RESOLVED ( i ) that the update on the progression of National Highways Nationally Significant Infrastructure Project Development Consent Order (DCO): the A12 Chelmsford to A120 Widening Scheme, its context, engagement to date, the planning performance agreement, the project’s next steps and estimated timescales be noted; (ii) that the Maldon District A12 DCO Engagement Mandate as set out in 3.6 be endorsed for use by Officers and/ or appointed witnesses at Pre-Examination and Examination stages confirming the extent of the Council’s support and concern as a Host Authority concerning the A12 Chelmsford to A120 Widening National Strategic Infrastructure Project (NSIP) ; (iii) that the Director of Strategy, Performance and Governance be given delegated powers to appoint (in writing) specific Officers, as well as external contractors if required, to act as witnesses for Maldon District Council for the A12 DCO Examination; and (iv) that the Director of Strategy, Performance and Governance be given delegated authority in consultation with the A12 DCO Member Consultation Group as defined in 3.7 to approve any formal response or statement, as required to be made, from time to time, during the Pre-Examination and Examination stages to either National Highways, or the Planning Inspectorate.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
1.1The purpose of this report is to update the Council on the progress that has been made by National Highways on its A12 Chelmsford to A120 Widening Scheme Development Consent Order (DCO) and to seek the Council’s approval of an Engagement Mandate that will be used when engaging further with National Highways, neighbouring authorities and the Planning Inspectorate during the Examination stage of the DCO.
Recommendations
(i) that the update on the progression of National Highways Nationally Significant Infrastructure Project Development Consent Order: the A12 Chelmsford to A120 Widening Scheme, its context, engagement to date, the planning performance agreement, the project’s next steps and estimated timescales be noted;
(ii) that the Maldon District A12 DCO Engagement Mandate as set out in 3.6 be endorsed for use by Officers and/ or appointed witnesses at Pre-Examination and Examination stages confirming the extent of the Council’s support and concern as a Host Authority concerning the A12 Chelmsford to A120 Widening National Strategic Infrastructure Project (NSIP);
(iii) that the Director of Strategy, Performance and Governance be given delegated powers to appoint (in writing) specific Officers, as well as external contractors if required, to act as witnesses for Maldon District Council for the A12 DCO Examination; and
(iv) that the Director of Strategy, Performance and Governance be given delegated authority in consultation with the A12 DCO Member Consultation Group as defined in 3.7 to approve any formal response or statement, as required to be made, from time to time, during the Pre-Examination and Examination stages to either National Highways, or the Planning Inspectorate.
Our Vision: Sustainable Council – Prosperous Future 3. BACKGROUND
3.1Project Context
3.1.1 The A12 is an important economic route in Essex and across the east of England. It provides the main south-west / north-east route through Essex and Suffolk, connecting Ipswich with London and the M25.
3.1.2 The A12 Chelmsford to A120 Widening Scheme is a ‘highways’ NSIP as defined by Section 22 of Planning Act 2008 (PA2008) (as amended). It is a proposal to widen the A12 from two to three lanes between Junction 19 (Boreham Interchange, Chelmsford) and Junction 25 (A120 Marks Tey Interchange, Colchester).
3.1.3 The project would be delivered by National Highways, a government-owned company charged with operating, maintaining and improving England’s motorways and major A-roads; also referred to as the Strategic Road Network (SRN). National Highways is delivering £27.4bn of investment in the SRN between 2020 and 2025 as described in the Department for Transport’s Road Investment Strategy 2 (RIS2), which includes a commitment to fund the A12 NSIP scheme.
3.1.4 National Highways advise that the section proposed for widening carries high volumes of traffic, with up to 90,000 vehicles every day. Between 9%-12% of this traffic is in the form of Heavy Goods Vehicles (HGVs), which underlines its importance to freight connection, particularly the Ports of Felixstowe and Harwich. It is also an important commuter route, which leads to congestion and delays and means average speeds are particularly slow, despite its A-road status.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.