That the boilers and associated pipework and controls, electrical switchgear and mains distribution panels are replaced and enabling health and safety works are carried out, all as identified in the report by Mervyn Hayes Consultants set out in Appendix A to the joint report of the Assistant Director of Regeneration and Cultural Services and the Theatre and Events Manager and at the approximate costs set out in that Appendix, plus a contingency of 10%. 2. That the necessary urgent works to the HAC are funded from balances, and the monies recouped through either reduced subsidy and/or increased income.
Word for word from the decision Maidstone published for this meeting.Source: meetings.maidstone.gov.uk
1.4.1 The boilers, associated pipework, controls, air handling systems and electrical installations at the Hazlitt Arts Centre are known to be coming towards the end of their useful life and one boiler has already failed. Maintenance costs and the risk of failure are also increasing. Consultants were appointed to advise on the most efficient way of ensuring the business of the Hazlitt Arts Centre continues and to examine ways of improving energy efficiency and comfort levels.
1.4.2 In the course of the investigation into the operating systems at the HAC the contractor identified potential failure and capacity issues with the main electrical intake board which could necessitate shutting the building down for electrical work to take place which could affect business continuity. There are health and safety concerns about the risk to contractors instructed to work on this equipment. It is therefore recommended that the main board is replaced as part of this work.
1.4.3 The consultant’s report confirmed that after over fifteen years of service, in addition to the boiler that has already failed, the remaining three are also at risk of failing and that there is a strong possibility that one or more could fail this winter. The existing boilers are no longer in production and, as a result, it has not been possible to find any replacement parts for the boiler that has failed. Therefore, an efficient heating solution needs to be in place before the heating is turned on for the busy winter season, which includes the pantomime.
1.4.4 The consultant also identified potential problems with the existing pipework and radiators which are over thirty years old. The system was flushed out in the summer of 2010 in the hope of improving heating efficiency, however, this has resulted in exposing weaknesses in the pipework causing leaking in some areas. It is therefore considered expedient to replace the elderly pipework and radiators at the same time as the boiler plant to ensure maximum efficiency of the new system. Additionally modern boilers are recognised to be extremely sensitive and debris from the old pipework could seriously compromise the new equipment.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.