Temporary Accommodation Acquisition (phase 7b) and the Local Authority Housing Fund
DecidedExecutive1 paper
AI summaryMaidstone Cabinet approves £3.4m temporary accommodation purchases for 2026/27 and joins Local Authority Housing Fund Round 4, aiming to deliver 24 new homes by 2028/29.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedProperty purchases and LAHF R4 participation both approved
Money£3.4m plus £4,103,018 grantCapital budget plus LAHF R4 grant allocation
What happens nextOfficers to begin purchasesCase-by-case approval in consultation with Lead Member
Who it affectsHomeless and Afghan resettlement householdsIncludes 12 TA units and 12 resettlement units
What was decided
Delegated authority given to the Director of Finance and Resources to purchase temporary accommodation properties up to £3.4m in 2026/27, in consultation with the Lead Member for Housing and Homelessness. Report P7
The Council will participate in the Local Authority Housing Fund Round 4 with its £4,103,018 allocation, and the Director of Regeneration and Place will finalise deployment of the monies. Report P8, P3
The Head of Mid Kent Legal Services is authorised to negotiate and complete all necessary legal documentation. Report P9
Why
Owning and refurbishing properties is more cost-effective than relying on nightly paid temporary accommodation, and the Council retains a controllable asset. Report 2.5, 6.4, 9.1
Pairing the £3.4m capital budget with the LAHF R4 grant allows 24 new homes to be delivered, roughly double what the capital programme alone would provide. Report P4, 2.16
The Purchase and Repair programme has already added 155 units across phases 1 to 7a, with 1 and 2 bedroom properties identified as best matching current demand. Report 2.2, 2.3, 2.8
What happens next
Officers will proceed with investment activity, approving each property on a case-by-case basis in consultation with the Lead Member. Report 11.1, 11.2
Ward councillors will be notified of any intended purchases within their ward. Report 11.2
DMS and Clairglow will carry out safety checks, refurbishment, gas safety testing and heating works on acquired properties. Report 2.9
The money
£3.4m Total 2026/27 budget for Phase 7b purchases and repairs Report P2, 2.7, 6.1
£2m Capital allocation agreed by Council on 25 February 2026 for Phase 7b Report P2, 6.1
£1.4m Underspend brought forward from Phase 7a Report P2, 6.1
£4,103,018 LAHF Round 4 grant allocation from MHCLG for 2026/27 to 2029/30 Report P3, 2.16
Options considered
Rejected: Continue Purchase and Repair into Phase 7b only, buying 1 and 2 bedroom properties within the £3.4m budget. Misses the opportunity to double the number of homes by using LAHF R4 grant Report 3.1, 4.1
Chosen: Continue Purchase and Repair into Phase 7b and participate in LAHF R4, delivering 24 additional homes. Most cost-effective approach, leveraging grant alongside existing capital Report 4.1, 2.16
Rejected: Do nothing and stop purchasing further properties. Increases financial risk through continued reliance on more expensive nightly paid accommodation Report 3.3
Implications
Financial: Net rental income largely covers financing costs; ongoing revenue impacts from voids, repairs and compliance will be monitored through Housing Revenue and TA budgets. Report 2.5, 6.3
Legal: Decision is within Council powers under section 1 of the Localism Act 2011 (general power of competence) and section 111 of the Local Government Act 1972. Report P11
Equalities: No change in service is proposed, so no equalities impact assessment is required. Report P12
Climate: Where refurbishment is needed, specifications will improve fabric performance, insulation, heating controls and energy efficiency where practical and cost-effective. Report 8.2, 8.5
Risk: If property need diminishes, units could be converted to private rented sector housing via Maidstone Property Holdings Limited or sold; unspent LAHF monies would be returned. Report 5.2, 5.3
Staffing: The recommendations will be delivered with current staffing, supplemented by external consultants to help source properties. Report 7.1
Who and where
Homeless households owed temporary accommodation duties by the Council Report P28, 2.12
Families on the Afghan Resettlement Programme (resettlement element) Report P28, 2.11, 2.12
Rough sleepers and households in housing need within the borough Report 2.2, 7.2
Ward councillors notified of property purchases in their wards Report 11.2
Timeline
2017: Council agreed reducing temporary accommodation use as a corporate priority Report 2.1
25 February 2026: Council agreed £2m capital allocation for Phase 7b Report P2
March 2026: Council awarded LAHF R4 funding of £4,103,018
9 June 2026: Housing and Community Cohesion Policy Advisory Committee considered the report
2026/27: 20 properties to be delivered (12 TA element, 8 resettlement element) Report 2.13, P33
2027/28: 0 properties to be delivered Report 2.13, P33
2028/29: 4 properties to be delivered (4 resettlement element) Report 2.13, P33
31 March 2030: LAHF R4 Memorandum of Understanding target delivery date for 24 homes Report 2.12, 2.16
Plain English for the jargon
LAHF R4: Local Authority Housing Fund Round 4, a government grant programme
TA: Temporary Accommodation provided to households owed a homelessness duty
ARP: Afghan Resettlement Programme
LHA: Local Housing Allowance, used to set rent levels for the portfolio
Purchase and Repair Programme: Maidstone's scheme to buy and refurbish properties for use as temporary accommodation
MHCLG / DLUHC: Ministry of Housing, Communities and Local Government, formerly the Department for Levelling Up, Housing and Communities
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item22
Resolved
That 1. Delegated authority be given to the Director of Finance & Resources, in consultation with the Lead Member for Housing and Homelessness, to purchase properties as determined by the Director of Regeneration and Place, for use as temporary accommodation up to the total value of £3.4m in 2026/27. 2. The Council participate in the Local Authority Housing Fund (LAHF Round 4) in accordance with its allocation set out in the report, and for the Director of Regeneration and Place to finalise the deployment of these monies in consultation with the portfolio holder for Housing and Homelessness. 3. The Head of Mid Kent Legal Services be authorised to negotiate and complete all necessary legal documentation and formalities to give effect to these recommendations.
Word for word from the decision Maidstone published for this meeting.Source: meetings.maidstone.gov.uk
This report provides an update on the Council’s Purchase and Repair programme for temporary accommodation, using the approved 2026/27 capital budget and underspend brought forward. The report also sets out the opportunity to supplement the programme through participation in Local Authority Housing Fund Round 4 (LAHF R4).
There is £2m allocated within the capital programme agreed by Council on 25th February 2026 for a further phase (phase 7b) of investment in purchase and repair properties for use as Temporary Accommodation to help alleviate homelessness. This paper sets out the number and type of accommodation to be acquired. There is also an underspend within the capital programme for Temporary Accommodation of £1.4m (phase 7a), which equals a budget for 2026/27 of £3.4m.
The report also details the Local Authority Housing Fund Round 4 (LAHF R4) that makes £4,103,018 of grant funding available to the Council by the Department for Levelling Up, Housing, and Communities that can be used to supplement this overall program.
The additional LAHF grant will enable the council to deliver the capital program on more advantageous terms leveraging the grant to deliver 24 new homes rather than half the number without it. Purpose of Report
Decision
This report makes the following recommendations to the Cabinet: That
1. The Director of Finance, Resources and Business Improvement, be given delegated authority, in consultation with the Lead Member for Housing and Homelessness, to purchase properties as determined by the Director of Regeneration and Place, for use as temporary accommodation up to the total value of £3.4m in 2026/27; and
2. The Council participate in the Local Authority Housing Fund (LAHF Round 4) in accordance with its allocation set out in the report, and for the Director of Regeneration and Place to finalise the deployment of these monies in consultation with the portfolio holder for Housing and Homeslessness; and
3. The Head of Mid Kent Legal Services be authorised to negotiate and complete all necessary legal documentation and formalities to give effect to these recommendations. 1. CROSS-CUTTING ISSUES AND IMPLICATIONS
Issue Implications Sign-off Finance, Social The overall balance of the finance, social value Adrian Value and and environment implications is assessed as Lovegrove - Environment positive. Financially, the continued Purchase & Head of Service Repair programme is intended to provide a more Finance cost-effective and controllable supply of temporary accommodation than ongoing reliance on nightly paid accommodation, with the Council Shelly Wilcken - retaining an asset and being able to plan Biodiversity and investment over the medium term. From a Climate Change social value perspective, increasing the availability of good-quality, self-contained accommodation within the borough supports homelessness prevention and relief and improves stability and outcomes for households in housing need. Environmentally, the approach enables the Council to influence standards and, where refurbishment is required, to consider practical improvements to energy efficiency and condition alongside wider sustainability considerations. Impact on Accepting the recommendations will materially Alison Elliott – Corporate improve the Council’s ability to achieve the Development Priorities corporate objectives around Quality Homes for Project Manager All
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.