CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Maidstone Borough Council
Cabinet., Wednesday 13 August 2014 at 6.30pm

Budget Monitoring 1st Quarter

Noted Executive 4 papers

Cabinet. noted this item on Wednesday 13 August 2014. Below is the council's own wording, with the papers it was decided on.

Item33

Resolved

That the satisfactory revenue position at the end of the first quarter of 2014/15 be noted. 2. That the proposals for slippage and re-profiling in the capital programme to 2015/16, including the specific allocations for the local growth fund approved schemes as set out in paragraph 1.7.5 of the report of the Director of Regeneration and Communities, be agreed. 3. That increased income from development control applications be utilised to fund additional appeals costs, as set out in paragraph 1.4.10b of the report of the Director of Regeneration and Communities. 4. That £230,000 of the additional income arising from the return of the unused top slice for the business rates safety net (£198,000) and the repayment from HMRC (£42,825) for over declared VAT in relation to car parking overpayments be utilised as follows: Office accommodation project 90,000 Land charges fee refunds 120,000 Economic Development business database 230,000 5. That agreement be given to the temporary virement of £50,000 from the Leader’s contingency to employ an Information Manager for 12 months, as detailed in paragraph 1.4.8 of the report of the Director of Regeneration and Communities. 6. That the detail in the report on the collection fund, general fund balances and treasury management activity be noted.
Word for word from the decision Maidstone published for this meeting. Source: meetings.maidstone.gov.uk

Follow this further

Built from Maidstone's papers

What the report saysPro

Report to Cabinet.

MAIDSTONE BOROUGH COUNCIL

CABINET

WEDNESDAY 13 AUGUST 2014

REPORT OF DIRECTOR OF REGENERATION AND COMMUNITIES

Report prepared by Ellie Dunnet

1. BUDGET MONITORING 1ST QUARTER

1.1Issue for Decision

1.1.1 To consider the capital and revenue budget and expenditure figures for the first quarter of 2014/15.

1.1.2 To consider other financial matters with a material effect on the medium term financial strategy or the balance sheet.

1.2Recommendation of Head of Finance & Resources

1.2.1 It is recommended that Cabinet:

a) Note the satisfactory revenue position at the end of the first quarter of 2014/15;

b) Agree the proposals for slippage and re-profiling in the capital programme to 2015/16 including the specific allocations for the local growth fund approved schemes as set out in paragraph 1.7.5;

c) Agree to utilise increased income from development control applications to fund additional appeals costs, as set out in paragraph 1.4.10b of this report;

d) Agree to utilise £230,000 of the additional income in accordance with the proposals set out in paragraph 1.4.9d of this report;

e) Agree to the temporary virement of £50,000 from the Leader’s contingency to employ an Information Manager for 12 months, as detailed in 1.4.8 of this report;

f) Note the detail in the report on the collection fund, general fund balances and treasury management activity. 1.3 Reasons for Recommendation

1.3.1 The Director of Regeneration & Communities is the Responsible Financial Officer, and has overall responsibility for budgetary control and financial management. However in practice day to day budgetary control is delegated to service managers, with assistance and advice from their director and the finance section. This report advises and updates the Cabinet on the current position with regards to both revenue and capital expenditure against the approved budgets, and also includes sections on Collection Fund performance and Treasury Management performance.

1.3.2 The report uses a number of terms that may require definition and a glossary of terms is given in section 1.14.3 of the report.

1.4Revenue

1.4.1 The budget used in this report is the agreed estimate for 2014/15 including the carry forward resources agreed by Cabinet in May 2014. Actual expenditure to June 2014 includes all major accruals for goods and services received but not paid for by the end of the quarter.

1.4.2 An analysis that is summarised by Portfolio, of the full year budget, the profiled budget to June 2014 and expenditure to June 2014 is attached as Appendix A. The financial analysis is based on direct expenditure only. This removes the influence of internal recharges and accounting adjustments upon the variance analysis. An indicative projected year end outturn figure is also shown.

1.4.3 Appendix A shows that actual spend is £432,516 less than the budget at the end of the first quarter, including one off receipts of £240,000 as set out in paragraph 1.4.9d. A detailed analysis of the figures at cost centre level shows 135 out of a total of 230 cost centres are currently reporting actual spend less than budget. Subject to the proposed use of the one off income, the projected outturn at 31 March 2015 is currently £392,516.

1.4.4 Also shown at Appendix A is a subjective analysis across all services. This identifies that within the net under spend £114,618 relates to employee costs, due to continuing vacancy levels.

1.4.5 The third table at Appendix A summarises the position specifically with regard to fees and charges income. At the end of the first quarter this income is £69,560 above the target figure. It should be noted that within this total there are some areas reporting income below budget. Further details of service areas where major

D:\moderngov\data\published\Intranet\C00000146\M00002116\AI00018652\$yh1kt4wu.docx variations from budgeted fees and charges are given later in this section of the report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Revenue Budget Q1Appendix A 30 KB Download
PDF
Capital BudgetAppendix B 56 KB Download
PDF
Treasury Management Q1Appendix C 25 KB Download
PDF
Budget Monitoring 1st QuarterReport 138 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 6 attended
MA
Councillor Mrs Annabelle BlackmoreChairman, present
DB
Councillor David BurtonCommittee Member, present
MG
Councillor Malcolm GreerCommittee Member, present
SM
Councillor Steve McLoughlinCommittee Member, present
JP
Councillor John PerryCommittee Member, present
MR
Councillor Marion RingCommittee Member, present

On this subject at Maidstone

Search all
  1. Budget Monitoring 1st QuarterThis decision
  2. Report of the Director of Finance and Business Improvement - Third Quarter Budget Monitoring 2016/17Noted
  3. Report of the Director of Finance and Business Improvement - Third Quarter Budget MonitoringApproved
  4. Report of the Director of Finance and Business Improvement - Second Quarter Budget Monitoring 2016/17Noted
  5. Report of the Head of Finance and Resources - Third Quarter Budget Monitoring 2015-16Noted
  6. Report of the Head of Finance and Resources - Second Quarter Budget Monitoring 2015-16Noted

More from Maidstone Cabinet.

All decisions
MeetingDecisionOutcome
14 Apr 2015 Report of Head of Finance and Resources - Use of Potential Revenue Under Spend 2014-15That the schemes set out in Appendix A to the Report of the Head of Finance and Resources be approved and the priorit... Approved Open
14 Apr 2015 Report of the Director of Environment and Shared Service - Office Accommodation Project(1) That the progress on the office accommodation projects be noted; (2) That approval is given to the funding of £65... Noted Open
14 Apr 2015 Report of the Head of Policy and Communications - Communications and Engagement Strategy(1) That delegated authority be given to the Head of Policy and Communications, in consultation with the Leader, to m... Approved Open
14 Apr 2015 Report of the Director of Communities and Regeneration - Town Centre Visioning(1) That the Maidstone Town Centre masterplanning and delivery programme is commenced; and (2) That approval is given... Approved Open
14 Apr 2015 Report of the Planning, Transport and Development Overview and Scrutiny Committee - Review of Transport in Maidstone - Alternatives to using a Car ReportThat the SCRAIP relating to the review of ‘Transport in Maidstone – alternatives to using a Car’ be referred to the S... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies