Report of the Head of Planning and Development - Results of the VISUM transport modelling
NotedPlanning6 papers
Strategic Planning, Sustainability and Transportation Committee noted this item on Wednesday 19 August 2015. Below is the council's own wording, with the papers it was decided on.
That the Committee notes the results of the transport modelling undertaken jointly by MBC and KCC and its implications for the preparation of the Integrated Transport Strategy and the Maidstone Borough Local Plan. 2. That the Committee’s broad support of the Maidstone Joint Transport Board’s recommendation dated 23 July 2015 be noted and that the Officers are requested to do further work on transport policy development.
Word for word from the decision Maidstone published for this meeting.Source: meetings.maidstone.gov.uk
Report to Strategic Planning, Sustainability and Transportation Committee
Strategic Planning, 18 August 2015 Sustainability &Transportation Committee Is the final decision on the recommendations in this report to be made at this meeting? Yes
Results of the VISUM Transport Modelling Final Decision-Maker Strategic Planning Sustainability & Transport Committee Lead Director or Head of Service Rob Jarman; Head of Planning & Development Lead Officer and Report Author Steve Clarke, Principal Planning Officer (Spatial Policy) Classification Non-exempt Wards affected All
This report makes the following recommendations to the final decision-maker: 1. That the Committee accepts the results of the transport modelling undertaken jointly by MBC and KCC and its implications for the preparation of the Integrated Transport Strategy and the Maidstone Borough Local Plan.
This report relates to the following corporate priorities: • Keeping Maidstone an attractive place for all • Securing a successful economy for Maidstone Borough
Timetable Meeting Date Strategic Planning, Sustainability and N/A Transportation Committee Results of the VISUM Transport Modelling
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1Transport is a key area of public policy for the Council (MBC) and a significant element of the emerging Local Plan. This report describes the context and analysis which has been carried out by MBC and Kent County Council (KCC), to inform the preparation of transport policy for the Borough. The Forecasting report for the Maidstone VISUM Transport Model is attached at Appendix 1 and the non-technical summary at Appendix 2.
1.2The report comprises five sections, outlining the need for a transport strategy, the wider policy context, the transport options tested, the test results, and the implications for policy formulation. Three options for the future transport network are tested using the Maidstone VISUM transport model which is jointly commissioned by MBC and KCC. The amount of development modelled was 17,381 housing units, 151,000m² of employment land and 12,100m² of retail. Councillors will note that the housing figure modelled was not the Objectively Assessed Need of 18,560.
1.3The three options are; ‘do minimum’ (DM), a highways package (DS1), and a sustainable package (DS2) and each option is tested for traffic flows, mode share and network performance. Due to the highways related nature of the model, the sustainable package is tested using a reduced number of vehicle trips by 2031 (1,395 vehicles in the AM peak and 1,351 vehicles in the PM peak) based on an assessment of Department for Transport (DfT) guidance (TAG M5.2) and taking 25% of the recommended allowance in the DfT guidance, as a proxy for the anticipated increase in walking, cycling and increased public transport use which is anticipated to result from the promotion of sustainable transport policies in the Local Plan and national and regional policy.
1.4The results are presented in tables which show how journey times, journey numbers and mode share vary according to the options. As expected, congestion is seen to increase significantly with the ‘do minimum’ option (DM), with slightly less congestion for the ‘highways package’ (DS1) which includes the construction of the ‘Leeds – Langley by-pass’ and the greatest reduction is for the ‘sustainable package’ (DS2) which includes the same local highways improvements as DS1 (except for the Leeds-Langley by-pass) and a range of sustainable transport measures implemented.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategic Planning, Sustainability and Transportation Committee at Maidstone and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.