RESOLVED (i) that the contents of the report be noted; (ii) that the CCG Project Manager and Melanie Crass, Director of Primary Care and Resilience for Mid Essex CCG be invited to attend the next meeting of the Overview and Scrutiny Committee to provide an update on the change of status from a community hospital to a health hub.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
1.1To update Members on progress of the Maldon Health Hub Project.
Recommendation
That the contents of this report be noted.
3. SUMMARY OF KEY ISSUES
3.1This report is for Members’ information only.
3.2Members at their meeting on 30 August received an update on the Community Hospital project and were informed of the Clinical Commissioning Group’s (CCG) stated commitment to the development of an affordable primary / community care facility for central Maldon to replace St Peters Hospital.
3.3Members are asked to note that the project has now been rebadged the Maldon Health Hub project. This is because at the current time there is no certainty that beds will be provided within the new facility and it may not therefore be considered to be a “hospital”. There is a question around whether in-patient services will still be delivered and this is part of the wider review across Essex of acute activity. This is intrinsically linked to both the Success Regime and more local discussions around community beds. Consideration of options for delivery of beds through an extra care facility will be undertaken through development of the business case. The title of the Board will be updated to Maldon Health Hub Stakeholder Project Board to reflect this change.
3.4The Project Board met on Monday 12 December to receive a project update from the CCG. Board Members again expressed the desire for a more transparent approach to project reporting to report progress on key project milestones and to provide the
Agenda Item no. 10 Our Vision: Working in Partnership to make the Maldon District a better place to live, work and enjoy necessary assurance to Board Members that the project is progressing in accordance with plans.
3.5Discussions also concentrated on the need for greater certainty on how the NHS England’s (NHSE) Strategic Estates Plan, setting out how primary care needs are to be met within the District will be delivered. This includes work to address needs in Southminster, Burnham-on-Crouch, Maldon and Heybridge. The CCG confirmed that in future they will provide an update on relevant projects one week prior to Board meetings so that progress updates can be provided. Board Terms of Reference will be updated to reflect this. The Council also has officer representation at the CCG’s Local Estates Forum and they will be asked to report progress into the Project Board.
3.6The Project Manager confirmed that an operational project group had now been set up to lead on technical aspects of project delivery. Lead officers have been identified and the first meeting has been held. Maldon District Council (MDC) will be represented at these meetings.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointment of Vice-ChairpersonRESOLVED that Councillor L J Haywod be appointed Vice-Chairperson of the Overview and Scrutiny Committee for the Muni...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.