Review of Corporate Risk - Quarter 2

Decided Finance 3 papers

Performance, Governance and Audit Committee decided this item on Thursday 19 January 2023. Below is the council's own wording, with the papers it was decided on.

Item493

Resolved

RESOLVED (i) That Members reviewed the Corporate Risk Register ... view the full minutes text for item 493.
Word for word from the decision Maldon published for this meeting. Source: democracy.maldon.gov.uk

Follow this further

Built from Maldon's papers

What the report saysPro

Report to Performance, Governance and Audit Committee

Purpose of the report

1.1The Risk Management Policy requires this Committee to undertake a quarterly review of the Corporate Risk Register as assurance that the corporate risks are being managed effectively.

Recommendations

(i) That Members review the Corporate Risk Register in APPENDIX 1 and provide comment and feedback for consideration.

(ii) That Members review progress of the Corporate Risk Mitigating actions in APPENDIX 2 and provide comment and feedback for consideration.

(iii) That Members are assured through this review that corporate risk is being managed effectively.

(iv) That Members challenge risk where the Committee feels that the Council’s corporate goals may not be achieved.

3. SUMMARY OF KEY ISSUES

3.1APPENDIX 1 shows a summary and detailed table of the Corporate Risk Register, the latest ratings and officer commentary. The control strength of each risk is also now included as well if there are any active mitigating actions. APPENDIX 2 shows progress of all active mitigating actions. The criteria for this is set out in the updated Risk Management Framework adopted in Septembers PGA committee.

3.2All risks were subject to a detailed review considering the new Risk Management Framework policy adopted by PGA in September and recommendations made by the Risk Management Audit in November.

Amendments made were:  Quarterly report amendment to include each risk control rating - APPENDIX 1  Performance Overview of Corporate risks – APPENDIX 1  R31 retitled, no other details changed  Was: Resources and operating staffing structure is not sufficient for resilience  Now: Inadequate staffing structure and resource for resilience

. Our Vision: Sustainable Council – Prosperous Future  R32 retitled, no other details changed  Was: Failure to manage the operational impact of the cost-of- living crisis  Now: Uncertainty of the cost-of-living crisis impacts  Quarterly reporting of mitigating actions to PGA – APPENDIX 2

3.3Increased/New Risks since last quarter  Increased Risk (Likelihood) – R1 - Failure to safeguard children and vulnerable adults  Decreased Risk (Likelihood) - R3 - Failure to target services/influence partners effectively to support identified housing needs of increasing aging population  Decreased Risk (Likelihood) - R29 - Failure to deliver services as a result of COVID- 19  Note concerning increasing risks from service level: Service level risks are identified and monitored in Service Plans by the relevant Service Plan Owners. They are then escalated, if deemed appropriate and necessary, to committee level for consideration.

4. CONCLUSION

4.1Overall, no major Corporate Risk Register concerns have been raised. The aftereffects of COVID19, and the economical and cost of living crisis is a presence on the landscape, however the Council continues to mitigate any risks caused by this. Work continues to ensure all risks are mitigated, and where possible, working towards their closure.

5. IMPACT ON STRATEGIC THEMES

5.1It is important that risk is monitored and managed effectively, to ensure that Maldon District Council progresses towards and/ achieves its stated outcomes.

6. IMPLICATIONS

(i) Impact on Customers – Those risks in the Corporate Risk Register are defined as having a wider impact on our customers and delivery. The monitoring and mitigation of these will reduce the impact on customers.

(ii) Impact on Equalities – None.

(iii) Impact on Risk – If risk is not managed effectively by the Council, it puts the Councils strategic delivery at risk and increases unnecessary exposure to potential, operational, reputational, or regulatory consequences.

(iv) Impact on Resources (financial) – All risk management is undertaken within existing planned budget. Exceptions being for a potential enactment of a recommendation outside of pre-defined resource.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 276 KB Download
PDF
Appendix 2Appendix 2 201 KB Download
PDF
Review of Corporate Risk: Quarter 2Report 240 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 10 attended
WS
Councillor Wendy Stamp CCChairperson, present
MJ
Councillor Mrs Jane L Fleming CCVice-Chairperson, present
MR
Councillor Michael R EdwardsCommittee Member, present
AS
Councillor Adrian S FlukerCommittee Member, present
AL
Councillor Anne L HullCommittee Member, present
JV
Councillor John V KeyesCommittee Member, absent
NJ
Councillor Nick J SkeensCommittee Member, absent
EL
Councillor Emma L StephensCommittee Member, apologies
MJ
Councillor Mrs Jeanette C StiltsCommittee Member, present
MM
Councillor Mrs Maddie E ThompsonCommittee Member, present

On this subject at Maldon

Search all
  1. Review of Corporate Risk - Quarter 2This decision
  2. Review of Corporate Risk Quarter 1Decided
  3. Review of Corporate Risk - Quarter 4Decided
  4. Review of Corporate Risk - Quarter 3Agreed
  5. Review of Corporate Risk - Quarter 4Decided
  6. Review of Corporate Risk - Quarter 3Decided

More from Maldon Performance, Governance and Audit Committee

All decisions
MeetingDecisionOutcome
17 Sep 2026 Minutes of the last meetingRESOLVED that the Minutes of the meeting of the Committee held on 16 July 2026 be approved and confirmed. Approved Open
17 Sep 2026 External Audit: Building Back AssuranceRESOLVED that the Committee received, considered, and accepted the following: (i) the outcomes of the risk assessment... Decided Open
17 Sep 2026 Corporate Performance Quarter 1RESOLVED (i) T hat the Committee received, considered and reviewed the information as set out in the report and Appen... Decided Open
17 Sep 2026 Review of Corporate Risk Quarter 1RESOLVED (i) That the Committee reviewed and provided comments and feedback on the Corporate Risk Register as set out... Decided Open
17 Sep 2026 Annual Governance Statement Actions UpdateRESOLVED that the Committee had reviewed and commented on the Annual Governance Statement’s table and updates set out... Decided Open