RESOLVED (i) That the approach that Maldon District Council seeks to ensure that housing demand created through the provision of a new nuclear power station at Bradwell, once operational, will be within the District, and defined within a Development Plan Document, be endorsed; (ii) That workshops are provided for all Members at the earliest opportunity which will include the opportunity to provide comment on the principles of delivering housing to meet the need of Bradwell B Power Station once operational. And that in advance of any such workshops Members are provided with background papers in a timely manner.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
1.1The purpose of this report is to inform Council of the potential need to provide housing, within the District, to meet the need of Bradwell B Power Station once operational. To ensure that the Council has control of the location and magnitude of housing it is proposed to deliver a Development Plan Document (DPD), as resolved by the Council in February 2020. This report highlights the key housing issues and Member input required to deliver the DPD.
Recommendations
(i) That Members to endorse the approach that Maldon District Council seeks to ensure that housing demand created through the provision of a new nuclear power station at Bradwell, once operational, will be within the District, and defined within a Development Plan Document;
(ii) That a workshop to be provided for all Members which will include the opportunity to provide comment on the principles of delivering housing to meet the need of Bradwell B Power Station once operational.
3. SUMMARY OF KEY ISSUES
3.1Bradwell B Nuclear Power Station
3.1.1 Current Government policy is that new nuclear power stations are a key component of the County’s future energy generation strategy. The National Policy Statement for Nuclear Power Generation (NPS EN-6) (2011) explains that there is an urgent need for new nuclear power stations and identifies Bradwell as one of eight sites considered suitable for the siting of a new nuclear power station.
3.1.2 China Generation Nuclear Power Corporation (CGN) and EDF Energy are partnering together to develop proposals for the Bradwell B nuclear power station. The Stage One Consultation is currently underway.
3.1.3 Once operational it is estimated that there will be almost 1,000 jobs created at the new power station. It is envisaged that a large number of these future employees will wish
Agenda Item no. 11 Our Vision: Sustainable Council – Prosperous Future to locate in close proximity to the site of the proposed new power station within the District of Maldon.
3.1.4 The increased housing demand, resulting from the growth in operational jobs, means that it is very likely that there will be significant pressure on the existing local housing market within the District, which is likely to lead to the need to provide additional housing to meet this demand.
3.1.5 It is anticipated that there will also be wider growth in the local economy during both the construction and the operational phases, such as support services and supply chain sectors. It is anticipated that expansion of the local economy will be likely to generate additional growth in the local labour force and population. This will generate demand for additional housing and associated infrastructure and will further impact on the existing local housing market.
3.1.6 Planning permission to build Bradwell B (plus associated developments such as roads and construction worker accommodation), a Nationally Significant Infrastructure Project (NSIP), would be granted through a Development Consent Order (DCO). This would be granted by the relevant Secretary of State, who would be advised by the UK Planning Inspectorate.
3.1.7 A DCO is different from normal Town and County Planning Act (TCPA) planning applications where the decision maker is the relevant local authority. In the case of DCOs Local Authorities do not have a decision-making role but are important consultees throughout the development of the proposals.
3.1.8 However it is possible for the longer-term housing demand to be identified and delivered via the Local Development Plan (LDP) process, and in this case through the development of a Development Plan Document (DPD).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.