Maidstone Integrated Transport Package

Noted Committee 1 paper

AI summaryMaidstone Joint Transportation Board noted a report on the £8.9m Maidstone Integrated Transport Package, with the A20 Ashford Road/Willington Street scheme still awaiting further funding.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThe MITP report was noted by the Board
Money£8.9mLocal Growth Fund from SELEP allocated to MITP
What happens nextA20 Ashford Road scheme deliverySubject to additional funding becoming available
Who it affectsMaidstone road users and KCCTransport infrastructure in the borough

What was decided

The Board noted the report on the Maidstone Integrated Transport Package.

Why

The £8.9m Local Growth Fund from the South East Local Enterprise Partnership has been fully spent on the MITP programme by 2023/24, with most schemes complete or withdrawn. Report 1.1, 1.2, 1.3

Several schemes were withdrawn after opposition from county and borough councillors and the JTB, with the report summarising current status, spend and abortive costs. Report 1.3, 1.4, 3.4

What happens next

Decide whether to wait for outstanding S106 contributions (Option 1) or pursue forward funding (Option 2) to deliver the A20 Ashford Road/Willington Street scheme. Report 6.1, P37, P38

Arrange disposal of the Wheatsheaf Public House, declared surplus to highway requirements. Report 6.2

MBC councillors need to agree how £2.99m of S106 contributions for bus prioritisation on the A274 Sutton Road should now be used. Report 3.3, 6.3

The money

  • £8.9m Local Growth Fund awarded to the MITP programme Report 1.1, 3.1, P16
  • £4.343m S106 monies provisionally secured for MITP schemes Report 1.4, 3.2, P19
  • £2.746m S106 drawn down to date Report 1.4, 3.2, P19
  • £1.276m Abortive costs where capital was spent but projects not delivered Report 3.4, P23
  • £3.066m Current budget for the A20 Ashford Road/Willington Street scheme Report 1.7, P8
  • £7.244m Total cost of A20 Coldharbour Roundabout (complete) Report 1.7, P8
  • £2.55m Banked S106 for A274 Sutton Road/Willington Street (scheme withdrawn) Report 3.3, P45
  • £2.99m S106 for widening A274 Sutton Road with bus prioritisation Report 3.3

Options considered

  • Rejected: Option 1: Await outstanding S106 contributions before construction of the A20 Ashford Road/Willington Street scheme. Could incur a delay of 3 to 4 years and increase delivery costs Report 6.1, P37
  • Rejected: Option 2: Pursue forward funding to enable earlier delivery of the A20 Ashford Road/Willington Street scheme. Cabinet Member for H&T and local KCC Member endorsed Wheatsheaf PH disposal; no decision stated on this option Report 6.1, 6.2, P38
  • Rejected: A274 Sutton Road/Willington Street (Phase 1). Withdrawn following councillor objections in 2024; not supported by JTB in January 2018 as it would require removal of grass verges and trees Report 7.5, P8
  • Rejected: Cripple Street/Boughton Lane junction improvement. MBC councillors did not support loss of green space and mature trees; alternative options did not deliver benefits Report 7.38, P8
  • Rejected: Sheals Crescent junction priority change. Would reduce capacity and increase risk of incidents; withdrawn in 2023 Report P8
  • Rejected: A20 London Road/Hall Road conversion to roundabout. Following public and MP opposition in 2023; focus shifted to drainage improvements only Report 7.45, P8
  • Rejected: A26 Tonbridge Road/Fountain Lane double mini roundabout. Would provide limited traffic capacity benefits and introduce unacceptable safety risks Report 4.3, 8.12, 8.14
  • Rejected: M20 Junction 7 improvements (separate scheme). Currently insufficient funding; CIL bid rejected in 2023, further CIL bid made November 2025 awaiting decision Report 4.2, 8.7

Implications

  • Financial: Abortive costs of £1.276m have been moved from capital to revenue, creating a revenue burden for Kent County Council. Report 3.4, 5.4, P23, P45
  • Financial: Kent County Council is unable to promote and sustain the full programme of major schemes originally envisaged for Maidstone due to insufficient funding. Report 5.5
  • Risk: There is currently insufficient funding to deliver the A20 Ashford Road/Willington Street scheme, the last remaining MITP scheme; outstanding S106 not expected until 2028 or 2029. Report 1.5, 6.1, P45
  • Risk: Some S106 funding for M20 Junction 7 is time restricted and a contract must be let by 01 January 2029 or contributions may need to be returned. Report 8.6
  • Legal: Developer funding of £2.28m for A274 Sutton Road between Willington Street and Wallis Avenue must be spent for that purpose or agreement reached with signatories to re-allocate, otherwise returned to developers. Report 7.10
  • Other: KCC has used LGF to forward fund outstanding S106 contributions; once S106 is banked, LGF will be repaid to the scheme from which it was borrowed. Report P45

Who and where

  • Residents and road users in Maidstone borough Report 1.1, 2.1
  • Kent County Council as highway authority Report 1.2, 5.4
  • Maidstone Borough Council Report 1.3, 3.3, 6.3
  • Tonbridge and Malling Borough Council residents and road users (cross-boundary impacts) Report 1.2, 7.17
  • Developers who have paid S106 contributions for A274 Sutton Road Report 7.10

Timeline

  • February 2016: SELEP approved Phase 1 of MITP and award of £1.3m LGF
  • June 2017: B2246 Hermitage Lane North completed
  • January 2018: Maidstone JTB did not endorse the A274 Sutton Road/Willington Street scheme as proposed Report 7.5
  • June 2018: SELEP approved A20 Coldharbour Roundabout business case and £2.7m LGF Report 7.20
  • November 2018: SELEP approved reallocation of £1.3m and increase of £0.7m LGF to A20 Ashford Road/Willington Street scheme Report 7.8, 7.11
  • April 2019: SELEP approved Phase 3 business case and £4.2m LGF Report 7.30
  • November 2019: Wheatsheaf Public House purchased by KCC Report 7.34
  • March 2022 to September 2023: Trial closure of Cranborne Avenue carried out Report 7.35
  • April 2022: Listed building consent granted for relocation of ragstone wall at A20 Ashford Road/Willington Street Report 7.13
  • February 2023: Armstrong Road junction improvement completed Report 7.37
  • 2023: Sheals Crescent and A20/Hall Road schemes withdrawn Report 7.45, P8
  • September 2024: Cranborne Avenue closure made permanent Report 7.35
  • 2024/2025: A274 Sutton Road/Willington Street and Cripple Street schemes formally withdrawn Report P8
  • February to November 2024: A20 Coldharbour Roundabout completed Report 7.22
  • February 2025: Permanent works to close Cranborne Avenue completed Report 7.36
  • 2023/24: Local Growth Fund £8.9m spend completed in line with SELEP requirements Report 1.2
  • November 2025: KCC made a further CIL bid to MBC for M20 Junction 7 Report 4.2, 8.7
  • 2026: Minor works to relocate stop line of southbound approach at Wheatsheaf to be completed
  • early 2027: A249 Bearsted Road scheme due for completion Report 4.1, 8.4
  • 2027: Potential delivery of M20 Junction 7 if sufficient funding becomes available Report 4.2
  • 2028 or 2029: Expected date for outstanding S106 developments to reach payment trigger points Report P45
  • 01 January 2029: Deadline for M20 Junction 7 contract to be let or time-restricted S106 may need to be returned Report 8.6

Plain English for the jargon

  • MITP: Maidstone Integrated Transport Package
  • SELEP: South East Local Enterprise Partnership
  • LGF: Local Growth Fund
  • S106: Section 106 planning obligations, developer contributions towards infrastructure
  • CIL: Community Infrastructure Levy
  • KCC: Kent County Council
  • MBC: Maidstone Borough Council
  • JTB: Joint Transportation Board
  • PH: Public House
  • T&M: Tonbridge and Malling Borough Council
  • RBLI: Royal British Legion Institute
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item170

Resolved

That the report be noted.
Word for word from the decision Maidstone published for this meeting. Source: meetings.maidstone.gov.uk

Follow this further

Built from Maidstone's papers

What the report saysPro

Report to Maidstone Joint Transportation Board

Executive summary

1.1The Maidstone Integrated Transport Package (MITP) consisted of an £8.9m package of schemes that were originally agreed by the South East Local Enterprise Partnership (SELEP). Over the years there has been some confusion as to what the schemes actually were. The original bid document that was submitted to Government defined the scope as projects to assist the delivery of new and expanded Park and Ride sites in Maidstone. Subsequent to the bid submission and in light of developments with the Maidstone Local Plan at the time, the construction and operation of Park and Ride sites were not supported by Maidstone Borough Council, and an alternative package of transport schemes was identified by KCC and agreed by SELEP.

1.2The spend of the Local Growth Fund (£8.9m) was completed in 2023/24 in line with SELEP requirements and has been allocated to improvements at the A20 Coldharbour, Hermitage Lane (North), A229 Loose Rd junction with Armstrong Rd and the closure of Cranbourne Avenue at the Wheatsheaf junction. An allocation has also been put towards the ongoing A20 Ashford Rd/Willington Street scheme.

1.3It should be noted that several schemes were removed from the MITP as there was opposition from County and Borough Councillors and the Maidstone Joint Transportation Board. Money was spent developing these proposals, but the improvements to the A274 Sutton Road junction with Willington Street, Cripple Street, Sheals Crescent and the A20 London Road junction with Hall Road were subsequently dropped.

1.4In total, there are £4.343m of S106 monies provisionally secured from developer sites in Maidstone and Tonbridge & Malling that can be used towards the current schemes with £2.746m spent to date. The remaining S106 monies are yet to be banked by KCC because the developments have not reached the necessary trigger points.

1.5The A20 Ashford Road junction with Willington Street proposal is the last remaining scheme to be delivered within the MITP. The design has been completed but there are currently insufficient funds available to progress this scheme to delivery until other funds become available.

1.6Several schemes are assumed to be included in the MITP, including the A249 Bearsted Road, M20 Junction 7 improvements, A229 Linton Crossroads and A26 Tonbridge Road (Fountain Junction). However, monies spent on these projects has come from other funding streams that have been made available to KCC.

1.7Table 1: Summary of the current status of MITP Schemes:

Project Name Current Status Budget A20 Ashford Rd/Willington Street Ongoing (delivery subject to additional funding) £3.066m B2246 Hermitage Lane North Complete £0.623m A20 Coldharbour Roundabout Complete £7.244m A229 Loose Rd – Armstrong Rd Complete £2.312m A229 Loose Rd - Wheatsheaf Complete (minor work to finish at Cranborne Ave) A274 Sutton Rd/Willington Street Withdrawn following Councillor objections in 2024 N/A A229 Loose Rd – Cripple Street Withdrawn following Councillor objections in 2024 N/A A229 Loose Rd – Sheals Crescent Withdrawn due to safety concerns in 2023 N/A A20/Hall Rd, Aylesford Withdrawn following public and MP objections in 2023 N/A

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Maidstone Integrated Transport PackageReport 1 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 21 attended
RA
Richard AshParish Representative, present
SB
Councillor Sarah BarwickCommittee Member, present
BB
Councillor Brian BlackCommittee Member, absent
OJ
Councillor Oliver James BradshawCommittee Member, present
RB
Councillor Ronald BurkeCommittee Member, present
BC
Councillor Brian ClarkChairman, present
GC
Councillor Gary CookeCommittee Member, present
PR
Peter Ronald CoullingParish Representative, apologies
SA
Councillor Spencer Anthony DixonCommittee Member, apologies
SE
Councillor Sarah Elizabeth EmbersonCommittee Member, absent
RF
Councillor Robert FordCommittee Member, absent
JH
Councillor Joe HigsonCommittee Member, present

All 21 on the meeting page

On this subject at Maidstone

Search all
  1. Maidstone Integrated Transport PackageThis decision
  2. Report of the Head of Planning and Development - Maidstone Integrated Transport Strategy and Maidstone Walking and Cycling StrategyApproved
  3. Maidstone Integrated Transport StrategyApproved

More from Maidstone Maidstone Joint Transportation Board

All decisions
MeetingDecisionOutcome
25 Mar 2026 Exempt itemsThat all items on the agenda be taken in public as proposed. Decided Open
25 Mar 2026 Minutes of the Meeting Held on 21 January 2026That the Minutes of the meeting held on 21 January 2026 be approved as a correct record and signed. Approved Open
25 Mar 2026 Maidstone Joint Transportation Board Work ProgrammeRESOLVED : That 1. Item 1: Updates on the junctions within the MITP, and Item 2: Allocation of Community Infrastructu... Decided Open
25 Mar 2026 ANPR Cameras in Town CentreThat the report be noted. Noted Open
25 Mar 2026 Maidstone Highway Works ProgrammeRESOLVED : That the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies