Executive Committee, Tuesday 29 August 2006 at 5.00pm

EC793 - Review of Medium Term Financial Plan

Noted Executive 1 paper

Executive Committee noted this item on Tuesday 29 August 2006. Below is the council's own wording, with the papers it was decided on.

Item44

Resolved

RESOLVED that the report be noted.
Word for word from the decision Malvern Hills published for this meeting. Source: moderngov.malvernhills.gov.uk

Follow this further

Built from Malvern Hills's papers

What the report saysPro

Report to Executive Committee, 4 pages

Ward: All Portfolio Holder: Cllr J Rayner Executive Committee 29th August 2006

Report of the Director of Resources Review of the Council’s Medium-Term Financial Plan

1. Purpose of Report 1.1 To outline the purpose, principles and timetable for the review of the Council’s medium-term financial plan

Recommendation that the report be noted.

2. Introduction 2.1 The purpose of the Medium-Term Financial Plan (MTFP) is to set out the financial position for the Council over the next three years, and identify the revenue and capital budget requirements in each of those years, including the alignment of financial plans to priorities. To ensure that the financial planning process is kept in line with the Council’s priorities, policies and funding needs, an annual review of the plan is required.

2.2The plan is based on a rolling three-year estimate of the council’s financial position for revenue expenditure, and a rolling five year position for capital expenditure.

2.3The current MTFP was approved in two stages – the revenue budgets in November 2005, and the capital budgets in February 2006.

2.4The Government’s Comprehensive Spending Review (CSR07) will be completed in July 2007. It is too early to know what that will bring, but many of the headline ‘drivers’ have already emerged (mainly relating to lower increases in revenue support grant and expected efficiency gains of at least 2.5% each year).

3. Principles and Assumptions 3.1 The key principles and assumptions underpinning the current plan include:

a. spending decisions are based upon the Council’s priorities, with budget reductions in non-priority areas and funds released to reinvest on priority actions and services;

b. council tax increases assumed to be no more than 3% per year;

Page 1 Report No: EC793 c. the achievement of a balanced budget, with no use of balances to meet baseline spending; and

d. the general fund balance will not fall below £1million.

3.2It will be necessary to review these assumptions when rolling forward the MTFP for 2007/08 onwards.

4. Process 4.1 The review of the MTFP will be treated as a corporate project and, as such, it will follow the agreed project management guidelines, based on PRINCE 2 methodology. This has included establishing a project board comprising the portfolio holder for resources, myself, the Head of Financial Services and the Head of Environmental Services. The Accountancy Services Manager is the Project Manager.

4.2A comprehensive project initiation document (PID) has been approved by the board. The PID addresses the following issues:

• The revenue element of the plan will cover the period 2007/08 to 2009/10 • The capital element of the plan will cover the period 2007/08 to 2011/12 and will be closely linked to the property strategy • Revised assumptions for inflationary pressures • Identified efficiency gains, including savings to be achieved through business process improvement and other service changes • Spending pressures arising through legislative changes and/or other Government initiatives • Spending pressures arising through local policy changes • Material corrections to base budgets • Commitment to maximise income: through increased charges, better collection rates or new funding sources (one-off as well as recurring)

4.3The review outcomes will be used to inform the setting of the detailed revenue and capital budgets for 2007/08.

4.4The project will be ‘delivered’ in several dependent phases, including:

• Information gathering and analysis • Identification of overall position • Consideration of priorities/non-priorities (including political input) • Financial modelling / option appraisals • Communication of proposals/intentions • Public consultation

4.5The timetable for the review is as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EC793: Review of Medium Term Financial PlanReport 4 pages DownloadRead as text

More from Malvern Hills Executive Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... Decided Open
15 Sep 2026 Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... Noted Open
15 Sep 2026 Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... Noted Open
15 Sep 2026 Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... Agreed Open
15 Sep 2026 Street Naming and Numbering PolicyRESOLVED that the revised ‘Street Naming and Numbering Policy’, as presented in Appendix 1, be adopted. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies