Maidstone Borough Council
Audit, Governance and Standards Committee, Monday 27 July 2026 at 6.30pm

Internal Audit Annual Report and Annual Opinion 2025/26

Noted Finance 2 papers

AI summaryMaidstone's Audit, Governance and Standards Committee noted a sound assurance opinion on the council's 2025/26 governance, risk and control, with one weak finding in Housing Rents and an approximately £51k audit team saving.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedOn governance, risk and internal control
Moneyapproximately £51k saving76% of audit team budget spent
What happens nextInternal Quality AssessmentDue by end of August 2026
Who it affectsCouncil wide governanceAll services and risk management

What was decided

The committee noted the Head of Mid Kent Audit Partnership's annual opinion.

The committee noted the work underlying the opinion and the assurance of its independent completion under the proper standards.

Why

17 audits were completed during 2025/26, with most rated Strong or Sound and only one rated Weak, allowing a positive conclusion on the council's risk management, control and governance processes. Report P14, P15, 4.6, P35

Mid Kent Audit worked in full conformance with the new Global Internal Audit Standards and independently of officers and members. Report 1.3, 1.5, 1.6

What happens next

Complete the Internal Quality Assessment by end of August 2026 and develop a Quality Assurance and Improvement Plan, with an External Quality Assessment to follow. Report P52

Monitor progress on the five high priority actions raised, including those from the Weak rated Housing Rents audit, and report to the committee. Report 4.5, 4.13

The money

  • approximately £51k Saving to the authority from the audit team against budget Report P48
  • 351 days Audit plan budgeted days Report P47
  • 357 days Audit days delivered, equating to 102% of budgeted figure Report P47
  • £174k Predicted savings in 2026/27 from temporary accommodation changes Report P81
  • £149k Predicted savings in 2027/28 from temporary accommodation changes Report P81
  • £440,000 Temporary accommodation savings between June 2023 and January 2025 Report P82

Options considered

  • Chosen: Trial a new risk-based method for identifying audit work, prioritising essential and high priority audits before medium priority work. To ensure an appropriate level of work to reach a balanced audit opinion and to keep the plan as a live, dynamic document Report P33
  • Chosen: Move several medium and high priority audits to the 2026/27 plan, or remove them from the plan. Risk priority reviewed, or to be considered as part of LGR workstreams for the future new unitary authority Report P34

Implications

  • Financial: The audit team delivered its plan at 76% of the budgeted figure, resulting in an approximate £51k saving to the authority. Report P48
  • Risk: The Housing Rents audit identified weak controls with 3 high priority actions, and management has set up a project team to address the findings, including colleagues from finance. Report P35, 4.13, P59, P60
  • Legal: The Data Protection audit found that only one draft Appropriate Policy Document was in place for special category data, leaving the council non compliant with Schedule 1 of the Data Protection Act 2018. Report P66
  • Staffing: Recruitment challenges caused by a national shortage of local government internal auditors have been addressed through a blended approach using contractor support and a trainee programme. Report 4.3

Who and where

  • Maidstone Borough Council residents and service users, particularly housing, licensing and temporary accommodation users Report P35, P70, P80
  • Council staff in audited services including housing, data protection, IT, licensing and human resources Report P35, P62, P70, P75
  • The Audit, Governance and Standards Committee Report P52
  • Mid Kent Audit Partnership and the partner councils of Ashford, Swale and Tunbridge Wells Report 4.4

Timeline

  • March 2025: The 2025/26 audit plan was approved by the Audit, Governance and Standards Committee. Report 4.7
  • November 2025: Reports demonstrated progress against the audit plan. Report 4.7
  • Period ending 30 June 2026: Head of Internal Audit annual opinion provided. Report P12
  • End of August 2026: Internal Quality Assessment to be completed, with a Quality Assurance and Improvement Plan developed and shared with the committee. Report P52

Plain English for the jargon

  • Global Internal Audit Standards: New standards that replaced the previous Public Sector Internal Audit Standards.
  • SIRO: Senior Information Risk Owner.
  • MFA: Multi factor authentication, used to protect staff accounts from unauthorised access.
  • LGR: Local Government Reorganisation, with reference to workstreams for the future new unitary authority.
  • ROPA: Records of Processing Activities, a GDPR requirement.
  • APD: Appropriate Policy Document, required under the Data Protection Act 2018.
  • QAIP: Quality Assurance and Improvement Plan.
  • EQA: External Quality Assessment.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item23

Resolved

RESOLVED : 1. That the Head of Mid-Kent Audit Partnership’s opinion be noted. 2. That the work underlying the opinion and the Head of Mid-Kent Audit Partnership’s assurance of its independent completion in conformance with proper ... view the full minutes text for item 23.
Word for word from the decision Maidstone published for this meeting. Source: meetings.maidstone.gov.uk

Follow this further

Built from Maidstone's papers

What the report saysPro

Report to Audit, Governance and Standards Committee

June 2026

Internal Audit Annual Report and Opinion 2025/26

MAIDSTONE BOROUGH BOROUGH MAIDSTONE COUNCIL COUNCIL 1. Introduction 1.1 The Accounts and Audit Regulations 2015 require that the Council “must undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes; taking into account public sector internal auditing standards or guidance.”

1.2The Global Internal Audit Standard 11.3 (Communicating Results) refers to the Chief Audit Executive being required to make a conclusion about the effectiveness of governance, risk management and control. The Public Sector Application Note 10B states:

“In the UK public sector, a chief audit executive must prepare such an overall conclusion at least annually in support of wider governance reporting, mindful of any specific sector obligations or processes. This overall conclusion must encompass governance, risk management and control.”

1.3The work undertaken in 2025/26 was completed under the new Global Internal Audit Standards and the Public Sector application note as referred to above. These replaced the previous Public Sector Internal Audit Standards.

1.4This document is the 2025/26 Annual Report by Mid Kent Audit on the internal control environment at Maidstone Borough Council (“the Council”). The annual internal audit report summarises the outcomes of the reviews that been carried out on the Council’s framework of governance, risk management and internal control and designed to assist the Council making its annual governance statement.

1.4This report provides the annual Head of Audit Opinion and a summary of the key factors taken into consideration in arriving at that opinion as at 30 June 2026.

1.5We have completed our work in full conformance with the Global Internal Audit Standards and Public Sector Application Note. We have also worked independently, free from undue influence of either officers or Members.

1.6The Assurance ratings and action priority definitions are included at Annex 2 of this report.

1.7Details about the Mid Kent Audit Partnership are included at Annex 3 of this report. 2. Head of Internal Audit Annual Audit Opinion

Assurance ratings This report is the Head of Internal Audit’s annual Strong – Performing Controls are well designed and operating statement on the adequacy and effectiveness of the Well as intended, exposing the service to no systems of governance, risk management and uncontrolled risk. internal control within Maidstone Borough Council for the period ending 30 June 2026. Sound – Operating Controls are generally well designed effectively and operated but there are some It is my opinion that sound assurance can be placed opportunities for improvement, upon the systems in place that ensure adequate and particularly with regard to efficiency effective management, control and governance or to address less significant uncontrolled operational risks. processes exist to manage the achievement the council’s objectives. Weak – Requires support Controls have deficiencies in their design to consistently operate and/or operation that leave it exposed to The audit opinion is based on an evaluation and effectively uncontrolled operational risk and/or analysis of the work carried out by Mid Kent Audit failure to achieve key aims. during the year on the effectiveness of managing Poor –Not Operating Immediate action is required to address those risks identified by the Council and covered by effectively fundamental gaps in the control the internal audit plan or associated assurance. Not environment and / or other weaknesses all risks fall within the agreed work programme. For or non-compliance that leave the risks not directly examined reliance has been taken, organisation exposed to failure or where appropriate, from other associated sources of significant risk. assurance to support the Opinion statement.

………………………………………………………… Katherine Woodward Head of Mid Kent Audit Partnership 3. Summary of Internal Audit Activity 2025/26

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enc. 1 for Internal Audit Annual Report and Opinion 2025/26Report 573 KB DownloadRead as text
PDF
Internal Audit Annual Report and Annual Opinion 2025/26Report 66 KB Download

At this meeting

Whole meeting

Who was there

12 of 14 attended
SB
Councillor Sarah BarwickCommittee Member, present
RB
Councillor Ronald BurkeCommittee Member, apologies, sent representative
RC
Councillor Richard ConyardCommittee Member, present
GC
Councillor Grace CouchCommittee Member, apologies, sent representative
PR
Peter Ronald CoullingParish Representative, present
DD
David DobbsIndependent Member, present
RF
Councillor Rob FieldChairman, apologies
GF
Councillor Gill FortCommittee Member, present
DG
Councillor Donna GreenanSubstitute Member, present as substitute
VJ
Councillor Vanessa JonesCommittee Member, apologies
MR
Councillor Martin RoundCommittee Member, present
CR
Councillor Claudine RussellSubstitute Member, present as substitute

All 14 on the meeting page

On this subject at Maidstone

Search all
  1. Internal Audit Annual Report and Annual Opinion 2025/26This decision
  2. Internal Audit and Assurance Plan 2026/27Approved
  3. Internal Audit PartnershipAgreed

More from Maidstone Audit, Governance and Standards Committee

All decisions
MeetingDecisionOutcome
27 Jul 2026 Exempt ItemsRESOLVED : That all items on the agenda be taken in public as proposed. Decided Open
27 Jul 2026 Minutes of the meeting held on 16 March 2026RESOLVED : That the Minutes of the meeting held on 16 March 2026 be approved as a correct record and signed. Approved Open
27 Jul 2026 Minutes of the meeting held on 19 May 2026RESOLVED : That the Minutes of the meeting held on 19 May 2026 be approved as a correct record and signed. Approved Open
27 Jul 2026 2026/27 Work ProgrammeRESOLVED : That subject to the addition of the Corporate Risk Register to the list of items to be reported to the Nov... Noted Open
27 Jul 2026 Housing Benefit Subsidy Claim 2024/25RESOLVED : That the findings of the audit undertaken by Grant Thornton, the External Auditor, to certify the Housing ... Noted Open