Temporary Accommodation Acquisition (phase 7b) and the Local Authority Housing Fund
DecidedCommittee1 paper
AI summaryMaidstone councillors back £3.4m temporary accommodation spend and joining a £4.1m government housing grant, to deliver 24 extra homes by 2029.
Written from the decision and the officer reportPDF Pro
OutcomeRecommendedApprove £3.4m property purchases and join LAHF Round 4
Money£3.4m in 2026/27 plus £4,103,018 grantCapital budget plus LAHF Round 4 grant funding
What happens nextCabinet to decideCommittee recommends Cabinet approval
Who it affectsHomeless households and Afghan resettlement familiesUp to 24 new temporary and resettlement homes in the borough
What was decided
The committee agreed to recommend that the Director of Finance and Resources be given delegated authority to buy properties for temporary accommodation up to £3.4m in 2026/27, in consultation with the Cabinet Member for Housing and Homelessness. Report P7
The committee agreed to recommend that the council join the Local Authority Housing Fund Round 4 and accept its £4,103,018 allocation, with the Director of Regeneration and Place to finalise how the money is spent. Report P7, 2.10
The committee agreed to recommend that the Head of Mid Kent Legal Services be authorised to complete all necessary legal paperwork. Report P7
Why
The Purchase and Repair programme gives the council a more controllable, cheaper supply of temporary accommodation than nightly paid lets, and lets it keep an asset on its books. Report 2.5, P8, 6.4
Joining the LAHF R4 grant roughly doubles the number of new homes the council can deliver in the same period, from around 12 to 24, by combining grant with existing capital. Report P4, 2.10, 2.16
Increasing self-contained, good-quality homes in the borough supports homelessness prevention and better outcomes for households in housing need, including Afghan resettlement families. Report P8, 2.10, 7.2
What happens next
If Cabinet approves, officers will begin the investment activity and approve each property purchase case by case, with ward councillors notified. Report 11.1, 11.2
DMS and Clairglow will carry out safety checks, refurbishment, gas safety testing and heating works on the properties bought. Report 2.9
The LAHF R4 target is to deliver 20 homes in 2026/27 and 4 in 2028/29, totalling 24 by 31 March 2030. Report 2.12, P39, P40, P41, P42
The money
£3.4m Total 2026/27 budget for phase 7b purchases (£2m new plus £1.4m underspend from phase 7a) Report P2, 2.7, 6.1
£2m Capital allocation for phase 7b agreed by Council on 25 February 2026 Report P2
£1.4m Underspend from phase 7a brought forward into 2026/27 Report P2, 2.7
£4,103,018 LAHF Round 4 grant allocation from the Department for Levelling Up, Housing and Communities for 2026/27 to 2029/30 Report P3, 2.10, 2.16
Options considered
Chosen: Continue Purchase and Repair phase 7b and participate in LAHF R4. Most cost-effective way to grow the temporary accommodation portfolio and roughly doubles homes delivered by using grant money alongside the £3.4m capital budget. Report 3.2, 4.1, P52
Rejected: Continue Purchase and Repair phase 7b only with the £3.4m budget. Would deliver only around half the number of additional homes over the same period. Report 3.1, 2.10
Rejected: Do nothing and buy no further properties. Carries increased financial risk from continued reliance on more expensive nightly paid accommodation. Report 3.3
Implications
Financial: Multi-year revenue impacts from voids, responsive repairs, compliance checks, landlord costs and financing the capital, largely offset by rental income and reduced nightly paid costs. Report 6.3, 6.5
Legal: The council has general power of competence under section 1 of the Localism Act 2011 and power under section 111 of the Local Government Act 1972 to enter into the purchases and grant arrangements. Report P9, P10
Equalities: No change of service is proposed, so an equalities impact assessment is not required. Report P10
Climate: Refurbishment will include fabric, insulation, heating controls, lighting and ventilation improvements where practical, plus reuse of existing homes and consideration of flood and overheating risk. Report 8.2, 8.3, 8.4, 8.5
Risk: Risks are within the council's risk appetite; if demand falls, properties can be converted to private rented stock within Maidstone Property Holdings Limited or sold, and any unspent LAHF money must be returned. Report 5.1, 5.3
Staffing: Delivered with current staffing, supported by external consultants for property sourcing. Report 7.1
Who and where
Households owed a homelessness duty by the council, who will be offered good-quality self-contained temporary accommodation in the borough Report 2.1, 2.5, P8
Families on the Afghan Resettlement Programme, who will be offered settled housing on fixed-term secure tenancies Report P34, 2.11, 2.12
Ward councillors, who will be notified when a property in their ward is being considered for purchase Report 11.2
Maidstone Property Holdings Limited, which could take on properties as private rented stock if the temporary accommodation need reduces
Timeline
2017: Council agreed that reducing temporary accommodation use would be a corporate priority and approved the Purchase and Repair budget Report 2.1
25 February 2026: Council approved £2m capital allocation for phase 7b in the 2026/27 capital programme Report P2
March 2026: Ministry of Housing, Communities and Local Government awarded the council £4,103,018 through LAHF Round 4 Report 2.10
2026/27: Target to deliver 20 of the 24 LAHF-funded homes, including 12 for the temporary accommodation element Report 2.12, P38, P39, P40, P41, P42
2028/29: Target to deliver the remaining 4 LAHF-funded resettlement homes Report 2.12, P42
31 March 2030: Memorandum of Understanding deadline for delivery of 12 temporary accommodation and 12 resettlement homes Report 2.12
Plain English for the jargon
LAHF R4: Local Authority Housing Fund Round 4, a government grant administered by the Department for Levelling Up, Housing and Communities to provide temporary and resettlement homes.
Purchase and Repair programme: Maidstone's scheme to buy properties in the borough and refurbish them for use as temporary accommodation.
Phase 7a and 7b: Successive phases of the Purchase and Repair programme; 7b is the new phase for 2026/27 and 7a is the previous phase with an underspend being carried forward.
Nightly paid accommodation: Temporary accommodation paid for by the council on a per-night basis, which is more expensive and less controllable than owned stock.
Afghan Resettlement Programme (ARP): Government scheme to resettle Afghan families in the UK; LAHF R4 funds settled housing for eligible households.
LHA: Local Housing Allowance, the rate used to set rental income levels for the temporary accommodation properties.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17
Resolved
RESOLVED to RECOMMEND to the CABINET: That 1. The Director of Finance and Resources, be given delegated authority, in consultation with the Cabinet Member for Housing and Homelessness, to purchase properties as determined by the Director of Regeneration and Place, for use as temporary accommodation up to the total value of £3.4m in 2026/27; 2. The Council participate in the Local Authority Housing Fund (LAHF Round 4) in accordance with its allocation set out in the report, and for the Director of Regeneration and Place to finalise the deployment of these monies in consultation with the Cabinet Member for Housing and Homelessness; and 3. The Head of Mid Kent Legal Services be authorised to negotiate and complete all necessary legal documentation and formalities to give effect to these recommendations.
Word for word from the decision Maidstone published for this meeting.Source: meetings.maidstone.gov.uk
Report to Housing and Community Cohesion Policy Advisory Committee
Executive summary
This report provides an update on the Council’s Purchase and Repair programme for temporary accommodation, using the approved 2026/27 capital budget and underspend brought forward. The report also sets out the opportunity to supplement the programme through participation in Local Authority Housing Fund Round 4 (LAHF R4).
There is £2m allocated within the capital programme agreed by Council on 25th February 2026 for a further phase (phase 7b) of investment in purchase and repair properties for use as Temporary Accommodation to help alleviate homelessness. This paper sets out the number and type of accommodation to be acquired. There is also an underspend within the capital programme for Temporary Accommodation of £1.4m (phase 7a), which equals a budget for 2026/27 of £3.4m.
The report also details the Local Authority Housing Fund Round 4 (LAHF R4) that makes £4,103,018 of grant funding available to the Council by the Department for Levelling Up, Housing, and Communities that can be used to supplement this overall program.
The additional LAHF grant will enable the council to deliver the capital program on more advantageous terms leveraging the grant to deliver 24 new homes rather than half the number without it.
Purpose of report
Decision
This report asks the Committee to consider the following recommendation to the Cabinet: That
1. The Director of Finance and Resources, be given delegated authority, in consultation with the Cabinet Member for Housing and Homelessness, to purchase properties as determined by the Director of Regeneration and Place, for use as temporary accommodation up to the total value of £3.4m in 2026/27; 2. The Council participate in the Local Authority Housing Fund (LAHF Round 4) in accordance with its allocation set out in the report, and for the Director of Regeneration and Place to finalise the deployment of these monies in consultation with the Cabinet Member for Housing and Homelessness; and 3. The Head of Mid Kent Legal Services be authorised to negotiate and complete all necessary legal documentation and formalities to give effect to these recommendations. 1. CROSS-CUTTING ISSUES AND IMPLICATIONS
Issue Implications Sign-off Finance, Social The overall balance of the finance, social value Head of Service Value and and environment implications is assessed as Finance Environment positive. Financially, the continued Purchase & Repair programme is intended to provide a more cost-effective and controllable supply of Biodiversity and temporary accommodation than ongoing reliance Climate Change on nightly paid accommodation, with the Council retaining an asset and being able to plan investment over the medium term. From a social value perspective, increasing the availability of good-quality, self-contained accommodation within the borough supports homelessness prevention and relief and improves stability and outcomes for households in housing need. Environmentally, the approach enables the Council to influence standards and, where refurbishment is required, to consider practical improvements to energy efficiency and condition alongside wider sustainability considerations. Impact on Accepting the recommendations will materially Development Corporate improve the Council’s ability to achieve the Project Manager Priorities corporate objectives around Quality Homes for All.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Housing and Community Cohesion Policy Advisory Committee at Maidstone and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.