Cabinet, Wednesday 18 March 2026 at 6.30pm

Homes England Audit Results - Corbens Phase 3

Noted Executive 2 papers

AI summaryMaidstone Cabinet notes a green Homes England audit for Corbens Phase 3, one of five council-built affordable housing schemes, with no breaches found.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedGreen grade, no breaches identified
MoneyNoneNo financial commitments associated with the report
What happens nextOfficers log acknowledgementOn the Homes England Compliance Audit system
Who it affectsCorbens Phase 3 schemeFirst social rented units under council housebuilding

What was decided

Cabinet noted the Compliance Audit report results for Corbens Phase 3, as required by Homes England funding conditions. Report P4, 2.4

Why

The audit outcome, agreed by Homes England's Strategic Investment Board, was graded green, meaning no breaches were identified and no further action is needed. Report 2.4, 2.5

Homes England funding rules require the final Compliance Audit report to be brought to committee for attention. Report 2.4

What happens next

The Housing and Community Cohesion Policy Advisory Committee considered the matter on 10 March 2026, with feedback to be given to Cabinet. Report 6.2

Once agreed, officers will log into the Homes England Compliance Audit system to confirm the committee's acknowledgement. Report 7.1

Options considered

  • Chosen: Note the audit report. Report is for noting only; no options required. Report 3.1, 4.1, P18, P20

Implications

  • Other: Positive impact on the corporate priority Quality Homes for All, as the outcome continues to allow the council to deliver council housing. Report P5

Who and where

  • Maidstone Borough Council, as Homes England grant recipient and council housebuilder Report 2.1, 2.2
  • Future social tenants of Corbens Phase 3 Report P1

Timeline

  • January 2022: Officers applied to Homes England for grant funding for five council-owned development schemes. Report P1
  • August 2025: Homes England notified the council that Corbens Phase 3 would be audited for funding guide compliance. Report P1
  • 10 March 2026: Housing and Community Cohesion Policy Advisory Committee considered the matter. Report 6.2
  • 18 March 2026: Cabinet noted the Compliance Audit report results. Report P4

Plain English for the jargon

  • Compliance Audit: A Homes England review of a sample of funded schemes to check that grant conditions and contractual requirements have been met.
  • Green grade: The best Homes England audit outcome, indicating no breaches were identified and no further action is required.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item258

Resolved

That the Compliance Audit Report results for Corbens Phase 3 be noted.
Word for word from the decision Maidstone published for this meeting. Source: meetings.maidstone.gov.uk

Follow this further

Built from Maidstone's papers

What the report saysPro

Report to Cabinet

Executive summary

In January 2022 Officers successfully applied to Homes England for grant funding to assist in the delivery of five Council owned development schemes. The delivery of these affordable housing sites would see the first social rented units delivered under the Council house building program. In August 2025 Officers were notified that one of the five schemes, Corbens Phase 3, would be audited by Homes England to ensure compliance with the funding guide. This report is to share the outcome of that audit.

Purpose of report

For noting

This report makes the following recommendation to the Cabinet:

That the Compliance Audit report results for Corbens Phase 3 be noted. 1. CROSS-CUTTING ISSUES AND IMPLICATIONS

Issue Implications Sign-off Impact on This has a positive impact on corporate Head of New Corporate priorities as the outcome of this audit will Business and Priorities continue to allow Maidstone Borough Housing Council to the Quality Homes for All Development Corporate Strategy objective.

Biodiversity There are no impacts on Biodiversity and Biodiversity and and Climate Climate Change associated with this Climate Change Change report. Manager

Financial, There are no impacts on Financial, People Head of Finance People and and Planet associated with this report. Planet Staffing There are no impacts on staffing Head of New associated with this report. Business and Housing Development Legal There are no impacts on Legal associated Deputy Head of with this report, which is only for noting. Legal Partnership Information There are no impacts on personal Information Governance information (as defined in UK GDPR and Governance Data Protection Act 2018) the Council Manager processes.

Equalities There are no impacts on Equalities Equalities & associated with this report. Communities Officer Public There are no impacts on Public Health Health Policy Health associated with this report. Officer

Crime and There are no impacts on Crime and Head of New Disorder Disorder associated with this report. Business and Housing Development Procurement There are no impacts on Procurement Head of New associated with this report. Business and Housing Development 2. INTRODUCTION AND BACKGROUND

2.1The purpose of the Compliance Audit exercise is to carry out a comprehensive review of a sample of Homes England funded schemes to confirm that grant recipients have met Homes England’s funding conditions and contractual requirements and have properly exercised their responsibilities.

2.2As the grant recipient the Council are responsible for using grant for the purposes stated in the grant agreement, maintaining proper records which comply with Homes England’s terms and conditions of grant, and providing relevant information to Homes England in accordance with the requirements of the grant conditions.

2.3The audit findings inform future investment decisions and reassure the Homes England Chief Accounting Officer that public funds have been properly used.

2.4The outcome of the 2025/26 audit has now been agreed by Homes England’s Strategic Investment Board. As part of the Homes England funding requirements, the final Compliance Audit report, must be brought to committee’s attention.

2.5The final grade and results of the audit is ‘green’, meaning that no breaches have been identified and no further action is needed.

2.6Summary of Audit Results

2.7Financial Commitments

There are no financial commitments associated with this report.

3. AVAILABLE OPTIONS

3.1No options required, report for noting only

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corbens Phase 3: Compliance Audit ReportAppendix 1 104 KB Download
PDF
Homes England Audit Results: Corbens Phase 3Report 87 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
CE
Councillor Clive EnglishCommittee Member, present
TH
Councillor Tony HarwoodCommittee Member, present
SJ
Councillor Stuart JefferyChairman, present
DN
Councillor David NaghiCommittee Member, present
ST
Councillor Stephen ThompsonCommittee Member, present
SW
Councillor Simon WalesCommittee Member, present
MS
Councillor Michael SummersgillCommittee Member, present
RR
Councillor Rachel RodwellCommittee Member, present

More from Maidstone Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 Exempt ItemsThat all items be taken in public. Decided Open
8 Sep 2026 Minutes of the Meeting held on 22 July 2026That the Minutes of the meeting held on 22 July 2026 be approved as a correct record and signed. Approved Open
8 Sep 2026 Swale Borough Local Plan Review (Regulation 19) Public ConsultationThat Maidstone Borough Council’s draft response to the Swale Borough Council Local Plan Review Regulation 19 consulta... Agreed Open
8 Sep 2026 Tunbridge Wells Borough Local Plan Review Scoping Consultation (Regulation 20)That Maidstone Borough Council’s response to the Tunbridge Wells Borough Council Local Plan Review Scoping consultati... Agreed Open
8 Sep 2026 KCC Minerals Sites Plan Consultation ResponseThat 1. The draft publication consultation response be agreed, subject to typographical edits and officers strengthen... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies