That Maidstone Borough Council form an with Ashford, Swale and Tunbridge Wells Borough Council in accordance with the aims and structures that are set out in the Business Case, which appears as an exempt appendix to the report of the Head of Internal Audit & Risk Strategy, be agreed, subject to: a) All four partner authorities agreeing to form an . b) Final agreement on any remaining financial issues being delegated to the Director of Change and Environmental Services in consultation with the Director of Resources and Partnerships.
Word for word from the decision Maidstone published for this meeting.Source: meetings.maidstone.gov.uk
1.3.1 At an early meeting of the Mid Kent Improvement Partnership in 2008, it was identified that Internal Audit would be an appropriate service to be provided in partnership across the four MKIP authorities.
1.3.2 A report was provided to the Cabinet Member for Corporate Services on 27 March 2009 seeking approval to move to the next stage in creating a four-way partnership. The proposal had previously been discussed at a meeting of the Audit Committee on 16 February 2009.
1.3.3 The decision of the Cabinet Member was that:
D:\moderngov\data\published\Intranet\C00000146\M00000374\AI00004098\ReporttoMaidstoneCabiinetfourwaypartnership0.doc i) An Internal Audit Partnership with Ashford Borough Council, Swale Borough Council and Tunbridge Wells Borough Council, subject to the proposals on Risk Management being in place before the partnership commences and that the [Audit] committee receive a report on this matter, be agreed.
ii) The structure for the service, as set out in Appendix B to the Report of Management Team be agreed.
iii) A provisional level of 36 audits per year for Maidstone equating to a total of 540 ‘chargeable’ days audit work per annum be agreed.
iv) Delegated authority be given to the Director of Change and Environmental Services to put in place arrangements to cease the current Audit arrangements between Ashford Borough Council and Maidstone Borough Council and to progress the Audit Partnership.
v) A report be presented to Cabinet in May 2009, after all of the boroughs have considered the proposals.
Actions taken since March 2009
1.3.4 The arrangements have taken considerably longer to progress than was envisaged in March. This has been largely because of the need to take all aspects of the partnership arrangements through the decision making process of the four partner authorities and to adhere to four separate sets of policies for dealing with personnel.
1.3.5 As part of the decision making process, further financial analysis was required by Tunbridge Wells Borough Council. An interim business case was therefore prepared and reported to the Tunbridge Wells Cabinet on 23 June 2009. The interim business case contained a more detailed assessment of costs and also made comparisons with the private sector. The private sector comparisons clearly demonstrated that the in-house approach would not only be less expensive but also had a number of other benefits over the out-sourced option. Tunbridge Wells was therefore able to agree to move forward following the June meeting.
1.3.6 As all four authorities had confirmed their intention to proceed in principle, it was possible to appoint the Head of Internal Audit Partnership (in designate). The post was subject to interview on the 2 September 2009, which resulted in the appointment of Brian Parsons, the current Head of the Internal Audit Partnership for Maidstone and Ashford.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.