: 1) That the Committee approved moving ahead with the process to build and maintain a comprehensive risk register as set in Section 4 and Appendix 1 to the report of the Director of Environment and Shared Services; 2) That delegated authority is given to the Chief Executive (as the accountable officer) to take operational decisions necessary for the ongoing maintenance and review of the risk register; and 3) That the Committee receive and consider bi-annual summary risk register reports for review, scheduled for January and July.
Word for word from the decision Maidstone published for this meeting.Source: meetings.maidstone.gov.uk
Policy & Resource Committee 24 June 2015 Is the final decision on the recommendations in this report to be made at this meeting? Yes
Risk Management Process Refresh Final Decision-Maker Policy & Resources Committee Lead Director or Head of Service Director of Environment and Shared Services Lead Officer and Report Author Head of Audit Partnership Classification Non-Exempt Wards affected n/a
This report makes the following recommendations to the final decision-maker: 1. Approve moving ahead with the process to build and maintain a comprehensive risk register as set out in section 4 and Appendix 1. 2. Delegate to the Chief Executive (as the accountable officer) authority to take operational decisions necessary for the ongoing maintenance and review of the risk register. 3. Agree to receive and consider biannual summary risk register reports for review, scheduled for January and July.
This report relates to the following corporate priorities: • Great People • Great Place • Great Opportunity
Timetable Meeting Date Policy and Resources Committee 24 June 2015 Council n/a Other Committee n/a Risk Management Process Refresh
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1This report leads on from a review undertaken by Mid Kent Audit of risk management processes at another authority, but noting that several of the matters raised were also relevant to Maidstone BC. While it is important to recognise that the Council’s current approach to risk management is adequate – in the sense that the external audit value for money conclusion and Head of Internal Audit opinion are both unqualified – there exists capacity to refresh the process in order to achieve efficiencies and better quality outcomes. Specifically, the revisions to the process seek to achieve:
• Increased clarity in roles and responsibilities for risk management, placing the process clearly within the scope of a named responsible director (the Director of Environment and Shared Services) and a service (internal audit). • A more uniform approach across the Council allowing for comprehensive overview of risk as it exists and evolves and consideration within the context of the Council’s operations as a whole, and • Clearly scheduled opportunities for review of risk by senior officers and members.
1.2Based on the review of risk management approaches adopted elsewhere across the public and private sectors, and consultation and workshops with Council officers and Members, the Council has developed a refreshed approach to risk management summarised in appendix I. This approach aims to realise the additional benefits of a revised process as described above within current resources (principally delivered administratively in year one by internal audit in line with the Audit Plan agreed by the Council’s Audit Committee on 30 March 2015).
1.3This report outlines the approach, inviting comment from Members, and asks their approval that it be implemented to the timescale and with the intended outcomes described.
2. INTRODUCTION AND BACKGROUND
2.1The formal definition of risk management, drawn from the HM Treasury Orange Book is: “all the processes involved in identifying, assessing and judging risks, assigning ownership, taking action to mitigate or anticipate them as well as monitoring and reporting on what has been done”. More succinctly, risk management is how the Council identifies, prioritises and deals with the risks it faces.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.