Maldon District Council
Performance, Governance and Audit Committee, Thursday 17 September 2026 at 7.30pm

Leisure Contract Update

Noted Finance 3 papers

AI summaryMaldon District Council's Performance, Governance and Audit Committee noted progress on the £5.8m Leisure Management Contract, including on-schedule refurbishment, stable membership and a growing social outreach programme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedRefurbishment, membership and social outreach endorsed
Money£5.8m investment, c£500k per annumLeisure estate investment, average Council income over 20 years
What happens nextPhases 3 and 4 in Q3Health suite and splash pad due for completion
Who it affectsLeisure centre users and residentsCouncil leisure estate and priority neighbourhoods

What was decided

Members noted progress of the Leisure Management Contract, including the on-schedule refurbishment programme, stable membership performance, and the positive development of the social outreach programme. Report P2

Members noted that financial performance was being delivered as set out in the contract, with the fixed management fee monitored monthly at operational contract meetings and reported quarterly via the Leisure Contract Partnership Board. Report P3

Why

The contract commenced in March 2025 and governance arrangements through the Leisure Contract Partnership Board are operating effectively, with no financial issues or risks identified at this stage. Report 3.1, 3.8, 4.1

Phases 1 and 2 of the refurbishment are complete, membership is in line with contract forecast, and 71 referrals from 17 organisations were made in Quarter One under the strengthened social outreach programme. Report 3.4, 3.6, 3.7

What happens next

Phases 3 and 4, the health suite and the splash pad replacing the river rapids at Blackwater Leisure Centre, are due for completion in Quarter Three. Report 3.5

Places Leisure is developing further outreach initiatives and the operator, council officers and the new Active Living and Leisure Officer will continue monthly and quarterly performance and financial reporting. Report 3.3, 3.7, 4.1

The money

  • £5.8m Investment across the Council's leisure estate under the contract Report 3.1
  • c£500k per annum Average income to the Council over the 20-year contract term Report P30

Implications

  • Financial: A fixed management fee is paid to the Council with the added security of a parent company guarantee, and the refurbishment programme remains within the approved budget. Report 3.8, P30
  • Risk: No identified risks or concerns relating to contract performance, compliance or fraud; risks are reviewed routinely. Report P29
  • Equalities: No adverse impacts on protected groups identified; temporary arrangements during refurbishment have been kept accessible and inclusive, and the works will enhance future accessibility. Report P28
  • Climate: Environmental considerations are embedded in the refurbishment, focusing on energy efficiency, reduced carbon emissions and modernised building systems. Report 5.4, P23
  • Staffing: Places Leisure currently employs 66% of staff from within the district, around 120 to 150 people depending on season, with a designated community staff member now in place. Report P31
  • Other: Customers have faced short-term disruption from the refurbishment, including temporary changes to access and timetables, which the contractor has managed through advance notice and alternative options. Report P27

Who and where

  • Leisure centre users across the district Report 3.6, P27
  • Residents in priority neighbourhoods targeted by the social outreach programme Report 3.7
  • Places Leisure staff, around two thirds of whom live in the district Report P31
  • Clinical and non-clinical organisations making referrals to the exercise referral scheme Report 3.7

Timeline

  • March 2025: Leisure Management Contract commenced Report 1.1, 3.1
  • Quarter One: 71 referrals made from 17 organisations; hot weather drove high splash park activity Report 3.6, 3.7
  • Phase 1 and 2 completed: New fitness suite and adventure climb installed, and two new studios formed Report 3.4, P9
  • Quarter Three: Phase 3 health suite construction and Phase 4 splash pad installation due for completion Report 3.5
  • End of year: Membership numbers expected to recover in line with contract plan Report 3.6
  • Quarterly: Leisure Contract Partnership Board meetings continue Report 3.3, 4.1

Plain English for the jargon

  • JSNA: Joint Strategic Needs Assessment, a data-led review of local health and demographic needs
  • MTFS: Medium-Term Financial Strategy, the Council's medium-term budget plan
  • SLT: Senior Leadership Team of Maldon District Council
  • MDC: Maldon District Council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

RESOLVED (i) That Members noted the progress of the Leisure Management Contract, including the on-schedule refurbishment programme, stable membership performance, and the positive development of the social outreach programme; (ii) That Members noted that financial performance was being delivered as set out in the contract. This included the fixed management fee which was monitored monthly at operational contract meetings and reported quarterly via the Leisure Contract Partnership Board.
Word for word from the decision Maldon published for this meeting. Source: democracy.maldon.gov.uk

Follow this further

Built from Maldon's papers

What the report saysPro

Report to Performance, Governance and Audit Committee

Purpose of the report

1.1To provide Members with an update on the performance and delivery of the Leisure Management Contract, which commenced in March 2025.

Recommendations

(i) That Members note the progress of the Leisure Management Contract, including the on-schedule refurbishment programme, stable membership performance, and the positive development of the social outreach programme;

(ii) That Members note that financial performance is being delivered as set out in the contract. This includes the fixed management fee which is monitored monthly at operational contract meetings and reported quarterly via the Leisure Contract Partnership Board.

3. SUMMARY OF KEY ISSUES

3.1The Leisure Management Contract commenced in March 2025. The contract includes an investment of £5.8m across the Council’s leisure estate, the operation of the Council’s leisure centres, delivery of health and wellbeing programmes, and a strengthened social outreach to support active lifestyles within priority communities.

3.2Maldon District Council (MDC) has appointed an Active Living and Leisure Officer to manage the Leisure Management Contract moving forward. This Officer sits within the Health Integration and Wellbeing Team, reflecting the strategic ambition of the contract to achieve positive health outcomes for residents.

3.3In Quarter One (Q1) the Health Integration and Wellbeing Team has been working with the contractor to strengthen operational plans and reporting through refreshed monthly reporting arrangements. Performance and financial information are cascaded up to the MDC Senior Leadership Team (SLT) monthly and to the Leisure Contract Partnership Board consisting of Members, Officers and Places Leisure management team which continues to meet on a quarterly basis.

3.4Refurbishment works across the leisure facilities, continue to progress on time and within budget. No risks to the development project have been reported that are expected to impact delivery schedules. Key milestones achieved to date include:

Our Vision: Where Quality of Life Matters  Phase 1 – installation of new fitness suite and adventure climb facilities - completed  Phase 2 – formation of two new studios - completed

3.5The remaining two phase are on track for completion in Quarter Three:  Phase 3 – construction of a health suite  Phase 4 – installation of a splash pad adjacent to the swimming pool to replace the river rapids feature.

3.6Membership numbers across the leisure centres are performing in line with contract forecast. Membership numbers reduced slightly due to the swimming pool closure to accommodate Phase 4 demolition works at Blackwater Leisure Centre, but these are expected to increase again in line with the contract plan by the end of the year. Hot weather in Q1 has driven extremely high activity levels in the splash park in the Promenade Park.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 874 KB Download
PDF
Appendix 2Appendix 2 481 KB Download
PDF
Leisure Contract UpdateReport 146 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 12 attended
WS
Councillor Wendy Stamp CCChairperson, present
MG
Councillor Matthew G NeallVice-Chairperson, present
DO
Councillor Doug O BownCommittee Member, apologies
SD
Councillor Sarah DodsleyCommittee Member, present
JC
Councillor Jade C HughesCommittee Member, present
RG
Councillor Ron G PrattCommittee Member, present
RH
Councillor Richard H SiddallCommittee Member, apologies
UG
Councillor Una G C Siddall-NormanCommittee Member, apologies
ND
Councillor Nick D SpenceleyCommittee Member, present
ME
Councillor Maddie E ThompsonCommittee Member, present
DS
Derek SmithAdvisor, present
CH
Cheryl HughesOfficer, expected

On this subject at Maldon

Search all
  1. Leisure Contract UpdateThis decision
  2. Leisure Contract UpdateDecided
  3. Member Scrutiny Request - Leisure Contract: Communications and Messaging (request by Councillor A M Lay)Decided
  4. Member Scrutiny Request - Leisure Contract: Post Implementation Review (request by Councillor E L Stephens)Decided
  5. Leisure Contract UpdateNoted
  6. Leisure Contract Refurbishment Final AccountApproved

More from Maldon Performance, Governance and Audit Committee

All decisions
MeetingDecisionOutcome
17 Sep 2026 Minutes of the last meetingRESOLVED that the Minutes of the meeting of the Committee held on 16 July 2026 be approved and confirmed. Approved Open
17 Sep 2026 External Audit: Building Back AssuranceRESOLVED that the Committee received, considered, and accepted the following: (i) the outcomes of the risk assessment... Decided Open
17 Sep 2026 Corporate Performance Quarter 1RESOLVED (i) T hat the Committee received, considered and reviewed the information as set out in the report and Appen... Decided Open
17 Sep 2026 Review of Corporate Risk Quarter 1RESOLVED (i) That the Committee reviewed and provided comments and feedback on the Corporate Risk Register as set out... Decided Open
17 Sep 2026 Annual Governance Statement Actions UpdateRESOLVED that the Committee had reviewed and commented on the Annual Governance Statement’s table and updates set out... Decided Open