RESOLVED that (i) the outstanding highway, street lighting and drainage works be completed in order that these works can then proceed to adoption; and (ii) the lowest tender for the work be accepted in the sum of £55,715 to be funded from the capital programme.
Word for word from the decision Malvern Hills published for this meeting.Source: moderngov.malvernhills.gov.uk
Portfolio Holder: Cllr P Grove Executive Committee
28th October 2008 Report of Head of Legal & Governance
The Haysfield, Malvern - Completion of infrastructure 1. Purpose of Report 1.1 To seek approval to undertake works at The Haysfield, Malvern to complete the construction of the carriageway, street lighting and sewers to adoptable standard
Recommendation that -
(i) the outstanding highway, street lighting and drainage works be completed in order that these works can then proceed to adoption; and (ii) the lowest tender for the work be accepted in the sum of £55,715 to be funded from the capital programme.
2. Background 2.1 Malvern Hills District Council bought the land at the Haysfield in October 1995.
2.2At the time there was a perceived shortage of serviced industrial land in Malvern and this was acting as a constraint against existing businesses expanding/new businesses locating to Malvern. This was before either the industrial land at Townsend Way or the Science Park had been developed. MHDC therefore decided to buy the land, install the services (roads, drainage etc) and sell the land as five individual building plots
2.3Malvern Hill District Council entered into a sewer adoption agreement with Severn Trent Water in 1996 whereby Severn Trent would adopt the drains once completed to the required specification - the drains were duly constructed but the adoption process was not formally completed (see below)
2.4Malvern Hills District Council also entered into a similar agreement with the County Council in 1998 for adoption of the roads.
2.5The construction of the infrastructure works (roads and drains) was carried out in 1996. However, in accordance with normal development practice, the roads were only constructed to base course level at that stage - any top course was likely to get damaged by future construction traffic when building took place on the individual plots. The intention was therefore was to finish off the road and proceed to adoption once the last of the plots had been developed. Page 1 Report No: EC983 2.6 All plots were sold between 1998 and 2004. Plot 1 was subsequently developed into 9 individual units which were completed in 2005 and are now known as Haysfield Business Centre. 2.7 Although the transfers of the individual plots did not contain covenants by MHDC to complete the road:
(a) We had previously entered into the agreement with the County Council that we would construct the road to adoptable standards; and (b) purchasers bought in the reasonable expectation that the road would be made up to adoptable standard (including street lighting) (c) if we don't finish the road and ensure that it is adopted, MHDC will be faced with an on-going maintenance liability
2.8We received complaints in 2007 from the occupiers of the Haysfield Business Centre about the delay in completing the road. In response to those complaints, the Chief Executive replied in February this year accepting that the Council had a responsibility to make the road up to adoptable standards.
3. Proposed Work 3.1 A schedule of work required has been prepared by Worcestershire County Council Highways Department to make the elements adoptable, which includes replacement of kerbs, road repairs, final surfacing and markings and work to the street lighting. Work required by Severn Trent to get the sewers adopted has been included in the tender
3.2The project has been subject to competitive tender with 3 tenders being received £67,750.00. £62,696.00 and £55,715.00
4. Corporate Considerations Resource Implications: The costs of £55,715.00 can be met from the capital programme (Identify Financial, Legal, Property and Personnel issues)
Policy Implications: Links to the economic prosperity of the district by maintaining he infrastructure and off setting unforeseen (Identify how proposals link to future revenue implications for maintenance Council priorities and the current policy framework, and if they do not, identify implications)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.