Maldon and Heybridge Central Area Masterplan - Adoption as Supplementary Planning Document
AgreedPlanning3 papers
Planning and Licensing Committee agreed this item on Thursday 14 September 2017. Below is the council's own wording, with the papers it was decided on.
RESOLVED (i) that the changes to the Maldon and Heybridge Central Area Masterplan as set out in this report including removal of the bridge across the River Chelmer, be agreed; RECOMMENDED (ii) that the Maldon and Heybridge Central Area Masterplan (as set out in Appendix 1 to the report), be adopted.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
1.1To present the final version of the Maldon and Heybridge Central Area Masterplan (the Masterplan) to the Committee as per recommendation (ii) of the report to Committee dated 20 July 2017 (Minute No. 275 refers).
Recommendations
(i) that the changes to the Maldon and Heybridge Central Area Masterplan as set out in this report including removal of the bridge across the River Chelmer, be agreed;
To the Council:
(ii) that the Maldon and Heybridge Central Area Masterplan (APPENDIX 1) be adopted.
3. SUMMARY OF KEY ISSUES
3.1The Committee approved the amendments to the Masterplan following the public consultation as set out in the report to the Committee dated 20 July 2017. The Committee made a further amendment to the Masterplan to remove the bridge across the River Chelmer (Minute No. 275 refers).
3.2Our consultants have prepared a final copy of the Masterplan (APPENDIX 1) that incorporates all of the approved amendments following the public consultation and that of the Committee to remove ‘the bridge’ across the River Chelmer from the Masterplan. All text references and graphics referencing the bridge across the River Chelmer have been removed.
3.3The development and regeneration strategy for the Masterplan area states at Policy S5(5), Local Development Plan (LDP) to: ‘Increase public access next to, and enhance the setting of the riverside to create a vibrant environment that incorporates a range of uses; and at Policy S5(6) to ‘Maintain and encourage the wider use of walking and cycling across the area through an improved public realm and improved linkages and connectivity between the town centre, the Causeway, the Hythe and the
Agenda Item no. 12 Our Vision: To make Maldon District a better place to live, work and enjoy Leisure Quarter and other key attractions.’ A key project of Policy S5, LDP is: ‘Where possible ensure public access along the river is delivered and improved.’ Whilst a bridged connection across the River Chelmer has been removed from the Masterplan, the desired walking and cycling connections along the South and North Quays at Fullbridge and along Heybridge Creek remain part of the Movement and Connectivity Framework and overarching Masterplan Framework on pages 18 and 16 of the Masterplan (APPENDIX 1).
3.4To deliver the Connectivity and Movement Framework including the strategic walking and cycling routes required under Policy S5, Project 7 has been renamed ‘Heybridge Creek Connection’ and refocuses on the Policy S5 requirements for improved public access at the waterside and the delivery of improved pedestrian and cycle connections along Heybridge Creek to connect with the Hall Road Bridge across the Chelmer and Blackwater Navigation in Heybridge and the riverside route along the South Quay (Project 5 The Maldon Riverside Path) and North Quay (Project 6 North Quay Regeneration) at Fullbridge, Maldon.
3.5The revised Project 7 Heybridge Creek Connection (APPENDIX 2) has retained the existing format and added revised text as highlighted yellow that refocuses the project to deliver strategic pedestrian and cycle connections through the entire Masterplan area via public access to riverside and estuarine routes, the existing network of the bridge at Fullbridge and existing footpaths at Chandlers Quay and on Station Road.
4. CONCLUSION
4.1Policy S5 LDP requires development and regeneration to take place in the Maldon and Heybridge Central area having regard to a masterplan endorsed by the Council. As a Supplementary Planning Document to supplement Policy S5 LDP, the Maldon and Heybridge Central Area Masterplan will be an effective tool to deliver key projects and interventions in support of economic growth and a regeneration strategy to guide the development management process as a material planning consideration in development management decisions.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.