(1) That the progress on the office accommodation projects be noted; (2) That approval is given to the funding of £65,000 for the first phase of the optimization of Maidstone House in connection with the Council’s short/medium term accommodation; (3) That approval is given to the funding of £10,000 to complete investigations into the alternative use of the Gateway; and (4) That the potential requirement of £165,000 for the second phase of the optimization of Maidstone House be noted.
Word for word from the decision Maidstone published for this meeting.Source: meetings.maidstone.gov.uk
1.3.1 In August 2014, Cabinet agreed the strategy and the scope of the work planned for the short/medium term and the long term provision of the Council’s office accommodation. The short/medium term strategy was being driven by the objective of implementing the break clause in the lease for the first floor of Maidstone House in October 2016; with the long term strategy being driven by the lease end date for the rest of Maidstone House and the Gateway in October 2023. 1.3.2 Cabinet agreed initial funding of £90,000 for the appointment of a specialist advisor in connection with formulating the long term strategy, the purchase of desk/meeting room booking software and the appointments of a space planner and a project manager to develop the workstreams for the short/medium term strategy.
1.3.3 In December 2014, Cabinet also agreed funding of £250,000 to proceed with the establishment of an Enterprise Hub on the first floor of the Gateway building. This, and the decision to amalgamate the contact centre with the Gateway team into the Gateway building, and the proposal to provide accommodation for the West Kent Commissioning Group have had an impact on the short/medium term strategy.
1.3.4 The initial funding of £90,000 has been supplemented by further funding of £106,500, agreed by Cabinet in February 2015, to enable advancement of the project through to the end of 2014/15.
Progress to date
1.3.5 Montagu Evans has been appointed to provide specialist advice in connection with the long term accommodation strategy. A three stage approach has been developed. The first stage, ascertaining accommodation requirements, has been completed, and has involved officers and a cross party group of Members. The next stage, site identification and evaluation, is nearing completion and the final stage, proposed delivery strategy and financial implications, will be completed in April.
1.3.6 Intus Ltd has been appointed as the space planner and following rigorous occupancy surveys of the existing accommodation and consultation with staff presented initial ideas for the new layouts of each floor in February. Final layouts are currently being worked on. The space planning brief assumed the release back to the Mall of the first floor of Maidstone House and was extended to include the creation of the Enterprise Hub on the terrace, the relocation of the contact centre to the Gateway and office space for the West Kent Clinical Commissioning Group. This exercise will also provide a blueprint for the Council’s future spatial requirements.
1.3.7 Part of the first floor is currently licensed to Mid Kent College as a training facility. This arrangement ends on 30 September 2015.
1.3.8 Investigations into suitable desk/meeting room software are continuing. This will enable a more effective and efficient use of desk space and meeting rooms in Maidstone House and meeting rooms in other Council accommodation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.