report supports the successful delivery of all six Corporate Risk Corporate Plan outcomes and our statutory Management obligations through identifying and managing risks in line with our business objectives.

Does this proposal require extra revenue and/or No capital spending?

If so, how much? N/A What is the source of Funding? N/A Has this Funding Source been agreed with the N/A Chamberlain’s Department? Report of: Dionne Corradine, Chief Strategy Officer Report author: Olivia Plunkett, Corporate Strategy Officer

Summary The City of London Corporation’s Risk Management Strategy 2024-2029 was endorsed by the Audit and Risk Management Committee in May 2024 and is reviewed annually to ensure progress remains aligned with its objectives. Year two focused on consolidating and maturing core risk management practices, embedding risk into strategic decision-making, improving the quality and use of risk data, and rolling out the risk appetite approach, supported by increased internal and external engagement.

Positive progress towards the strategy objectives was observed, as well as areas for further improvement. To support this, four priority activities have been identified for FY2026-2027. The full annual report and the updated strategy action plan are available in appendix 1.

Recommendation(s)

Members are asked to:

• Note the report (at appendix 1) • Note the strategic priorities for FY2026-2027 and updated strategy action plan. Main Report

1. The findings set out in the Risk Management Strategy 2024-2029 Year 2 annual report were informed by ongoing engagement with officers (including through the Chief Officer Risk Management Group and Risk Management Forum), the annual Risk Management Strategy survey (made available to all officers), corporate risk deep dives with Chief Officers, increased one-to-one sessions with departmental risk coordinators, Internal Audit risk related findings, and professional development and external learning events.

2. The key findings were that: • Risk management has improved overall, with stronger engagement, more regular committee reporting, and greater integration into day-to-day business, and a shift towards a more thematic view of risk. • Risk maturity varies across the organisation, with good practice in some areas with a need for stronger foundations in others. • There is space for development of on proactive risk management, including earlier identification of emerging risks and improved horizon scanning.

3. These findings will be reflected in year three of the strategy, with the focus shifting from development to maturity, prioritising: • Strengthening consistency of risk culture across the organisation • Anticipating changes in our operating environment and adapting to unforeseeable events with pace and consideration • Embedding an enhanced engagement model that deepens partnership and creates a culture of clear ownership across the risk landscape • Providing regular, insight‑led reporting to the Senior Leadership Team (SLT) and Executive Leadership Board (ELB) to inform decision making, including prioritisation. Corporate & Strategic Implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
_Risk Management Strategy Annual Report_ 2025-26Appendix 1 9 pages Download
PDF
Risk Management Strategy 2024-2029: Annual Review (Year 2)Report 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at London Corporation

Search all
  1. Risk Management Strategy 2024-2029 - Annual Review (Year 2)This decision
  2. Annual Report of the Audit and Risk Management CommitteeAgreed
  3. Risk Management UpdateNoted
  4. Audit and Risk Management CommitteeApproved
  5. Risk Management UpdateNoted
  6. Recruiting External Representatives to the Audit & Risk Management CommitteeDecided

More from London Corporation Audit and Risk Management Committee

All decisions
MeetingDecisionOutcome
6 Jul 2026 MinutesThat the public minutes and non-public summary of the previous meeting held on 11 May 2026 be agreed as a correct rec... Agreed Open
6 Jul 2026 Outstanding Actions of the CommitteeThat the report be received, and its contents noted. ... view the full minutes text for item 4. Noted Open
6 Jul 2026 Committee Work ProgrammeThat the report be received, and its contents noted. ... view the full minutes text for item 5. Noted Open
6 Jul 2026 Annual Report of the Audit and Risk Management CommitteeAgreed the 2025/26 Annual Report of the Audit and Risk Management Committee (Appendix 1) for onward submission to the... Agreed Open
6 Jul 2026 Risk Management UpdateNoted this report and the corporate and red departmental risk registers summaries contained within this report and at... Noted Open