AI summaryMaidstone policy committee recommends Cabinet approve up to £2.2 million for Archbishop's Palace refurbishment into a wedding and events venue, expected to be operating by February 2027.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedRecommend £2.2m spend and continued delegations
Money£2.2 millionUp to £2.2m capital budget for Palace
What happens nextCabinet decisionCabinet to consider recommendations
Who it affectsPalace and Maidstone residentsHeritage building and borough visitors
What was decided
Recommend to Cabinet that it agrees to capital expenditure of up to £2.2 million for the Palace project. Report P6
Recommend continued delegation to the Director of Finance, Resources and Business Improvement to select and appoint professional advisers, obtain consents, enter into contracts for services, and enter into a conditional agreement for lease with the preferred tenant. Report P6
Recommend continued delegation to the Head of Legal Services to negotiate and complete all necessary legal formalities for the building contract, the lease and purchase of services. Report P6
Why
Public consultation and marketing have established a wedding and events venue as the most popular and viable use for the Palace, consistent with residents' preferences. Report 3.1, P20, P24
The preferred operator has over 20 years' experience, runs a successful Grade II listed wedding venue, hosts over 400 events a year, and the project meets the Council's investment criteria with payback in under six years and a 5.5% annual return. Report 1.6, 1.17, 3.1
The capital budget has increased from £1.5 million to £2.2 million to cover design development, a lift installation, archaeological and flood work, project and design team fees, contingency, and emergency repairs to the Dungeon scheduled ancient monument. Report 1.16, P43
What happens next
Submit the planning and listed building consent applications in May 2026, with a target determination date of July 2026. Report P47, P63
Develop the detailed costed scope of landlord works and agree the project management strategy in April and May 2026, run a tender process from May or June 2026, and mobilise the contractor in August 2026. Report P47, P64, P65
Target practical completion in January 2027 and handover to the tenant, with completion of the lease, in February 2027. Report P47, P66
The money
£2.2 million Updated capital budget for the Palace works, included in the 2026/27 capital programme Report P9, 1.16
£1.5 million Original capital budget approved by Cabinet in January 2024 Report P25, 1.16
£350,000 Net annual shortfall against ongoing budgets while the building remains in its present state, being £100,000 lost rent and £250,000 running costs Report P9, 1.4
£120,000 Expected annual rental income from the Palace under the new arrangement Report 1.16
£250,000 Ten per cent contingency in the updated cost plan Report P43
£150,000 Cost of emergency works to the Dungeon scheduled ancient monument Report P43
£100,000 Annual rent previously paid to the Council by the former tenant Kent County Council Report P9, 1.4
£250,000 Approximate annual running costs previously met by the former tenant Report P9, 1.4
Options considered
Chosen: Wedding and events venue (current direction). Top public preference in the 2021 consultation and identified as the most viable option after the boutique hotel attempt failed Report P20, P24, 1.5, 1.6
Rejected: Boutique hotel, with Balfour Hospitality as preferred partner. Concluded not commercially viable in April 2023 given the scale of investment required Report P21, P23
Rejected: Mixed use culture and weddings. Second public preference in the 2021 consultation but not taken forward once a wedding venue operator was identified Report P20
Implications
Financial: Capital budget rises from £1.5 million to £2.2 million, with payback in under six years and a 5.5% annual return expected. The Council will lose the £100,000 annual rent previously received from Kent County Council but expects £120,000 per year in new rental income once operational. Report 1.16, 1.17, P25
Legal: Acting on the recommendations is within the Council's powers under Section 1 of the Localism Act 2011 and Section 111 of the Local Government Act 1972, with all legal documentation approved by the Council's shared legal service before completion. Report P10
Equalities: There is no impact on equalities as a result of the recommendations, and an Equalities Impact Assessment would only be carried out if a policy or service change is identified. Report P10
Climate: The upgrade works are intended to be environmentally sustainable and will take account of the flood risk associated with the site, supporting the Corporate Strategy priority of a high quality place adapted for a changing climate. Report P8
Risk: Risks include construction delivery, Historic England delays, local government reorganisation affecting new contracts, the commercial success of the operator, and the sensitivity of the historic site. These will be managed within the Council's Risk Management Framework. Report 4.1, P51, P52, P53, P54, P55, P56, 4.2
Staffing: The Council will need access to additional external expertise to deliver the recommendations. Report P10
Who and where
The preferred operator, an experienced hotel and wedding venue owner running a successful Grade II listed wedding venue and hosting over 400 events a year Report 1.6
Maidstone borough residents, who will have continued pedestrian public access and free showround open days at the Palace Report 1.7
Wedding and events clients and other visitors to the borough Report 1.6, 1.7
The Council's parking services, which currently use the building on a temporary basis and will be replaced by wedding guests using part of Mill Street car park Report P22, 1.8
Historic England, which must sign off listed building consent and has previously lacked timely resourcing Report 1.12, P52
All Saints Church, which adjoins the Palace and with which the Council is liaising to align plans Report 1.2
Timeline
March 2023: Kent County Council vacated the premises and the building was taken over temporarily by Parking Services Report P22
April 2023: Balfour Hospitality's exclusivity period expired, with the boutique hotel judged not commercially viable Report P23
July 2023: Cabinet approved seeking an operator focused on modest investment and a wedding or events venue Report P24
January 2024: Cabinet approved signing the Agreement for Lease with the preferred operator and a £1.5 million capital budget Report P25
October 2025: Agreement for Lease signed Report P27
May 2026: Submit planning and listed building consent applications Report P47, P63
January 2027: Practical completion of works Report P47, P66
February 2027: Handover to tenant and completion of lease Report P47
Plain English for the jargon
Listed Building Consent: Permission required for alterations to a listed building
HE: Historic England, the public body that advises on heritage matters
EqIA: Equalities Impact Assessment
KCC: Kent County Council, the former tenant of the Palace
Shared legal service: The Council's in-house legal service, referred to in the report as Mid Kent Legal Services
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item147
Resolved
RESOLVED to RECOMMEND to the CABINET: That 1. It agreed to capital expenditure of up to £2.2 million; 2. It continued to delegate authority to the Director of Finance, Resources and Business Improvement to select and appoint professional advisers to obtain all relevant consents, enter into contracts for applicable services as necessary, and to enter into a conditional agreement for lease with the preferred tenant, and; 3. It continued to delegate authority to the Head of Legal Services to negotiate and complete all necessary legal formalities for the building contract, the lease and purchase of services as set out above.
Word for word from the decision Maidstone published for this meeting.Source: meetings.maidstone.gov.uk
Report to Climate Transition, Corporate and Environmental Services Policy Advisory Committee
Executive summary
An extensive process of member and public consultation has been carried out concerning the future use of the Archbishop’s Palace. The Palace was vacated by Kent County Council in 2023 and initially the Council entered an exclusivity agreement with a development partner that did not lead to a subsequent contract. A second marketing exercise resulted in a signed Agreement for Lease with an operator and the appointment of a specialist design team to take forward the change of use and refurbishment project on behalf of the Council.
The report presents an update on the progress of the planning and listed building consent process and an update on the likely cost of the proposed works. Purpose of Report
Recommendation to Cabinet
This report makes the following recommendations to the Climate Transition, Corporate & Environmental Services Policy Advisory Committee.
That the Cabinet is recommended:
1. To agree to capital expenditure of up to £2.2 million. 2. To continue to delegate authority to the Director of Finance, Resources and Business Improvement to select and appoint professional advisers to obtain all relevant consents, enter into contracts for applicable services as necessary, and to enter into a conditional agreement for lease with the preferred tenant. 3. To continue to delegate authority to the Head of Legal Services to negotiate and complete all necessary legal formalities for the building contract, the lease and purchase of services as set out above. ARCHBISHOP’S PALACE – NEXT STEPS
1. CROSS-CUTTING ISSUES AND IMPLICATIONS
Issue Implications Sign-off Impact on The project described in this report supports Director of Corporate the Council’s Corporate Strategy priorities, Finance and Priorities most notably A High Quality Place adapted for Resources a Changing Climate. Biodiversity The upgrade works are intended to be Director of and Climate environmentally sustainable and they will take Finance and Change into account the flood risk associated with the Resources site.
Financial, Running costs of the building were previously Director of People and in the region of £250k per annum and were Finance and Planet met by the former tenant, who additionally Resources paid the Council £100k per annum rent. Accordingly, there is a net shortfall of £350k per annum against ongoing budgets whilst the building remains in its present state. The capital budget of £2.2 million is included within the 2026/27 capital programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Climate Transition, Corporate and Environmental Services Policy Advisory Committee at Maidstone and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.