Maldon District Council
Overview and Scrutiny Committee, Thursday 4 December 2025 at 7.30pm

Member Scrutiny Request - Leisure Contract: Communications and Messaging (request by Councillor A M Lay)

Decided Scrutiny 2 papers

AI summaryMaldon Overview and Scrutiny Committee agreed to fold a Working Group review of leisure contract communications into the wider Post-Implementation Review. Concerns centred on the gap between the November 2024 contract award and engagement with affected sports hall users.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedWorking Group's assessment to be included
MoneyNot stated
What happens nextPost-Implementation ReviewDetailed scrutiny via Committee workplan
Who it affectsBlackwater Leisure Centre usersSports hall groups needing relocation

What was decided

The Committee agreed to include the Working Group's conclusions on the communications and messaging scrutiny request as part of the proposed Leisure Contract Post-Implementation Review. Report P2

The Committee accepted the Working Group's initial assessment covering the timeline of decisions and communications, the timing of user contact, ownership of communications, and the future role of the Leisure Contract Working Group. Report 4.1

The scope is limited to communications: there is no review of the procurement process or the Council's decision to award the contract to Places Leisure. Report 3.2

Why

Councillor A M Lay raised concerns that commitments made by officers at the November 2024 Council meeting on owning the communications process had not been followed through with members. Report 3.1

Members were concerned that the public first learned of the sports hall changes from the local newspaper and social media, that the initial press release suggested engagement in weeks rather than months, and that the Council did not show visible ownership of communications. Report 3.6, 3.7

Officers told the Working Group that liaison with affected users had been good, that incorrect information had circulated on social media, and that relocation of all affected users had been satisfactorily resolved. Report 3.8

What happens next

The Committee is recommended to add the item to its scrutiny workplan for a more detailed review covering the points listed in the Working Group's conclusion. Report 4.1, P2

The detailed review will look at whether the leisure contract working group should have continued beyond procurement to oversee implementation issues such as engagement and communications. Report 3.9, 4.1

Options considered

  • Chosen: Add the communications scrutiny to the proposed Leisure Contract Post-Implementation Review. Allows a detailed review of the timeline, user contact, ownership of communications and working group role without revisiting the procurement decision Report P2, 4.1

Implications

  • Other: Individual scrutiny reviews will enable the impact on customers of the leisure facilities to be assessed. Report P20
  • Equalities: Equalities are considered as part of the reporting on review work undertaken by officers. Report P21
  • Risk: Scrutiny reviews enable potential corporate risks to the organisation and their mitigation to be identified. Report P22
  • Financial: Scrutiny reviews offer the potential for an assessment of financial impact to the organisation. Report P23
  • Staffing: Scrutiny reviews offer the potential for an assessment of any resource impact to the organisation. Report P24

Who and where

  • Users, groups and clubs of the Blackwater Leisure Centre sports hall displaced by the conversion to a gym and Clip & Climb facility Report 3.2, 3.5
  • Members of Maldon District Council receiving communications on the contract Report 3.1, 3.6
  • Customers of the Council's leisure facilities generally Report P20

Timeline

  • 14 November 2024: Council decision to award the new leisure contract to the preferred bidder Places Leisure Report 3.1
  • 29 November 2024: First press release announcing the contract award and signalling engagement with members and users in the coming weeks Report 3.3
  • April 2025: Contract completed and issued, following legal work after the November 2024 award Report 3.4
  • April to May 2025: Engagement with the contractor on whether the sports hall work would be deliverable that year or the next Report 3.4
  • 30 May 2025: Start of meaningful engagement with existing users of the sports hall Report 3.4
  • 5 June 2025: Joint statement from Places Leisure and the Council confirming the August 2025 start of works and commitments to assist affected users Report 3.5
  • August 2025: Closure of the main sports hall at Blackwater Leisure Centre for conversion into a gym and Clip & Climb facility Report 3.5

Plain English for the jargon

  • Post-Implementation Review: A review carried out after a contract has been awarded and is being delivered, to assess how it is working in practice.
  • Clip & Climb: An indoor climbing attraction described in the report as part of the proposed new facilities at Blackwater Leisure Centre.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item378

Resolved

RESOLVED t hat having received the report on the Working Group’s initial assessment, the conclusions of the Working Group be included as part of the proposed Leisure Contract Post-Implementation Review.
Word for word from the decision Maldon published for this meeting. Source: democracy.maldon.gov.uk

Follow this further

Built from Maldon's papers

What the report saysPro

Report to Overview and Scrutiny Committee

Purpose of the report

1.1The purpose of this report is to inform the Committee of its initial assessment of this scrutiny request.

Recommendation

That the Committee receives this report of the Overview and Scrutiny Committee Working Group’s initial assessment, and by way of an outcome, agrees to include the Working Group’s conclusions on this request as part the proposed Leisure Contract post-implementation review.

3. SUMMARY OF KEY ISSUES

3.1A scrutiny item request has been submitted by Councillor A M Lay as reflected in the proforma at APPENDIX A. This request focuses on the communications and messaging following the decision by the Council on 14 November 2024 to award a new leisure contract to its preferred bidder Places Leisure. Councillor Lay informed the Overview and Scrutiny Committee Working Group (the Working Group) that despite the commitments given by Officers to that Council meeting in terms of ownership of this process, subsequent events had impacted on Members.

3.2A significant implication of this new contract was the proposal by the contractor to change the facilities offered within the existing sports hall at the Blackwater Leisure Centre, such that certain users/groups would not be able to continue and would need to be found alternative facilities elsewhere. There is no request to review or scrutinise any aspect of the procurement process leading to or the Council’s decision in relation to the leisure contract.

3.3The first press release which announced the award of contract was issued on 29 November 2024 and referred to the number of exciting developments and significant investment in the various leisure facilities in the District and stated that over the coming weeks Places Leisure would be engaging with their existing members and centre users to explain what the changes and the new facilities will mean to them.

3.4Details of the significant investment, in particular the proposed upgrading of facilities in the sports hall, were included in the report to Council on 14 November 2024, and at the Council meeting Officers gave an assurance on the need to contact those users affected by the proposed changes. There was however a time gap between the contract award decision and the actual completion / issue of the contract in April

Our Vision: Where Quality of Life Matters 2025 due to the legal work involved. There then followed engagement with the contractors during April and May 2025 to establish whether the proposed work to the sports hall would be deliverable this year or next. This then impacted on the ability to engage meaningfully with existing users until 30 May 2025, and any other forms of communication would have been premature.

3.5A joint statement on behalf of Places Leisure and the Council was issued on 5 June 2025 in which it was explained that the first phase of the new investment was due to begin in August 2025. This would result in the closure of the main sports hall to allow for major work to be completed to turn the current space into a state-of-the-art Gym and Clip & Climb facility. A commitment was made to work closely with and assist users of the sports hall, including regular groups and clubs, to provide temporary and permanent alternative options. Meetings would be arranged with the impacted groups to discuss relocation options.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 274 KB Download
PDF
Member Scrutiny Request: Leisure Contract: Communications and Messaging (request by Councillor A M Lay)Report 230 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
SJ
Councillor Simon J N MorganChairperson, apologies
PL
Councillor Paula L SpenceleyVice-Chairperson, present
VJ
Councillor Vanessa J BellCommittee Member, present
JR
Councillor James R Burrell-CookCommittee Member, present
TF
Councillor Tony FittockCommittee Member, present
LJ
Councillor Linda J HaywoodCommittee Member, present
AM
Councillor Andrew M LayCommittee Member, present
CP
Councillor Clive P MorleyCommittee Member, present
EL
Councillor Emma L StephensCommittee Member, present
NJ
Councillor Nikki J SwindleCommittee Member, present

On this subject at Maldon

Search all
  1. Member Scrutiny Request - Leisure Contract: Communications and Messaging (request by Councillor A M Lay)This decision
  2. Member Scrutiny Request - Leisure Contract: Post Implementation Review (request by Councillor E L Stephens)Decided
  3. Member Scrutiny Request - Local Plan Policy H2 Housing MixDecided
  4. Member Scrutiny Request - Planning Services PerformanceDecided
  5. Member Scrutiny Request - Councillor S J N Morgan - Planning Appeal at Church Road, Wickham BishopsDecided
  6. Overview and Scrutiny Committee - Member Scrutiny Request Outcome - Corporate Project - Land at HeybridgeNoted

More from Maldon Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
30 Jul 2026 Minutes of the last meetingRESOLVED that the Minutes of the meeting of the Committee held on 4 December 2025 be approved and confirmed. Approved Open
30 Jul 2026 Appointment of Representatives to Outside Bodies and Working GroupsRESOLVED (i) That appointment to the Outside Body, Essex County Council Health Overview Policy and Scrutiny Committee... Decided Open
30 Jul 2026 Development Management Peer Review Action PlanRESOLVED (i) That the Committee considered the referral from the Senior Leadership Team in the light of the informati... Decided Open
14 May 2026 Election of ChairpersonRESOLVED that Councillor A S Fluker be appointed Chairperson of the Overview and Scrutiny Committee for the Municipal... Decided Open
14 May 2026 Appointment of Vice-ChairpersonRESOLVED that Councillor L J Haywod be appointed Vice-Chairperson of the Overview and Scrutiny Committee for the Muni... Agreed Open