Maidstone Borough Council
Maidstone Joint Transportation Board, Wednesday 25 March 2026 at 6.30pm

Maidstone Highway Works Programme

Noted Committee 1 paper

AI summaryMaidstone Joint Transportation Board noted Kent County Council's update on the Highways Forward Works Programme covering road, footway, drainage, lighting and developer funded schemes across the borough.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo further action required from the board
MoneyNot specified in the reportNo financial decisions taken
What happens nextWorks continue as programmedSubject to review and weather
Who it affectsMaidstone borough road usersResidents near programmed schemes

What was decided

The board noted the Highways Forward Works Programme update covering 2025/26 to 2026/27. Report P4, P24

No new schemes were approved and no changes were requested, as the report was for information only. Report P5, P6, P24

Why

Kent County Council Highways and Transportation provided the update to inform members of programmed schemes already approved for construction. Report P2, P6, P8

The programme replaces earlier two-year plans and is being extended to cover years three to five (2026/27 to 2028/29), with the revision work still in progress. Report P10, P11

What happens next

Delivery of the listed road, footway, drainage, lighting and transport schemes will continue, with residents informed by letter drop if dates change. Report P28, P140

Kent County Council will continue preparing the years three to five programme, largely based on asset management system data. Report P11

Street lighting replacement and major capital projects, including the A229 Blue Bell Hill scheme, are expected to progress on the dates set out in the report. Report P91, P117, P118

Options considered

  • Chosen: Note the report as presented. The report was classified as information only and the board resolved accordingly. Report P5, P24

Implications

  • Risk: The programme is subject to regular review and may change due to budget allocation, contract rate changes, inflation, conflicting works, or shifting priorities. Report P12
  • Other: Several machine resurfacing, footway and surface treatment schemes remain to be programmed or are currently proposed for the 2026/27 financial year. Report P35, P36, P37, P40, P63

Who and where

  • Residents and road users in Maidstone borough, including specific parishes such as Marden, Headcorn, Yalding, Lenham and Sutton Valence Report P14, P29, P70, P89
  • Members of the public living near the programmed works, who will be informed by letter drop if dates change Report P28, P140

Timeline

  • 11/08/2025: Refurbishment of A249 Albion Place / Union Street crossing completed Report P130
  • 26/11/2025: A20 Ashford Road (M20 J8) lane discipline sign scheme ordered Report P103
  • 30/12/2025: School Keep Clear markings upgrade ordered across 10 borough locations Report P112
  • Quarter 4 2025/26: Expected completion of A20 Ashford Road (M20 J8) and School Keep Clear schemes Report P103, P112
  • Summer 2026: Proposed start date for Royal Engineers Road / Stacey Street toucan crossing upgrade Report P122
  • Late 2029: Construction still programmed to begin on the A229 Blue Bell Hill major junction scheme Report P117
  • 2026/27: Footway and surface treatment works currently proposed for this financial year Report P40, P63
  • 19.02.2026: Combined Members Grant programme list up to date as of this date Report P133
  • Spring 2025: Several surface treatment schemes completed Report P51, P54, P55, P56, P58, P61
  • Summer 2025: Further surface treatment schemes completed across the borough Report P52, P53, P57, P59, P60, P62
  • 20.02.2026: Casualty reduction measures status correct as of this date Report P97

Plain English for the jargon

  • HAMP: Highways Asset Management Plan, Kent County Council's plan setting out how it manages its roads.
  • LTP: Local Transport Plan, the source of funding for transport improvement schemes.
  • S106: Section 106 agreement, a planning obligation used to fund works by developers.
  • CIL: Community Infrastructure Levy, a charge on new development used to fund infrastructure.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item172

Resolved

RESOLVED : That the report be noted.
Word for word from the decision Maidstone published for this meeting. Source: meetings.maidstone.gov.uk

Follow this further

Built from Maidstone's papers

What the report saysPro

Report to Maidstone Joint Transportation Board

To: Maidstone Joint Transportation Board

By: KCC Highways and Transportation

Date: 25th March 2026

Subject: Highways Forward Works Programme: 2025/26 – 26/27

Classification: Information Only

Summary: This report updates Members on the identified schemes approved for construction

1. Introduction

This report provides an update and summarises schemes that have been programmed for delivery in 2025/26 .

In summer 2021 Kent County Council published a Highways Asset Management Plan (HAMP), which included, as Appendix C, a five-year Forward Works Programme for the years 2021/22 to 2025/26. this reflected the need to move away from annual programmes and to consider asset management activity a multi-year one.

The first part of the programme concerned the two years 2021/22 - 2022/23. In October 2022 we replaced this with a programme covering the years 2022/23 - 2023/24, and we have now produced a new two-year programme covering the years 2024-25 – 2025-26. As before, most of the sites included in this programme have already been verified by our engineers.

The second part of our programme related to years three to five of our five-year programme (2023/24 - 2025/26). This too is in need of revision to cover the years 2026/27 - 29028-29 and the work required to do this is currently in progress. As before, our new years three to five programme will be largely based on data from our asset management systems, so may be subject to more changes as the schemes are verified.

This programme is subject to regular review and may change for a number of reasons including budget allocation, contract rate changes, inflationary pressures such as material price increases, conflicting works, and to reflect our changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase, and additional sites may be added or others advanced if their condition deteriorates rapidly so that we need to react in order to keep the highway in a safe and serviceable condition.

Further information about how we manage our highway infrastructure, including our county- wide five-year forward works programme, may be found on our website: https://www.kent.gov.uk/about-the-council/strategies-and-policies/transport-and-highways- policies/managing-highway-infrastructure

In addition to planned maintenance of our highway assets, this report includes transportation and safety schemes, developer funded works, Combined Members Grant schemes, and planned maintenance of public rights of way. Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A

Drainage Repairs & Improvements – see Appendix B

Street Lighting – see Appendix C

Transportation and Safety Schemes – see Appendix D • Casualty Reduction Measures • Externally Funded Schemes • Major Capital Programme

Developer Funded Works – see Appendix E

Bridge Works – see Appendix F

Traffic Systems – see Appendix G

Combined Members Grant – Member Highway Fund – see Appendix H

Road Markings – see Appendix I

Conclusion

1. This report is for Members’ information.

Contact Officers:

The following contact officers can be contacted on 03000 418181

Richard Emmett Senior Highway Manager West Kent Rebecca Bailey Maidstone Highway Manager Alan Casson Strategic Asset Manager Carol Valentine Drainage Asset Manager Helen Rowe Structures Asset Manager Sue Kinsella Street Light Asset Manager Toby Butler Traffic Operations and Technology Manager Jamie Hare Development Agreements Manager Nikola Floodgate Road Safety and Active Travel Group Manager Lee Burchill Major Capital Programme Manager Jonathan Dean Highway Manager Special Projects/HSR/Signs & Lines Appendix A – Road, Footway and Cycleway Renewal and Preservation Scheme

The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Maidstone Highway Works ProgrammeReport 186 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 21 attended
RA
Richard AshParish Representative, present
SB
Councillor Sarah BarwickCommittee Member, present
BB
Councillor Brian BlackCommittee Member, absent
OJ
Councillor Oliver James BradshawCommittee Member, present
RB
Councillor Ronald BurkeCommittee Member, present
BC
Councillor Brian ClarkChairman, present
GC
Councillor Gary CookeCommittee Member, present
PR
Peter Ronald CoullingParish Representative, apologies
SA
Councillor Spencer Anthony DixonCommittee Member, apologies
SE
Councillor Sarah Elizabeth EmbersonCommittee Member, absent
RF
Councillor Robert FordCommittee Member, absent
JH
Councillor Joe HigsonCommittee Member, present

All 21 on the meeting page

More from Maidstone Maidstone Joint Transportation Board

All decisions
MeetingDecisionOutcome
25 Mar 2026 Exempt itemsThat all items on the agenda be taken in public as proposed. Decided Open
25 Mar 2026 Minutes of the Meeting Held on 21 January 2026That the Minutes of the meeting held on 21 January 2026 be approved as a correct record and signed. Approved Open
25 Mar 2026 Maidstone Joint Transportation Board Work ProgrammeRESOLVED : That 1. Item 1: Updates on the junctions within the MITP, and Item 2: Allocation of Community Infrastructu... Decided Open
25 Mar 2026 Maidstone Integrated Transport PackageThat the report be noted. Noted Open
25 Mar 2026 ANPR Cameras in Town CentreThat the report be noted. Noted Open