RESOLVED (i) that the findings of the consultants employed to undertake the Historic Waterfront Revival Project be noted; (ii) that comments be collated RECOMMENDED (iii) that the Council’s Corporate Projects Task and Finish Working Group be requested to manage the next steps of the project as set out in APPENDICES 2 and 3 and below: The Consultants recommendations are set out in the following list. The main project should be an application to the Heritage Lottery Fund Parks for the People fund for work that involves: · restoring the qualities of the historic Edwardian park. · creating a park café with new toilets for the public and changing rooms for the splash park to replace the current toilet block. We (the consultants ) think that it would probably be optimal for it to incorporate a flexible space that can incorporate community events of different type and functions such as weddings. It would probably be a popular facility and offer a good return on investment. · improving the appearance of the kiosks (if not replaced) and creating a more attractive outdoor seating area in their vicinity. · extending and modernising Maldon District Museum, and employing a curator – manager. Maldon District Council (MDC) should help the museum to take a wider role in conserving and telling the whole Maldon story, including the maritime heritage. · replacing the public realm at Hythe Quay with surfacing that is more attractive and in keeping with the heritage, and reduces the impact of parking, while not compromising the operation of the businesses there. · adapting the Bailiff’s workshop and classroom occupied by the Gig Club to provide flexible ground floor space that can be used for activities of different sort. · providing a better interpretation and wayfinding system, including ... view the full minutes text for item 442.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
1.1To update this Committee on progress made towards the completion of the Coastal Revival Funded, Historic Waterfront Revival Project.
Recommendations
(i) that the findings of the consultants employed to undertake the Historic Waterfront Revival Project be noted;
(ii) that Members comments on the report be collated; and
(iii) that Council’s Corporate Projects Task and Finish Working Group be requested to manage the next stages of the project as outlined in APPENDICES 1 and 2 and paragraph 3.4.5 below.
3. THE MALDON HISTORIC WATERFRONT
3.1Introduction
3.1.1 Members may be aware that the Council was successful in obtaining £50,000 of grant funding to undertake the Historic Water front Revival Project. The project brief and details of the funding were considered by this Committee on the 12 September 2016 (Minute No. 528 refers). This Committee’s remit covers economic development and tourism and as a result has received reports on the Waterfront Revival in the first instance. A similar report will be considered by the Community Services Committee in October.
3.1.2 A grant of £50,000 was awarded to allow the Council to kick start the regeneration of Maldon Hythe and Historic Waterfront while sustaining traditional maritime knowledge, activities and skills and enhancing the historic quarter to provide a contemporary offer.
3.1.3 To deliver this aim, a feasibility study was commissioned and work undertaken with local businesses, community groups, charities and residents of the waterfront area, working together to find the best way forward and produce a coherent plan of action. The study was completed by Colliers International who pulled together a multi-skilled
Agenda Item no. 11 Our Vision: To make Maldon District a better place to live, work and enjoy team to provide options that were both sensitive to the historic setting and considered to be financially sustainable (assuming suitable funding is obtained).
3.1.4 The feasibility study ran alongside the emerging Maldon and Heybridge Central Area Masterplan (the Masterplan) and provided the Council with an early opportunity to explore, in greater detail, several projects highlighted within the master plan.
3.1.5 The Council is a key stakeholder in the Historic Waterfront area; land holdings include the Hythe Quay itself, Cooks Boatyard (under lease), Promenade Park and various buildings which could be re purposed or replaced in a wider development.
3.2Links to Maldon and Heybridge Central Area Masterplan
3.2.1 At the meeting of this committee on the 17 January 2016 Members resolved that the Masterplan be agreed (Minute No. 779 refers). The character, vitality and cultural importance of the Maldon and Heybridge Central Area are critical to the prosperity of the Maldon District and to the quality of life of the people who live there and the experience it offers to visitors. The Maldon and Heybridge Central Area incorporates Maldon Central, the Causeway Regeneration Area and the Leisure Quarter and forms the District’s focus for employment, retail, community and tourism facilities.
3.2.2 A significant amount of development is expected to take place in Maldon District over the next 15 years and the Maldon and Heybridge Central Area will be required to meet the needs of a growing population. It will be a thriving and vibrant destination that has strong connections with surrounding areas and is supported by its heritage assets, waterways and green spaces. It will need to support an increase in the number of employed people and a more diversified thriving economy in order to deliver a successful future and its role as a tourism and leisure destination needs to be strengthened.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.