Infrastructure Funding Statement and Section 106 Six Monthly Update
ApprovedFinance2 papers
Performance, Governance and Audit Committee approved this item on Thursday 27 July 2023. Below is the council's own wording, with the papers it was decided on.
RESOLVED (i) That the Committee considered the update on Section 106 planning obligations. (ii) That the Committee approved the Maldon District Council Infrastructure Funding Statement for the financial year 2022 - 2023 for publication as set out in appendix 1.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
Report to Performance, Governance and Audit Committee
Purpose of the report
1.1This report covers the following matters.
1.1.1 A report on the year 2022 – 2023 to provide Members with an update on Section 106 infrastructure projects. It sets out the progress on section 106 projects delivery by Maldon District Council, NHS England and Essex County Council. Details of S106 agreements can be found here.
1.1.2 The presentation of the Maldon District Council Infrastructure Funding Statement (IFS) for the financial year 2022 – 2023 to be published on the Council`s website.
Recommendations
(i) That the Committee considers the update on Section 106 planning obligations.
(ii) That the Committee approves the Maldon District Council Infrastructure Funding Statement for the financial year 2022 - 2023 for publication as set out in APPENDIX 1
3. SUMMARY OF KEY ISSUES
3.1As set out in the Maldon District Council Infrastructure Funding Statement for the financial year 2022 – 23, APPENDIX 1 of this paper, the following funds were received and spent in regard to S106 planning obligations during the financial year 2022 - 2023.
Funds In £1,110,232.00 Funds Out £416,203.98
3.2The Funds remitted into the Council were in regard to the following funding streams.
Type of S106 Funding In Affordable Housing £64,448.00 Youth Facilities £621,021.70 Monitoring £850.00
Our Vision: Where Quality of Life Matters Health £423,912.30 Total £1,110,232.00
3.3There is now a substantial fund, £853,364.39, in regard to youth facilities projects, with £621,021.70 being remitted in the financial year 2022 – 2023 from the development at strategic site 2(a) Land South of Wyke Hill and Limebrook Way, Maldon. Officers are now looking to scope out relevant projects within the terms of the clauses in the S106 agreements to bring forward Youth Facilities in Maldon and Burnham-on-Crouch.
3.4With regard to the Health funding received. The majority of it, £389,847.30, was also from the development at strategic site 2(a) and was for improvements to health care facilities within the vicinity of the site, including the improvements of Longfield Medical Centre and Blackwater Medical Centre or such other facilities. £34,065.00 was from site 2(k) Marsh Road, Burnham-on-Crouch for additional primary health care facilities, though the S106 does not specify where the funds should be spent in the District.
3.5The Funds Out were remitted for the following projects.
Type of Funding Amount Project Affordable Housing £82,000.00 Community Housing Officer Affordable Housing £4250.00 Valuation Work for the purchase of affordable housing. Affordable Housing £207,851.45 Pre-planning submission work for the delivery of affordable housing in Heybridge. Youth Facilities £87,450.91 As per S106 agreement these funds were passed to Site 2d as pooled contributions to be spend on youth facilities’ on site. Open £19,291.62 As per S106 agreement these funds Space(LEAPS&NEAPS were passed to Site 2d as pooled contributions to be spend on Open Space, LEAPS & NEAPS on site. Health £15,360.00 Passed to the NHS for an options appraisal to improve health facilities in Burnham on Crouch
3.6It is acceptable to spend S106 funding on options appraisals/design and preparation work providing that work does not step outside the clauses of the relevant agreements and delivers on the ground what the agreement stipulates it should deliver. If that delivery fails, then the funding for the preparatory work should be paid back into the S106 funding. This is made clear to those that call on S106 funding for this type of work.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Performance, Governance and Audit Committee at Maldon and we tell you when its next papers are published, before the meeting rather than after it.
External Audit: Building Back AssuranceRESOLVED that the Committee received, considered, and accepted the following: (i) the outcomes of the risk assessment...
Corporate Performance Quarter 1RESOLVED (i) T hat the Committee received, considered and reviewed the information as set out in the report and Appen...
Review of Corporate Risk Quarter 1RESOLVED (i) That the Committee reviewed and provided comments and feedback on the Corporate Risk Register as set out...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.