RESOLVED (i) That the revised Local Development Scheme 2023 to 2027 be approved for publication on the Council’s website; (ii) That the Assistant Director for Planning and Implementation be granted delegated authority in consultation with the Chairperson of ... view the full minutes text for item 248.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
1.1To update Members on the timetable of the Local Development Plan (LDP) Review and present a revised statutory timetable and Local Development Scheme (LDS) for approval that can be maintained from this point in accordance with legal duties. This report is predicated on the approval of the previous report LDP Preferred Options. If the previous report is not agreed, then this report will need to be deferred because the timetable of the LDP will have to be reassessed.
Recommendations
(i) That the revised Local Development Scheme 2023 to 2027 be approved for publication on the Council’s website;
(ii) That the Assistant Director for Planning and Implementation be granted delegated authority in consultation with the Chairperson of the Strategy and Resources Committee to amend the Local Development Scheme timetable, should the timetable slip, to ensure the Council complies with legal requirements on maintaining the Local Development Scheme.
3. SUMMARY OF KEY ISSUES
3.1To plan, monitor, manage and understand the risks to the LDP Review as a project it is important to set out a revised timetable not only for the Council but also for the wider public, statutory stakeholders and organisations such as the Planning Inspectorate. This is so they know approximately when the Council will be publishing documents and undertaking consultation and when they therefore may need to engage.
3.2The broad timetable associated with local plans for Councils is legally called a ‘Local Development Scheme’. The LDS is required to be published under Section 15 of the Planning and Compulsory Purchase Act 2004 (as amended) and also maintained to ensure it remains in date between editions. A draft of the revised LDS is appended to this report at APPENDIX A.
3.3In late 2022, work on the LDP Review was paused because Members wished to have reassurance of the methodology of the review. Furthermore, the local elections made it impossible to set out an amended LDS timetable for the LDP Review until this point in time. With the consideration of the Growth Options and reducing the number down from the seven high level options to three which can be tested, a reset of the timetable can now be programmed more accurately. This is because, the
Our Vision: Where Quality of Life Matters remaining options will require a substantial amount of analysis and testing work to be carried out on them before Members can have enough information and evidence to inform their choice of a Preferred Option. That work comes at a human resources and financial cost for Maldon District Council, Essex County Council (ECC) and other statutory partners including the NHS. This is directly connected to the timetable because the clock on the LDP Review timetable can only be restarted when the number of growth options is reduced in number to allow the more substantial work to begin. A key piece of this work is transport modelling which is going to take a minimum of ten months to complete.
3.4The broad timetable in the LDS at APPENDIX A is predicated on getting through the work associated with the preparation of a Preferred Growth Option, including working with Duty to Co-operate Partners.
3.5Further updates to the LDS are likely in the future after Preferred Options to ensure the Council remains on track for preparing the LDP Review; however, a delegation is being sought to enable in-year edits to the timeline to take place to ensure it remains up-to-date in real-time to comply with legal duties.
4. IMPACT ON PRIORITIES AS SET OUT IN THE CORPORATE PLAN 2023 - 2027
4.1Supporting our communities
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.