Maidstone Borough Council
Cabinet, Wednesday 15 April 2026 at 6.30pm

Parkwood Industrial Estate Investment

Agreed Executive 2 papers

AI summaryMaidstone Cabinet has approved a £4 million refurbishment and energy efficiency programme at Parkwood Industrial Estate, covering 66 units across seven estates. Works run from April 2026 to March 2028 and will be procured by the Director of Finance and Resources.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedIncluding over-cladding of asbestos roofs
Money£4 million capital budgetWithin existing allocation, no new funding needed
What happens nextProcurement and works to beginProgramme runs April 2026 to March 2028
Who it affectsNot stated

What was decided

Cabinet agreed the programme of refurbishment works and Energy Performance Certificate improvements as set out in the report and recommended by the appointed Project Manager. Report P7

Cabinet gave delegated authority to the Director of Finance and Resources to procure the required works and use the funds allocated within the Capital Budget. Report P8

Why

Current and future legislation set minimum EPC requirements (E now, C by 2027, with B expected between 2030 and 2035) which the estate's ageing stock will not meet without investment. Report 1.3, P4

Roofs on Wren, Phoenix and 12 Heronden are nearing the end of their economic life, some are failing and letting water into tenant space, and the Council is contractually obliged to replace several of them. Report P36

The works will safeguard the existing rental income of £1.194 million, support Council services and meet the Corporate Strategy priorities of a high quality place and a fairer economy. Report P2, P10, P41

What happens next

Implement the schedule of works covering the seven estates, including over-cladding roofs, replacing windows and doors, upgrading lighting to LEDs and preparing roofs for solar panels. Report P19, P20, P21, P22, P23, P24, P52

Procure the works in line with the Council's financial procedure rules, complete an environmental impact assessment, and seek tenant contributions to mitigate cost. Report 1.10, P11

Run a programme of tenant liaison to manage disruption and set up an ongoing asbestos inspection regime for encapsulated roofs. Report P45, P46

The money

  • £1.194 million Current passing rent from 66 directly let units Report P2, 1.2
  • £4 million Capital budget allocated for the Parkwood programme Report P4, 1.10, P10
  • £2.3 million Estimated cost of the over-cladding element, based on market testing Report 1.10

Options considered

  • Rejected: Option 1: Do nothing. Council would be barred from letting properties that did not meet minimum EPC standards, causing falling rental income and higher holding costs. Report 3.1, P32
  • Rejected: Option 2: EPC improvements only. Insulated roofs are usually needed to meet future EPC standards, rental income and competitiveness would decline, and the Council would breach lease covenants to replace roofs. Report 3.2, P34, P35, P36
  • Chosen: Option 3: Full recommended works including over-cladding of asbestos roofs on Wren, Phoenix and 12 Heronden. Improves EPC ratings, safeguards rental income, extends asset life beyond 2050 and keeps holdings competitive; achievable within the £4 million budget. Report 3.3, P38, 4.1, P41

Implications

  • Legal: Accepting the recommendations fulfils the Council's duties under the Energy Performance of Buildings (England and Wales) Regulation 2012; failure could place the Council in breach. Report P11
  • Financial: All works are within the approved £4 million capital budget and require no new funding; tenant contributions will be sought to reduce cost to the Council. Report 1.10, P10
  • Climate: Provision has been made to allow installation of solar panels and the scheme aligns with the Biodiversity and Climate Change Action Plan. Report P10, 1.7
  • Risk: Asbestos will be retained and encapsulated; an ongoing inspection programme will be needed to ensure it is not disturbed, with market inflation and tenant disruption also monitored. Report 1.8, P46
  • Staffing: The programme will be delivered using current staffing. Report P11
  • Other: Crime and disorder may be helped by keeping the estate attractive, fully occupied and less prone to vandalism and anti-social behaviour. Report P12

Who and where

  • Tenants of the 66 directly let units across the seven Parkwood estates Report P2, 1.2
  • Local businesses and employees using the industrial estate Report 1.1, P41
  • Council services funded by surplus rental income from the investment portfolio Report P1, P41
  • Prospective tenants seeking premises from 2027 onwards when the EPC standard rises to C Report 1.3

Timeline

  • April 2026, March 2028: Programme of refurbishment and EPC works scheduled to take place. Report 1.11
  • 2027: Minimum EPC standard for commercial properties rises to C. Report 1.3
  • 2030-2035: Minimum EPC standard expected to rise to B during this period. Report 1.3
  • 1 April 2026: Matter considered and supported by the Climate Transition, Enforcement and Environmental Services Policy Advisory Committee. Report 6.2, P50
  • 15 April 2026: Cabinet decision taken to approve the programme and delegate procurement authority.

Plain English for the jargon

  • EPC: Energy Performance Certificate, a rating of a building's energy efficiency, with current minimum of E for commercial lets.
  • Over-cladding: A construction method where the existing roof is left in place and a new insulated roof is built over the top, leaving any asbestos undisturbed.
  • Passing rent: The current rent being paid by tenants under existing leases, here £1.194 million across 66 units.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item282

Resolved

That 1. The program of refurbishment works and Energy Performance Certificate improvements as set out in the report and as recommended by the appointed Project Manager and associated advisors be agreed. 2. Delegated Authority be given to the Director of Finance and Resources to procure the required works and utilise the funds allocated within the Capital Budget.
Word for word from the decision Maidstone published for this meeting. Source: meetings.maidstone.gov.uk

Follow this further

Built from Maidstone's papers

What the report saysPro

Report to Cabinet

Executive summary

The Council owns the freehold of the Parkwood Industrial Estate in Maidstone. The properties are held in the investment portfolio and surplus income, above and beyond that required for asset management, supports the provision of Council services.

The Council has retained seven estates (66 units) that it directly lets to tenants. The current passing rent is £1.194 million.

Investment in the estates is now needed to meet and deliver:

• current and future legislation regarding minimum EPC requirements • the council’s contractual obligations (e.g. roof replacement / repair covenants in leases) • environmental / sustainable improvements which might be possible to achieve (eg the improvement of roofs to allow for the installation of solar panels) • containment of asbestos to reduce potential future liabilities • redecoration / refurbishment of units to remain competitive when compared to competing estates at both Parkwood and elsewhere in the borough. This will safeguard as oppose to increase the income. £4 million has been allocated within the capital program to deliver the above. Approval is now required to proceed with the works together with agreement on the proposed strategy of asbestos containment.

Purpose of report

Decision

This report makes the following recommendations to the Cabinet: That

1. It agrees to proceed with the program of refurbishment works and Energy Performance Certificate improvements as set out in the report and as recommended by the appointed Project Manager and associated advisors; and

2. The Director of Finance and Resources be given delegated authority to procure the required works and utilise the funds allocated within the Capital Budget. 1. CROSS-CUTTING ISSUES AND IMPLICATIONS

Issue Implications Sign-off Impact on The four Corporate Strategy priorities are: Interim Corporate 1. A High Quality Place adapted for a Estates Priorities Manager Changing Climate 2. Resilient Communities 3. Quality Homes for All 4. Fairer Economy for People and Planet

The proposed works meet objectives 1 and 4 through: • Improved EPC ratings for Council owned properties • Making the properties capable of accommodating solar panels • Improving the standards of business premises within the borough which results in improved working environment for businesses • Continuing to support local businesses establish and grow • Removal of gas supplies where possible Biodiversity The implications of this report on biodiversity and Biodiversity & and Climate climate change have been considered and they Climate Change align with the Biodiversity and Climate Change Change Action Plan. In particular, provision has been Manager made to allow installation of solar panels where appropriate. Financial, The proposals set out in the recommendation are Director of People and all within the approved capital budget for works at Finance and Planet the Parkwood Industrial Estate of £4 million and Resources so need no new funding for implementation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Plan of estateAppendix 1 195 KB Download
PDF
Parkwood Industrial Estate InvestmentReport 102 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 8 attended
CE
Councillor Clive EnglishCommittee Member, present
TH
Councillor Tony HarwoodCommittee Member, present
SJ
Councillor Stuart JefferyChairman, present
DN
Councillor David NaghiCommittee Member, present
ST
Councillor Stephen ThompsonCommittee Member, present
SW
Councillor Simon WalesCommittee Member, present
MS
Councillor Michael SummersgillCommittee Member, apologies
RR
Councillor Rachel RodwellCommittee Member, apologies

On this subject at Maidstone

Search all
  1. Parkwood Industrial Estate InvestmentThis decision
  2. Parkwood Industrial Estate InvestmentAgreed

More from Maidstone Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 Exempt ItemsThat all items be taken in public. Decided Open
8 Sep 2026 Minutes of the Meeting held on 22 July 2026That the Minutes of the meeting held on 22 July 2026 be approved as a correct record and signed. Approved Open
8 Sep 2026 Swale Borough Local Plan Review (Regulation 19) Public ConsultationThat Maidstone Borough Council’s draft response to the Swale Borough Council Local Plan Review Regulation 19 consulta... Agreed Open
8 Sep 2026 Tunbridge Wells Borough Local Plan Review Scoping Consultation (Regulation 20)That Maidstone Borough Council’s response to the Tunbridge Wells Borough Council Local Plan Review Scoping consultati... Agreed Open
8 Sep 2026 KCC Minerals Sites Plan Consultation ResponseThat 1. The draft publication consultation response be agreed, subject to typographical edits and officers strengthen... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies