RESOLVED that a review of the Community Infractructure Levy Charging Schedule and Evidence Base be undertaken to test its suitability for Examination and, if required, Officers, in consultation with the Chairman of Planning and Licensing Committee, commission further work on the Charging Schedule and Evidence Base for consideration at Examination.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
1.1This report provides an update on the Community Infrastructure Levy (CIL). This is in light of the recent Examination Hearings into the Maldon Local Development Framework and the progression of the Maldon CIL Charging Schedule through to Examination, including recommended next steps ahead of the Examination.
Recommendation
That a review of the Community Infrastructure Levy Charging Schedule and Evidence Base is undertaken to test its suitability for Examination, and if required, Officers in consultation with the Chairman of Planning and Licensing Committee, commission further work on the Charging Schedule and Evidence Base for consideration at Examination.
3. SUMMARY OF KEY ISSUES
3.1The CIL was introduced in the Planning Act 2008 as a local charge on new development towards the provision of infrastructure. It came into force on 6 April 2010 through the Community Infrastructure Levy Regulations 2010. Development may be liable for a charge under the CIL, if the local planning authority has chosen to set a charge in its area.
3.2Most development which creates new floor space in excess of 100 square metres or involves the creation of one or more new dwellings is liable to CIL. However, certain types of development are eligible for relief or exempt from CIL.
3.3The use of ‘Section 106’ planning obligations has been scaled back by the Government to ensure there is no overlap between obligations and CIL. Pooling of obligations from more than five schemes was restricted after April 2014. This is because CIL is intended to take over the collection and pooling of funds to deal with the cumulative demands on infrastructure caused by development across a district.
3.4The Council submitted a Draft Charging Schedule to the Secretary of State on 12 September 2014. The Charging Schedule had been subject to public consultation at the Preliminary Draft Stage between January and March 2014, and again at Draft
Agenda Item no. 13 Our Vision: Working in Partnership to make the Maldon District a better place to live, work and enjoy stage in July 2014. The Inspector has indicated that the Local Development Plan (LDP) needs to be approved prior to the completion of the Charging Schedule.
3.5The Charging Schedule sets out the rates per square metre that will be applied to qualifying developments as the basis for CIL payments. To set a CIL charge, an authority must first show there is an overall need for infrastructure funding to support the LDP, and that there is a funding gap because other sources of funding will not be sufficient to provide all that is necessary.
3.6In order to do this the Council has produced an Infrastructure Delivery Plan, which is based on the draft Local Development Plan and assesses the value of the infrastructure requirements. As some of the infrastructure is being provided through the Garden Suburbs and Strategic Allocations set out in the LDP, where infrastructure is a direct requirement of those developments and will be delivered by the developers secured through Section 106 (S106) agreements, that infrastructure has not been assessed and the cost excluded from the CIL Charging Schedule.
3.7As set out in the July 2014 Draft Charging Schedule, to ‘set a CIL charge, an authority must first show there is an overall need for infrastructure funding to support the LDP, and that there is a funding gap because other sources of funding will not be sufficient to provide all that is necessary’. That report also concluded that ‘based on the current assessment of infrastructure needs, costs and funding, there is currently a funding gap totalling £78,733,452’.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.