Item134

Resolved

RESOLVED that (i) refurbishment and improvement works be undertaken to the Council House, Brunel House and Priory Lodge Hall in order to meet the Council’s future accommodation requirements; (ii) upon completion of those works, staff currently within Portland House be relocated and Portland House be sold as previously resolved; and (iii) the Property Working Party should oversee the implementation of the above proposals.
Word for word from the decision Malvern Hills published for this meeting. Source: moderngov.malvernhills.gov.uk

Follow this further

Built from Malvern Hills's papers

What the report saysPro

Report to Executive Committee, 7 pages

Ward: All Portfolio Holder: Cllr. J. Rayner Executive Committee 20th February 2007

Report of Head of Legal Services Property Working Party – Office Accommodation Strategy

1. Purpose of Report 1.1 To report on the recommendations of the Property Working Group following a further appraisal of office accommodation options

Recommendation that -

(i) refurbishment and improvement works be undertaken to the Council House, Brunel House and Priory Lodge Hall in order to meet the Council’s future accommodation requirements; (ii) upon completion of those works, staff currently within Portland House be relocated and Portland House be sold as previously resolved; and (iii) the Property Working Party oversee the implementation of the above proposals.

2. Background 2.1 The Property Strategy was approved by Council on 10th January 2006. Its objectives were:

 To use or dispose of any residual non-operational property for the purpose of community benefit or financial return  To dispose of land in accordance with the Council’s policy on provision of affordable housing.  To provide staff and visitors with accessible, attractive and safe accommodation & facilities, while taking into account the Council’s stated aim not to develop a single site solution.  To provide accommodation that contributes to improving interconnectedness in the way the Council functions.  To realise capital receipts from redundant property.

2.2The strategy was prepared against the background of the property condition survey undertaken in 2005 which highlighted the poor condition of the Council’s office accommodation, the extensive backlog of maintenance work required and the unsuitability of several buildings to meet modern office requirements. Three options were identified, in order of preference:

Page 1 Report No: EC847 (a) Refurbish Brunel House and build an extension on land currently in third party ownership (b) Redevelop the Portland House site (c) Develop the former treasurer’s site at Albert Road North for office accommodation.

2.3A fourth ‘minimum spend’ option was not recommended as it did nothing to address the underlying problems and unsuitability of the existing buildings.

2.4The capital programme strategy subsequently identified that the cost of any new office accommodation would need to be met from borrowing and the Property Working Party was therefore established by Executive Committee in February 2006 with a remit to

“ensure and be satisfied that there is a clear demonstration of the prudential principles of affordability, value for money and sustainability prior to the Council entering into borrowing arrangements and that subsequently the Working Party monitor the implementation of the property schemes.”

2.5The Property Working Party reported to Executive Committee in November 2006 (report EC810) with its detailed findings and concluded that none of the previously identified ‘new build’ options were affordable within the constraints of the revised medium term financial plan. It was resolved inter alia that:

(i) the proposed new build Council office accommodation schemes identified in the previously approved property strategy be not pursued; and

(ii) further feasibility work be undertaken for a scheme involving the refurbishment of the Council House and either redevelopment on the site of Priory Lodge Hall, including the relocation of staff from Brunel House and Portland House or the refurbishment of Brunel House and the Council House;

2.6This report deals with the Property Working Party’s findings in relation to the second of those resolutions and also addresses concerns expressed at that meeting regarding the size of the Council’s future accommodation requirements.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EC847: Property Working Party ReportReport 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Malvern Hills

Search all
  1. EC847 - Property Working Party ReportThis decision
  2. Property Working Party Minutes - 26th March 2008Decided
  3. EC797 - Interim Report of Property Working PartyDecided

More from Malvern Hills Executive Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... Decided Open
15 Sep 2026 Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... Noted Open
15 Sep 2026 Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... Noted Open
15 Sep 2026 Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... Agreed Open
15 Sep 2026 Street Naming and Numbering PolicyRESOLVED that the revised ‘Street Naming and Numbering Policy’, as presented in Appendix 1, be adopted. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies