It was further agreed that the Lead Specialist, Planning Policy and Implementation circulate information on the following outside of the meeting:- Ø Clarification from Essex County Council (ECC) regarding the s106 Toucan Crossing spend; Ø A breakdown of the health monies in respect of where it was generated and where it had been spent; Ø The net figure on parking spend; Ø Clarification from ECC regarding the investment in Burnham-on-Crouch primary school; Ø A breakdown of s106 spend on youth facilities. It was noted that spend had been delayed due to Covid however capacity was now in place to move forward She concluded by advising that meetings were now taking place on a 6 weekly cycle with NHS, Education and Highways which was a much better way of interacting and encouraging funding coming forward. The Chairman then moved the recommendations, duly seconded by Councillor Fleming, and the Committee agreed these by assent. reSOLVED (i) That the Committee considered the update on Section 106 planning obligations. (ii) That the Committee approved the Maldon District Council Infrastructure Funding Statement for the financial year 2021 - 2022 for publication as set out in appendix 1 .
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
Report to Performance, Governance and Audit Committee
Purpose of the report
1.1The purpose of this report is to provide Members of the Performance. Governance and Audit Committee (PGA) with an update on the monitoring of Section 106 planning obligations and to seek approval of the Maldon District Infrastructure Funding Statement for the financial year 2021/22, in accordance with the Council’s legal duties.
Recommendations
(i) That the Committee considers the update on Section 106 planning obligations.
(ii) That the Committee approves the Maldon District Council Infrastructure Funding Statement for the financial year 2021 - 2022 for publication as set out in APPENDIX 1.
3. SUMMARY OF KEY ISSUES
3.1As set out in the detail of APPENDIX 1 of this paper the following funds were received and spent in regard to S106 planning obligations during the financial year 2021 - 2022. Funding received in 2021/22 £167,435.89 Funding Spent in 2021/22 £63,058.45
3.2As of 31 March 2022 the Council is expecting £1,053,314.40 to be remitted from developers for infrastructure across the District. The triggers to collect the funding associated with the S106 agreements are being monitored in association with the function of monitoring housing commencements and completions in the District and once these triggers are met, the funding is being invoiced.
3.3During the financial year 2021 – 2022 the Council did not have to remit back to developers any funding because the clawback date within the S106 agreements had been met without spending the relevant funding.
3.4It is important to note that S106 contributions may only be spent on new facilities or improvements to facilities where the new development has, at least in part, contributed to the need for that facility or will have an impact on existing facilities. This means that funding will normally be invested in facilities based in the same
Our Vision: Sustainable Council – Prosperous Future locality or catchment area in which the contributing development is located unless it is contributing to the funding of strategic infrastructure.
3.5The IFS only relates to S106 obligations for which Maldon District Council is legally responsible for ensuring compliance. It does not cover:
a. Where Essex County Council (ECC) is the Local Planning Authority (LPA) (Minerals and Waste Applications); and/or b. Where MDC determined the planning application, but where ECC is signatory of the S106 to the effect that it is directly responsible for compliance of its contributions; and/or c. Section 278 highway work agreements between developers and ECC.
Appendix A of the IFS sets out the details of the ECC`s S106 Funding details for information only.
4. CONCLUSION
4.1In light of the report above and the matters before it, the PGA Committee has the following options:
4.2Option 1 – It can discuss the report and accept the recommendations set out in Section 2 of this report.
4.3Option 2 – The Committee can discuss the report and partially accept the recommendations. It could seek officers to make amendments to the IFS to address any issues which the Committee raises as a concern. If the Committee is not minded to approve the IFS, it will then have to delegate the final approval of an updated version to the Director of Strategy, Performance and Governance, in consultation with the Chairman of the PGA Committee.
5. IMPACT ON STRATEGIC THEMES
5.1The Strategic Themes of Place seeks to ensure that the council can demonstrate that it has tried to secure investment in the District’s infrastructure alongside development.
6. IMPLICATIONS
(i) Impact on Customers – Monitoring S106 agreements ensures that financial contributions are remitted in an effective and efficient way and they are then available to spend on infrastructure which will help the residents/businesses of Maldon District.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Performance, Governance and Audit Committee at Maldon and we tell you when its next papers are published, before the meeting rather than after it.
External Audit: Building Back AssuranceRESOLVED that the Committee received, considered, and accepted the following: (i) the outcomes of the risk assessment...
Corporate Performance Quarter 1RESOLVED (i) T hat the Committee received, considered and reviewed the information as set out in the report and Appen...
Review of Corporate Risk Quarter 1RESOLVED (i) That the Committee reviewed and provided comments and feedback on the Corporate Risk Register as set out...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.