Strategy and Resources Committee, Thursday 29 January 2026 at 7.30pm

Budget Monitoring Report - Period 8 (end November 2025)

Decided Committee 5 papers

AI summaryMaldon District Council's Strategy and Resources Committee noted a £104k revenue underspend forecast at 30 November 2025, with capital delivery also tracking below the revised budget by £1,324k.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedRevenue underspend forecast, capital slippage noted
Money£104k under revenue budget0.7% of £13,874k net service budget
What happens nextContinued monitoring through 2025/26Capital slippage to next year expected
Who it affectsCouncil finances and capital programmeAll services, capital schemes, reserves

What was decided

The Committee noted the forecast revenue outturn at 30 November 2025 is £104k under budget, 0.7% against the net service budget of £13,874k. Report P4

The Committee noted the forecast capital outturn of £5.656m against a revised budget of £6.980m and the schemes completed in the year so far. Report P5, P17

The Committee approved movements in Earmarked Reserves set out in Appendix 3 and noted the revenue budget reconciliation in Appendix 4. Report P6, P7

Why

Strong investment income and better than expected planning receipts drove the revenue underspend, partially offsetting unbudgeted I.T. maintenance costs. Report P13

Many capital projects start early in the year with completions typically arriving in the second half, explaining the apparent in-year underspend. Report P16

Officers reported operational budgets are well managed within allocated limits, giving assurance the starting point for next year's budget is sound. Report 3.2, 4.1

What happens next

Officers will continue financial monitoring through to 31 March 2026, with capital slippage to the following year anticipated. Report 3.1, 4.3

The financial position will be scrutinised in advance of local government reorganisation as part of planning for LGR delivery. Report P35

The money

  • £104k Forecast revenue underspend (0.7% of net service budget) Report P4
  • £13,874k Net service revenue budget 2025/26 Report P4
  • £240k Projected revenue underspend before transfer to reserves Report P12
  • £5.656m Forecast total capital programme delivery Report P5
  • £6.980m Revised capital budget 2025/26 Report P5
  • £1,324k Forecast capital underspend against revised budget Report P15
  • £255k Outstanding general fund debt at 30 November 2025 Report P19
  • £33k General debt written off to end November 2025 Report P20
  • £165k Council tax debt written off or written down Report P20
  • £103k Business Rates debt written off or written down Report P20
  • £301k Total collectible amounts reduced in year to date Report P20
  • £1,030k Bad debt provision set up at start of year Report P20

Options considered

  • Chosen: Note forecast revenue outturn of £104k under budget. Operational budgets are well managed and income is exceeding expectations. Report P4, 4.1
  • Chosen: Note forecast capital outturn of £5.656m against £6.980m. Capital schemes are being delivered largely within budget, with some slippage to next year. Report P5, 4.3
  • Chosen: Approve movements in Earmarked Reserves. Reserves are maintained at a robust level compared to likely requirements. Report P6, 4.4

Implications

  • Financial: Revenue forecast underspend of £240k reduced through a transfer to reserves, giving an effective £104k under budget. Report P12, P4
  • Financial: Capital programme showing £1,324k slippage, with delivery expected in the second half of the year or carried forward. Report P15, P16
  • Risk: Bad debt provision of £1,030k covers £301k of write-offs to date, with £255k of general fund debt outstanding. Report P20, P19
  • Other: Report considered in the context of local government reorganisation planning. Report P35

Who and where

  • All council services through the net revenue budget of £13,874k Report P4
  • Capital scheme delivery teams, with several projects completed in the year to November Report P17
  • Debtors owing £255k to the council across s106, leisure, community safety and other areas Report P19, P21

Timeline

  • Year to November 2025: Capital schemes completed within planned timescales and budgets Report P16, P17
  • 30 November 2025: Period 8 budget monitoring position reported Report 1.1, P4
  • 29 January 2026: Strategy and Resources Committee meeting date
  • 31 March 2026: Forecast end of financial year 2025/26 Report 3.1

Plain English for the jargon

  • Period 8: The eighth monthly budget monitoring period of the financial year, ending 30 November 2025.
  • Revenue outturn: The actual or forecast income and expenditure position at year end against the agreed budget.
  • Capital programme: The council's planned spending on long-term assets such as buildings, vehicles and infrastructure.
  • Earmarked Reserves: Funds set aside for specific future purposes rather than for general use.
  • S106: Section 106 planning obligations, contributions from developers towards local infrastructure.
  • LGR: Local Government Reorganisation, the restructuring of local authorities.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item468

Resolved

RESOLVED That the Committee: (i) notes that the forecast revenue outturn as at 30 November 2025 is £104k under budget (0.7%) against the net service budget of £13,874k. ... view the full minutes text for item 468.
Word for word from the decision Maldon published for this meeting. Source: democracy.maldon.gov.uk

Follow this further

Built from Maldon's papers

What the report saysPro

Report to Strategy and Resources Committee

Purpose of the report

1.1To provide Members of the Committee with an updated financial position for the Council for the period ended 30 November 2025 (Period 8).

1.2This matter is brought forward for consideration with the agreement of the Chairman so that the Council has clarity on the available funding for 2025/26 to be able to carry out its operations in a timely manner.

Recommendations

That the Committee:

(i) notes the forecast revenue outturn as at 30 November 2025 is £104k under budget (0.7%) against the net service budget of £13,874k. Further information can be found at APPENDIX 1 along with reasons for significant variances;

(ii) considers the forecast capital outturn as at 30 November 2025 which is for a total capital programme delivery of £5.656m against revised budget of £6.980m. Notes the schemes completed in the year so far (para 3.6). Further information can be found at APPENDIX 2 along with reasons for significant variances;

(iii) approves the movements in Earmarked Reserves set out in APPENDIX 3;

(iv) notes the revenue budget reconciliation between the opening and current budget in APPENDIX 4.

3. SUMMARY OF KEY ISSUES

3.1The Period 8 Budget Monitoring report provides financial forecast for the Council for the full year ending 31 March 2026 including revenue and capital forecasts and the impact of those on retained reserves (General and Earmarked).

3.2The report shows operational budget performance closely aligned to budget plans. This demonstrates the accuracy of the base budget position and the effectiveness of budget management by officers.

Our Vision: Where Quality of Life Matters APPENDIX 4 3.3 Revenue Budget Monitoring – Period 8

3.3.1 The forecast for the revenue budget projects an underspend of £240k against the 2025/26 budget, reduced through a transfer to reserves.

3.3.2 The strong performance is attributed to additional investment income along with better than expected receipts from the planning activities. Strong income performance has also offset additional unbudgeted costs in I.T ensuring that systems are sufficiently maintained. Further detail is included in APPENDIX 1.

3.4Capital Budget Monitoring – Period 8

3.4.1 The forecast for the capital budget projects an underspend of £1,324k against the revised 2025/26 Capital programme of £6,980k. The main project details can be found at APPENDIX 2.

3.4.2 Many capital projects get under way in the early part of the year. Completions tend to come through during the second half of the year. Schemes completed during the year to November are shown below. These were all completed within planned timescales and budgets.

3.4.3 Project delivery up to 30 November: Budget Actual Riverside Park Skate Park and Equipment £193k £193k West Maldon Councillor Shaughnessy Park £138k £138k Oaktree Meadow play site resurfacing and fencing £146k £146k Amphitheatre £79k £79k Community Engagement vehicles £36k £36k Parks Transit vehicle £35k; £35k Scout Hut, Brickhouse Farm £26k £25k 99 Wood Road – Community supermarket £20k £20k Demolition of Hythe Quay classroom £20k £20k Blackwater Leisure Centre Roof Safety system £20k £20k Budget Total Spend Maintenance team vehicle £38k £38k

3.5General Fund Debtors

3.5.1 Members have previously requested further information on the debt position. Outstanding debt for general fund activities as at 30 November was £255k, as shown in Table 1 below.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 23 KB Download
PDF
Appendix 2Appendix 2 41 KB Download
PDF
Appendix 3Appendix 3 42 KB Download
PDF
Appendix 4Appendix 4 22 KB Download
PDF
Budget Monitoring Report: Period 8 (end November 2025)Report 448 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 13 attended
JD
Councillor John DriverChairperson, present
JC
Councillor Jeanette C StiltsVice-Chairperson, apologies, sent representative
JR
Councillor James R Burrell-CookCommittee Member, present
SD
Councillor Sarah DodsleyCommittee Member, present
MF
Councillor Mark F L Durham CCCommittee Member, apologies, sent representative
TF
Councillor Tony FittockCommittee Member, present
KM
Councillor Kevin M H LaganCommittee Member, present
AM
Councillor Andrew M LayCommittee Member, present
RH
Councillor Richard H SiddallCommittee Member, present
PL
Councillor Paula L SpenceleyCommittee Member, present
ME
Councillor Maddie E ThompsonCommittee Member, present
SJ
Councillor Simon J N MorganCommittee Member, present as substitute

All 13 on the meeting page

On this subject at Maldon

Search all
  1. Budget Monitoring Report - Period 8 (end November 2025)This decision
  2. Budget Monitoring Report - Quarter 2Noted
  3. Budget Monitoring - Quarter 1Noted

More from Maldon Strategy and Resources Committee

All decisions
MeetingDecisionOutcome
23 Jul 2026 Minutes of the Last meetingRESOLVED that the Minutes of the meeting of the Committee held on 11 June 2026 be approved and confirmed. Approved Open
23 Jul 2026 Anti-Corruption Policy SuiteRESOLVED that the , as set out in Appendices A to E of the report, be agreed: · Anti-Money Laundering Policy at Appen... Agreed Open
23 Jul 2026 Friary Fields Property AcquisitionRESOLVED (i) That a capital budget of up to £800,000 be approved to fund the acquisition of the Friary Fields propert... Approved Open
23 Jul 2026 SUEZ Depot Expansion ProjectRESOLVED (i) That the total Suez Depot Expansion project budget of £348,289 be approved; (ii) That the Committee note... Approved Open
11 Jun 2026 Minutes of the Last meetingRESOLVED that the Minutes of the meeting of the Committee held on 19 March 2026 be approved and confirmed. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies