AI summaryMaidstone Cabinet approves up to £2.2 million to convert the Archbishop's Palace into a wedding and events venue, with a signed operator and planning applications due in May 2026.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedUp to £2.2m for Palace refurbishment
MoneyUp to £2.2 millionCapital budget within 2026/27 programme
What happens nextSubmit planning and listed building applicationsBoth applications due in May 2026
Who it affectsArchbishop's Palace, MaidstoneListed heritage asset beside River Medway
What was decided
Cabinet agreed capital expenditure of up to £2.2 million for the Palace project. Report P4
Delegated authority continues to be given to the Director of Finance and Resources to appoint professional advisers, obtain consents, enter contracts and agree a conditional lease with the preferred tenant. Report P5
Delegated authority continues to be given to the Head of Legal Services to complete the building contract, lease and service purchase documentation. Report P6
Why
A signed operator is in place, public consultation since 2020 supports a wedding and events use, and the revised cost plan still meets the Council's investment criteria with payback in under six years and a 5.5% annual return. Report 1.6, 1.17, P15, P20
Doing nothing would breach the agreement to lease, leave the Council continuing to absorb around £350,000 a year in running costs and lost rent, and miss the chance to bring the building back into use. Report 1.4, 3.1, P47
Alternative uses, including a hotel, were explored previously and found not to be commercially viable. Report 3.3, P18, P51
What happens next
Submit the detailed planning application and two Listed Building Consent applications in May 2026, then tender the building contract from May or June 2026. Report 1.12, 1.19, P43, P68
If consents are obtained, contractor mobilisation is expected from August 2026, with practical completion in January 2027 and handover to the tenant and lease completion in February 2027. Report 1.19, P43, P70, P71
Undertake emergency works to the Dungeon, a Scheduled Ancient Monument on the at risk register, covering roof, rainwater goods, vegetation, lintel and masonry repairs. Report 1.13, P33
The money
£2.2 million Total capital budget for the Palace refurbishment, within the 2026/27 capital programme Report P4, P7, 1.16
£1.5 million Original 2023 capital estimate for landlord improvements Report P20, 1.16
£250,000 Approximate annual running costs previously met by the former tenant Report P7, 1.4
£100,000 Annual rent previously paid to the Council by the former tenant Report P7, 1.4
£350,000 Approximate net annual shortfall while the building remains in its present state Report P7, 1.4
£120,000 Projected annual rental income once the Palace is in use as a wedding venue Report 1.16
£30,000 Additional cost of installing a lift Report P39
£150,000 Additional cost of emergency work to the Dungeon Report P39
£70,000 Additional cost from general price inflation Report P39
£100,000 Additional uplift due to archaeological and flood reports Report P39
£250,000 10% contingency added to the budget Report P39
£100,000 Additional project and design team fees arising from pre-application requirements Report P39
Options considered
Chosen: Proceed with the agreed refurbishment and wedding and events venue programme. Financially viable with payback under six years and a 5.5% return, consistent with public consultation, and supported by a signed operator with relevant track record. Report 3.2, P49, 4.1, P53
Rejected: Do nothing. Would breach the agreement to lease, continue the £350,000 a year net cost, and forgo income and community use of the building. Report 3.1, P47
Rejected: Pursue alternative options such as a hotel. Explored since 2020 and found not to be commercially viable, including a previous preferred partner that withdrew in April 2023. Report 3.3, P18, P51
Implications
Financial: The £2.2 million capital budget is included in the 2026/27 capital programme; the project is expected to pay back in under six years at a 5.5% annual return and to replace the current £350,000 a year net shortfall with at least £120,000 of annual rent. Report P7, 1.16, 1.17
Legal: Decisions are within the Council's powers under section 1 of the Localism Act 2011 and section 111 of the Local Government Act 1972, with all legal documentation approved by Mid-Kent Legal Services. Report P7
Staffing: The Council needs access to additional external expertise to deliver the recommendations. Report P7
Risk: Key risks are construction delivery, delays from Historic England, local government reorganisation creating extra approval steps, commercial success of the operator, and the historic and sensitive nature of the site; cost estimates remain uncertain until tenders are received. Report 1.18, 5.1, P56, P57, P58, P59, P60
Equalities: No equalities impact is expected from the recommendations; an EqIA would be carried out if a policy or service change is identified. Report P7
Climate: The works are intended to be environmentally sustainable and will take account of the site's flood risk, supporting the Corporate Strategy priority of a high quality place adapted for a changing climate. Report P7
Who and where
Maidstone Borough Council, as freeholder and prospective landlord Report 1.1, 1.6, P4
The preferred tenant, an experienced hotel and wedding venue operator with a Grade II listed wedding venue in its portfolio Report 1.6
Residents of the borough, who would gain a wedding and events venue and free showround open days Report 1.7, P15
Visitors to weddings and events, who would use a discrete section of Mill Street car park by agreement Report 1.8
All Saints Church authorities, with whom the Council is liaising to align plans for the adjoining sites Report 1.2
Historic England, which is involved through pre-application advice and will need to sign off the planning and listed building consents Report 1.11, 1.12, P57
Timeline
February 2020: Options for future use of the Palace first considered at an open meeting for councillors Report P13
October 2021: Public consultation attracted over 2,000 individual responses Report P15
March 2022: Policy and Resources Committee selected Balfour Hospitality as preferred partner for a boutique hotel Report P16
March 2023: Kent County Council vacated the premises Report P17
April 2023: Balfour Hospitality exclusivity period expired and the boutique hotel concept was found not commercially viable Report P18
July 2023: Cabinet approved seeking an operator for a more modest wedding and events venue use Report P19
24 January 2024: Cabinet approved signing an Agreement for Lease with the preferred operator and a £1.5 million capital budget Report P20
September 2024: Design team appointed Report P21
October 2025: Agreement for Lease signed Report P22
1 April 2026: Climate Transition, Corporate and Environmental Services Policy Advisory Committee considered and supported the matter Report 6.2, P65
May 2026: Submit detailed planning and two Listed Building Consent applications Report 1.12, 1.19, P68
May or June 2026: Tender commencement for the building contract Report 1.19, P43
July 2026: Determination of planning and listed building consent applications (provisional) Report 1.19, P43
January 2027: Practical completion of works and opening of the Palace as a wedding venue Report 1.19, P43, P71
February 2027: Handover to the tenant and completion of the lease Report 1.19, P43
Plain English for the jargon
Agreement for Lease: A conditional contract that sets out the terms on which a lease will be granted once specified conditions, such as obtaining planning consent, are met.
Listed Building Consent: Permission required from the local planning authority to alter, extend or demolish a listed building, in addition to any planning permission needed.
Scheduled Ancient Monument: A site of national importance protected under the Ancient Monuments and Archaeological Areas Act 1979, such as the Dungeon at the Palace.
Historic England: The public body that advises on and helps look after England's historic environment, including listed buildings and scheduled monuments.
EqIA: Equality Impact Assessment, a process to assess the likely effects of a policy or service change on people with protected characteristics.
Mid-Kent Legal Services: The shared legal service that will approve legal documentation for the Council on this project.
Section 24 directive: The reference here to additional approval procedures that will apply to new contracts over specified amounts once local government reorganisation plans are approved by Parliament.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item281
Resolved
That 1. The Capital expenditure of up to £2.2 million be agreed. 2. Delegated authority continues to be given to the Director of Finance and Resources, to select and appoint professional advisers to obtain all relevant consents, enter into contracts for applicable services as necessary, and to enter into a conditional agreement for lease with the preferred tenant. 3. Delegated authority continues to be given to the Head of Legal Services to negotiate and complete all necessary legal formalities for the building contract, the lease and purchase of services as set out above.
Word for word from the decision Maidstone published for this meeting.Source: meetings.maidstone.gov.uk
An extensive process of member and public consultation has been carried out concerning the future use of the Archbishop’s Palace. The Palace was vacated by Kent County Council in 2023 and initially the Council entered an exclusivity agreement with a development partner that did not lead to a subsequent contract. A second marketing exercise resulted in a signed Agreement for Lease with an operator and the appointment of a specialist design team to take forward the change of use and refurbishment project on behalf of the Council.
The report presents an update on the progress of the planning and listed building consent process and an update on the likely cost of the proposed works.
Purpose of report
Decision This report makes the following recommendations to the Cabinet: That
1. Capital expenditure of up to £2.2 million be agreed;
2. Delegated authority continues to be given to the Director of Finance, Resources and Business Improvement to select and appoint professional advisers to obtain all relevant consents, enter into contracts for applicable services as necessary, and to enter into a conditional agreement for lease with the preferred tenant; and
3. Delegated authority continues to be given to the Head of Legal Services to negotiate and complete all necessary legal formalities for the building contract, the lease and purchase of services as set out above. 1. CROSS-CUTTING ISSUES AND IMPLICATIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.