Resolved
RESOLVED that Officers continue to complete the detailed review of this project with the final report and assurances reported to this Committee in January 2018.
Overview and Scrutiny Committee decided this item on Wednesday 22 November 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that Officers continue to complete the detailed review of this project with the final report and assurances reported to this Committee in January 2018.
1.1To provide members of the Overview and Scrutiny Committee with a report providing conclusive findings on the procurement and delivery of the 2016 / 17 capital programme with particular reference to Project 180, the demolition and remediation of the St Cedd’s temporary building.
1.2This report contains eight recommendations arising from the conclusions raised in the Section 3 - Summary of Key Issues. These actions are for immediate implementation.
That the contents of this report be noted and assurance is provided to this Committee by 31 March 2018 that all of the recommendations contained in sections 3.3 – 3.11 of this report have been fully implemented.
3. SUMMARY OF KEY ISSUES
3.1This report is for Members’ information only.
3.2This purpose of this project has two key themes; the first element is to review the overall delivery of the 2016 / 17 capital programme to fully understand why the capital programme underspend by approximately £900,000 when these schemes were approved on the basis it was essential that they were delivered in 2016 / 17. The second element is a review of the procurement and delivery of Project 180 (also known as St Cedd’s and car park). Project 180 overspend in total has required approximately £60,000 of expenditure in addition to what was originally budgeted.
3.3Size of Capital Programme 2016 / 17
3.3.1 The 2016 / 17 Capital Programme approved by the Council on 4 February 2016 consisted of schemes to the value of £889,000 (Minute No. 875 refers). All of these schemes were deemed to be essential due to service failure implications or were included in the capital programme as they offered the potential to generate additional revenue streams for the Council. In itself the level of this capital programme should have been deliverable considering the resources available.
Agenda Item no. 8 Our Vision: To make Maldon District a better place to live, work and enjoy 3.3.2 However, due to underperformance of the 2015 / 16 capital programme additional schemes to the value of an additional £1.3m were added to the scheme. This then created a capital programme of approximately £2.2m which included in excess of 30 different schemes, the large majority sitting with the Customer and Communities directorate. Looking back, it is clear to see that the resource in place within this directorate was never sufficient to deliver this level of capital expenditure.
<Recommendation One>
Corporate Leadership Team (CLT) review the following year’s capital programme and provide assurance over deliverability of it in entirety before it is proposed to Members as part of the Budget setting exercise. As part of providing this assurance CLT need to consider any underspends within the current year’s capital programme.
3.4Monitoring and Review
3.4.1 Review of the 2016 / 17 reports represented to the Finance and Corporate Services Committee demonstrated that Capital Expenditure was reported to the Members on 26 September 2016 and 29 November 2016 but was not reported after this date and there is no evidence that the Capital Programme was reviewed by Members after this date. At the end of November 2016, a number of projects had not yet been started and therefore it could be concluded that these would not be delivered by year end.
3.4.2 Quarterly reviews should take place with lead officers for each project, where schemes are not deliverable by the end of the year they should be removed from the capital programme and re-bid for in the following year. The Council has foregone investment income due to cash flows being held for schemes that would not be delivered in 2016 / 17.
<Recommendation Two>
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Final Report: Procurement and Delivery of the 2016 / 17 Capital ProgrammeReport | 116 KB | DownloadRead as text |
Follow Overview and Scrutiny Committee at Maldon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jul 2026 | Minutes of the last meetingRESOLVED that the Minutes of the meeting of the Committee held on 4 December 2025 be approved and confirmed. | Approved | Open |
| 30 Jul 2026 | Appointment of Representatives to Outside Bodies and Working GroupsRESOLVED (i) That appointment to the Outside Body, Essex County Council Health Overview Policy and Scrutiny Committee... | Decided | Open |
| 30 Jul 2026 | Development Management Peer Review Action PlanRESOLVED (i) That the Committee considered the referral from the Senior Leadership Team in the light of the informati... | Decided | Open |
| 14 May 2026 | Election of ChairpersonRESOLVED that Councillor A S Fluker be appointed Chairperson of the Overview and Scrutiny Committee for the Municipal... | Decided | Open |
| 14 May 2026 | Appointment of Vice-ChairpersonRESOLVED that Councillor L J Haywod be appointed Vice-Chairperson of the Overview and Scrutiny Committee for the Muni... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.