RESOLVED (i) that the contents of the report and implementation of the recommendations (as detailed in sections 3.3 – 3.11 of the report and amended above) by 31 March 2018, be noted; (ii) that Officers report on the implementation of these recommendations to a future meeting of this Committee.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
1.1To provide Members of the Overview and Scrutiny Committee with a report providing conclusive findings on the procurement and delivery of the 2016 / 17 capital programme with particular reference to Project 180, the demolition and remediation of the St Cedd’s temporary building.
1.2This report contains seven recommendations arising from the conclusions raised in Section 3 - Summary of Key Issues. These actions are for immediate implementation.
Recommendation
That the contents of this report be presented for review and comment and assurance is provided to this Committee by 31 March 2018 that all of the recommendations contained in sections 3.3 – 3.11 of this report have been fully implemented.
3. SUMMARY OF KEY ISSUES
3.1This report is for Members’ review and comment.
3.2This purpose of this project has two key themes; the first element is to review the overall delivery of the 2016 / 17 capital programme to fully understand why the capital programme underspend by approximately £900,000 when these schemes were approved on the basis it was essential that they were delivered in 2016 / 17. The second element is a review of the procurement and delivery of Project 180 (also known as St Cedd’s and car park). Project 180 overspend in total has required approximately £60,000 of expenditure in addition to what was originally budgeted.
3.3Size of Capital Programme 2016 / 17
3.3.1 The 2016 / 17 Capital Programme approved by the Council on 4 February 2016 consisted of schemes to the value of £889,000 (Minute No. 875 refers). All of these schemes were deemed to be essential due to service failure implications, or were included in the capital programme as they offered the potential to generate additional revenue streams for the Council. In itself the level of this capital programme should have been deliverable considering the resources available.
Agenda Item no. 10 Our Vision: To make Maldon District a better place to live, work and enjoy 3.3.2 However, due to underperformance of the 2015 / 16 capital programme, additional schemes to the value of an additional £1.3m were added to the scheme. This then created a capital programme of approximately £2.2m which included in excess of 30 different schemes, the large majority sitting with the Customer and Communities directorate. Looking back, it is clear to see that the resource in place within this directorate was never sufficient to deliver this level of capital expenditure.
<Recommendation One>
Corporate Leadership Team (CLT) review the following year’s capital programme and provide assurance over deliverability of it in entirety before it is proposed to Members as part of the Budget setting exercise. As part of providing this assurance CLT need to consider any underspends within the current year’s capital programme.
3.4Monitoring and Review
3.4.1 Review of the 2016 / 17 reports represented to the Finance and Corporate Services Committee demonstrated that Capital Expenditure was reported to the Members on 26 September 2016 and 29 November 2016 but was not reported after this date and there is no evidence that the Capital Programme was reviewed by Members after this date. At the end of November 2016, a number of projects had not yet been started and therefore it could be concluded that these would not be delivered by year end.
3.4.2 Quarterly reviews should take place with lead officers for each project, where schemes are not deliverable by the end of the year they should be removed from the capital programme and re-bid for in the following year. The Council has foregone investment income due to cash flows being held for schemes that would not be delivered in 2016 / 17.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointment of Vice-ChairpersonRESOLVED that Councillor L J Haywod be appointed Vice-Chairperson of the Overview and Scrutiny Committee for the Muni...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.