EC797 - Interim Report of Property Working Party

Decided Executive 1 paper

Executive Committee decided this item on Tuesday 29 August 2006. Below is the council's own wording, with the papers it was decided on.

Item51

Resolved

RESOLVED that (i) a final report of the Working Party be presented to Executive Committee as soon as possible; (ii) in the meantime, arrangements be made for the disposal of Rockliffe, Temeside House, and the Willows Shop at full market value as soon as possible; (iii) a project plan for the relocation of staff from Highlea to other Council Buildings be prepared and, subject to staff consultation, be implemented as soon as possible; and (iv) Spring Lane Industrial plots and Spring Lane Starter Units be retained by the Council as investment properties. (With the permission of the Chairman, Councillor Grove spoke with regard to the proposed disposal of Temeside House in Tenbury.)
Word for word from the decision Malvern Hills published for this meeting. Source: moderngov.malvernhills.gov.uk

Follow this further

Built from Malvern Hills's papers

What the report saysPro

Report to Executive Committee, 8 pages

Ward: All Portfolio Holder: Cllr. J.Rayner Executive Committee 29th August 2006

Interim Report of the Property Working Party 1. Purpose of Report 1.1 To provide the Committee with an interim report of the work of the Property Working party and of its recommendations so far

Recommendation that -

(i) a final report of the Working party be presented to Executive Committee as soon as possible; (ii) in the meantime, arrangements be made for the disposal of Rockliffe, Temeside House, and the Willows Shop at full market value as soon as possible; (iii) a project plan for the relocation of staff from Highlea to other Council Buildings be prepared and, subject to staff consultation, be implemented as soon as possible (iv) Spring Lane Industrial plots and Spring Lane Starter Units be retained by the Council as investment properties

2. Background 2.1 The property condition survey undertaken in 2005 identified that the Council’s existing office buildings are in a poor state of repair and estimated the cost of carrying out the most important works as being in excess of £5m. However, simply repairing those existing buildings would do nothing to improve the quality of the Council’s accommodation. Most of the existing buildings were not originally designed for office use and are unsuited to modern office requirements. Furthermore, the Council does not have the capital reserves with which to fund such a programme of repairs.

2.2The property strategy was approved by Council on 10th January 2006 in response to the above findings. This provides for:  the construction of new Council office accommodation; and  disposal of other existing Council owned buildings which are, or will be, surplus to requirements.

Page 1 Report No: EC797 2.3 The property strategy forms part of the Council’s overall capital programme and it will at some point be necessary for the Council to borrow money in order to fund that programme; this is regardless of whether the Council builds new office accommodation or remains in its existing buildings. The more capital receipts that can be generated from the sale of existing buildings, the lesser that borrowing requirement. In approving the capital programme Executive Committee resolved (in accordance with the recommendation of the Scrutiny Panel) that a Property Working Party be established:

“to ensure and be satisfied that there is a clear demonstration of the prudential principles of affordability, value for money and sustainability prior to the Council entering into borrowing arrangements and that subsequently the Working Party monitor the implementation of the property schemes”

2.4The Working Party comprises Cllrs. J Rayner, S. Croad, G. Price, Director of Resources, Head of Legal Services, Head of Financial Services and has been assisted in its deliberations by the Accountancy Services Manager and officers from Worcester City Council - Andrew Harding (Estates Manager), Ian Forrester (Facilities Manager) and Richard Ansell (Maintenance Manager).

3. Disposals Programme 3.1 The Council’s property holdings divide into:  ‘operational buildings’ (those that we currently occupy ourselves); and  ‘non-operational’ (those we don’t).

3.2The property strategy envisaged the disposal of all non-operational properties and surplus operational buildings in order to generate capital receipts to fund the capital programme. These were divided into two phases – those to be sold immediately and those to be disposed of following the completion of the new offices. This approach has now been reviewed and amended – see below.

3.3The strategy included an initial estimate of likely sale values. These have now been subject to a more detailed valuation exercise. Appendix 1 shows the initial capital receipt estimates (column 1) and the revised valuations (column 2). These estimates are based on full market value. In particular no allowance has been made for any sales at less than market value e.g. for affordable housing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EC797: Interim Report of Property Working PartyReport 8 pages DownloadRead as text

More from Malvern Hills Executive Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... Decided Open
15 Sep 2026 Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... Noted Open
15 Sep 2026 Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... Noted Open
15 Sep 2026 Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... Agreed Open