That an allocation of £2.7m towards the cost of proposed schemes (as outlined in the Part II appendix of the report of Corporate Management Team) in order to provide a range of new, high quality affordable housing schemes across the borough, in partnership with various housing associations until 2011/12, subject to the relevant planning permission being granted (where applicable), be agreed.
Word for word from the decision Maidstone published for this meeting.Source: meetings.maidstone.gov.uk
1.2.2 The council has identified high levels of housing need both through its Housing Needs Survey 2005, which identified an annual affordable housing shortfall of 962 units, and from 3,161 applicants on the housing register as at 23rd June 2009. In order to meet this need in part the council agreed through its Housing Strategy and as a key priority, to enable the delivery of decent, good quality housing that people can afford.
D:\moderngov\data\published\Intranet\C00000146\M00000369\AI00002804\CabinetReportAffordableHousingCapitalExpenditure0.d ocx 1.2.3 On 21 May 2009, Cabinet reviewed proposals to determine the level and distribution of capital resources required for the delivery of the council’s contribution to the Maidstone Sustainable Communities Strategy (SCS), delivery of the council’s Strategic Plan and operational business requirements for the period 2009-10 to 2011/12.
1.2.4 Cabinet agreed the allocation of £6.3m capital resources for housing for the period 2009-10 to 2011-12. This report provides an update on those capital resources and proposes a number of new affordable housing schemes for investment, in order to allocate some of the uncommitted funds. This also helps to shape the programme for delivery during the period 2009-10 to 2011-12.
1.2.5 A total of 8 schemes have been identified which are considered the most deliverable at this stage. The housing associations are seeking a contribution from the council in order to make the proposed schemes viable. There are 5 schemes which are forecast to start on site by the end of 2009-10, with the remaining 3 schemes forecast to start on site early 2010-11. Further details regarding each specific new scheme proposal are provided below.
1.2.6 The existing committed schemes and new scheme proposals, result in a total expenditure of £5.7m leaving £600k uncommitted within the programme. There are other planned schemes under negotiation at present, most notably with Maidstone Housing Trust (MHT), which might require further investment from the council.
1.2.7 There is an urgency to secure funds against schemes due to increasingly limited funds available from the Homes and Communities Agency (HCA) for 2009/10 and 2010/11. Confirmation of allocations available from the council will give the housing associations the assurance they seek to be able to progress with their schemes, and enable them to submit bids to the HCA for approval in a timely fashion.
1.3Bowling Green, Parkwood (18 units)
1.3.1 The scheme has full planning consent for 18 bungalows (10 two-beds and 8 one-beds) on the former bowling green site at Parkwood. All of the properties will be available for social rent. MHT are proposing to start on site in September 2009, in anticipation of the completion of the land transfer with the council.
D:\moderngov\data\published\Intranet\C00000146\M00000369\AI00002804\CabinetReportAffordableHousingCapitalExpenditure0.d ocx 1.4 Armstrong Road & Park and Ride Site (95 units + 35 units)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.