Maidstone Borough Council
Cabinet, Wednesday 18 March 2026 at 6.30pm

River and Nature Restoration

Approved Executive 2 papers

AI summaryCabinet approves a £97,600 grant to Kent Wildlife Trust for a two-year river and nature restoration project across Maidstone Borough, plus up to £30,000 to match Environment Agency flood mitigation funding in Headcorn.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedGrants to Kent Wildlife Trust and to match Environment Agency funding
MoneyNot stated
What happens nextNot stated
Who it affectsNot stated

What was decided

Cabinet approved a £97,600 grant to Kent Wildlife Trust to deliver the river and nature restoration project set out in the report. Report P4

Cabinet approved a grant of up to £30,000 to match Environment Agency funding for flood mitigation measures in Headcorn.

Cabinet gave delegated authority to the Director of Finance and Resources, working with the Cabinet Member for Climate Transition, to conclude the legal agreements.

Why

The project aligns with the council's climate, biodiversity, and nature recovery priorities, and supports delivery of the Local Nature Recovery Strategy through the existing Nature Recovery Fund. Report P6, P9

The work is intended to tackle biodiversity decline, diffuse water pollution, increased flood risk, and habitat fragmentation across the farmed landscape, rivers, and floodplains. Report P10, P11, P12, P13, P14

Kent Wildlife Trust has experience running the existing Upper Beult and Marden farmer clusters and is well placed to act as a trusted intermediary between land managers, the council, regulators, and funders. Report P6, P15

What happens next

The Director of Finance and Resources, in consultation with the Cabinet Member for Climate Transition, will conclude the legal agreements with Kent Wildlife Trust and the Environment Agency.

Kent Wildlife Trust will recruit a dedicated Farm Cluster Officer to coordinate farmer clusters, meetings, knowledge exchange, and joint planning across the Lower Beult and Greensand Ridge. Report P29, P53

Kent Wildlife Trust will provide regular progress updates and review meetings with the council, with monitoring linked to agreed outcomes. Report P54, P55

The money

  • £97,600 Grant to Kent Wildlife Trust to deliver the river restoration project Report P63
  • £30,000 Match funding for Environment Agency flood mitigation in Headcorn (up to)
  • £39,000 Year 1 2026 Project Officer (including on-costs) Report P63
  • £39,600 Year 2 2027 Project Officer (including on-costs) Report P63
  • £4,000 Year 1 2026 Vision Development at Curtis Farm and Hammer Stream Report P63
  • £15,000 Year 2 2027 Vision Development at Curtis Farm and Hammer Stream Report P63
  • £43,000 Year 1 2026 total project costs Report P63
  • £54,600 Year 2 2027 total project costs Report P63

Options considered

  • Chosen: Approve £97,600 grant to Kent Wildlife Trust for the two-year project. To deliver the river and nature restoration partnership described in the report Report P4
  • Chosen: Approve up to £30,000 to match Environment Agency flood mitigation funding in Headcorn. To support flood mitigation measures in Headcorn
  • Chosen: Delegate authority to conclude legal agreements to the Director of Finance and Resources. To allow the agreements to be finalised in consultation with the Cabinet Member for Climate Transition

Implications

  • Financial: The council commits £97,600 to the project and up to £30,000 as match funding, with the work intended to unlock additional external funding and in-kind contributions. Report P60
  • Climate: The project is designed to contribute to the council's climate, biodiversity, and net zero commitments, including through carbon sequestration. Report P24
  • Other: Kent Wildlife Trust will work with the Environment Agency, water companies, farmers, and landowners, and may use the work to develop Biodiversity Net Gain, carbon, and ecosystem restoration credit opportunities. Report P7, P52

Who and where

  • Farmers and land managers in the Lower Beult catchment and Greensand Ridge Report P5, P20
  • Private landowners, estates, and community landholders across Maidstone Borough Report P34
  • Residents of Headcorn (flood mitigation works) Report P41
  • Existing Marden and Upper Beult farmer clusters Report P6, P32
  • Kent Wildlife Trust (project lead and grant recipient) Report P4, P52
  • Environment Agency (flood mitigation partner) Report P52
  • Volunteers and community participants in citizen science and engagement Report P48

Timeline

  • Yr 1 2026: First year of project delivery, including Project Officer costs of £39,000 and £4,000 of vision development work at Curtis Farm and Hammer Stream. Report P62, P63
  • Yr 2 2027: Second year of project delivery, including Project Officer costs of £39,600 and £15,000 of vision development work at Curtis Farm and Hammer Stream. Report P62, P63
  • 2 years: Overall proposed project duration of the Kent Wildlife Trust partnership. Report P2, P4

Plain English for the jargon

  • KWT: Kent Wildlife Trust, the project lead submitting this proposal to the council.
  • MBC: Maidstone Borough Council, the council receiving the proposal and approving the grant.
  • LNRS: Local Nature Recovery Strategy, which the council is committed to delivering in the borough.
  • NbS: Nature-based Solutions, approaches that work with natural processes to deliver environmental and climate outcomes.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item257

Resolved

That 1. A grant of £97,600 to Kent Wildlife Trust to deliver the river restoration project described in the report be approved; 2. A grant of up to £30,000 to match Environment Agency funding for flood mitigation measures in Headcorn be approved; and 3. Delegated authority be given to the Director of Finance and Resources, in consultation with the Cabient Member for Climate Transition, to conclude legal agreements with the Kent Wildlife Trust and the Environment Agency.
Word for word from the decision Maidstone published for this meeting. Source: meetings.maidstone.gov.uk

Follow this further

Built from Maidstone's papers

What the report saysPro

Report to Cabinet

Project Proposal - Supporting Farmer Clusters, Landowner Engagement, River & Nature Restoration in Maidstone Borough

Submitted by: Kent Wildlife Trust (KWT) Submitted to: Maidstone Borough Council (MBC) Proposed Project Duration: 2 years Geographical Focus: Maidstone Borough, with emphasis on developing farmer clusters in the Lower Beult River catchment and Greensand Ridge and the existing Marden farm cluster.

1. Overview

Kent Wildlife Trust (KWT) propose a two-year partnership project with Maidstone Borough Council (MBC) to deliver an integrated programme that strengthens and deepens landowner engagement and accelerates river and nature restoration across Maidstone Borough.

The project will focus on developing new farmer clusters, facilitating local farmers and land managers in the Lower Beult and the Greensand Ridge to work collaboratively at a landscape scale delivering nature recovery, water quality, climate resilience, and projects promoting greater access to nature.

Building on KWT’s extensive experience in developing and delivering the existing Upper Beult and Marden farmer clusters this proposal aligns with Maidstone Borough Council’s climate, biodiversity, and nature recovery priorities, whilst linking into a wider ‘super’ farmer cluster concept across the Low Weald from Ashford to Marden and Yalding.

KWT will provide coordination, technical advice, and partnership working to identify nature recovery opportunities at a landscape-scale that cannot be achieved through isolated actions alone. The project will also develop a suite of quick win habitat and species projects and focus on maximising KWT’s experience in securing funding to provide financial gearing to MBC’s Nature Restoration Fund. The emerging Nature-based Solutions funding opportunities which KWT have been working on for a number of years (BNG, carbon, ecosystem restoration credits etc) will also from an important part of any project.

2. Background and Rationale

MBC are committed to delivering on the Local Nature Recovery Strategy (LNRS) in the borough and has established a Nature Recovery Fund to support this. The Council are keen to promote projects which tackle:

• Declines in biodiversity across the farmed landscape, rivers and floodplains

• Pollution impacting water quality, including diffuse agricultural pollution and pollution resulting from development and the local highway network

• Increased flood risk and climate change pressures

• Habitat fragmentation limiting nature recovery

• Support for landowners and farmers in working with public bodies and delivering public goods Farmer clusters are one of the most effective ways to address these challenges through collaboration at a landscape scale to deliver greater environmental outcomes while supporting farming businesses.

KWT is well placed to facilitate this approach in Maidstone, acting as a trusted intermediary between land managers, local authorities, regulators, and funders.

3. Project Aims and Objectives

Overall Aim

To enable a coordinated, landscape-scale approach to nature recovery and river restoration in Maidstone Borough through farmer clusters, proactive landowner engagement, and targeted habitat and species focussed restoration projects.

Key Objectives:

1. Support and expand farmer clusters within the Lower Beult catchment and Greensand Ridge areas, to encourage collaborative nature restoration projects to be developed.

2. Engage and advise landowners on nature-friendly farming and land use, agri-environment schemes, and NbS (Nature-based Solutions)/natural capital opportunities.

3. Rivers, riparian tree cover and wetlands restoration working alongside SERT and their existing project with MBC to bolster landowner engagement to improve ecological condition, water quality, and natural flood management.

4. Enhance biodiversity and connectivity through maximising the impact and gearing of MBC’s Nature Restoration Fund

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enc. 1 for River and Nature RestorationReport 224 KB DownloadRead as text
PDF
River and Nature RestorationReport 102 KB Download

At this meeting

Whole meeting

Who was there

8 of 8 attended
CE
Councillor Clive EnglishCommittee Member, present
TH
Councillor Tony HarwoodCommittee Member, present
SJ
Councillor Stuart JefferyChairman, present
DN
Councillor David NaghiCommittee Member, present
ST
Councillor Stephen ThompsonCommittee Member, present
SW
Councillor Simon WalesCommittee Member, present
MS
Councillor Michael SummersgillCommittee Member, present
RR
Councillor Rachel RodwellCommittee Member, present

On this subject at Maidstone

Search all
  1. River and Nature RestorationThis decision
  2. River and Nature RestorationApproved

More from Maidstone Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 Exempt ItemsThat all items be taken in public. Decided Open
8 Sep 2026 Minutes of the Meeting held on 22 July 2026That the Minutes of the meeting held on 22 July 2026 be approved as a correct record and signed. Approved Open
8 Sep 2026 Swale Borough Local Plan Review (Regulation 19) Public ConsultationThat Maidstone Borough Council’s draft response to the Swale Borough Council Local Plan Review Regulation 19 consulta... Agreed Open
8 Sep 2026 Tunbridge Wells Borough Local Plan Review Scoping Consultation (Regulation 20)That Maidstone Borough Council’s response to the Tunbridge Wells Borough Council Local Plan Review Scoping consultati... Agreed Open
8 Sep 2026 KCC Minerals Sites Plan Consultation ResponseThat 1. The draft publication consultation response be agreed, subject to typographical edits and officers strengthen... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies