Executive Committee, Tuesday 28 October 2008 at 5.00pm

EC981 - Future Office Accommodation

Deferred Executive 1 paper

Executive Committee deferred this item on Tuesday 28 October 2008. Below is the council's own wording, with the papers it was decided on.

Item64

Resolved

RESOLVED that (i) Portland House be vacated and staff relocated to Brunel House and the Council House in accordance with the timetable and proposals outlined in the report; (ii) a capital budget be established of £75,000 in the current financial year to facilitate the office moves; the use of this budget to be delegated to the Head of Finance and Resources, in consultation with the Leader of Council and the Portfolio Holder for Resources; and (iii) given the constraints and priorities on the Council’s financial resources, options on the relocation of the Council’s administration to a new site be deferred until there is both further clarity on joint working and an improvement in the current economic conditions.
Word for word from the decision Malvern Hills published for this meeting. Source: moderngov.malvernhills.gov.uk

Follow this further

Built from Malvern Hills's papers

What the report saysPro

Report to Executive Committee, 6 pages

Ward:All Portfolio Holder: Cllr R Madden Executive Committee 28th October 2008

Report of Property Working Party Future Office Accommodation

1. Purpose of Report 1.1 To report back with the preferred option for both current and future office accommodation for the Council.

Recommendation that -

(i) Portland House be vacated and staff relocated to Brunel House and the Council House in accordance with the timetable and proposals outlined in the report; (ii) a capital budget be established of £75,000 in the current financial year to facilitate the office moves; the use of this budget to be delegated to the Head of Finance and Resources, in consultation with the Leader of Council and the Portfolio Holder for Resources; and (iii) given the constraints and priorities on the Council’s financial resources, options on the relocation of the Council’s administration to a new site be deferred until there is both further clarity on joint working and an improvement in the current economic conditions.

2. Background 2.1 The Property Working Party of 8th October considered the following options regarding Council Office Accommodation for its administrative Staff::

• As a first step to vacate Portland House and to relocate staff to the Council House and Brunel House thereby reducing property costs;

• Consolidating the Council’s Administration in one Administration Block at a different location OR • Following vacating Portland House, to retain the Administration in the two remaining properties at Brunel and Council House

2.2A report dated 26th September 2008 has been received from Colliers CRE, Chartered Surveyors & International Property Consultants providing advice on the Consolidation of the Council Administration in a single building.

Page 1 Report No: EC981 2.3 In reviewing the options, the Working Party took into account, the issues, costs, timing and the financial constraints the Council faces with respect to its financial situation and the funding available in current market conditions.

3. Vacating Portland House and relocating staff to Council House / Brunel House 3.1 The efficiencies programme included in the Medium Term Financial Plan 2009/10 to 2011/12 and the Budget for 2008/09, both assume savings form vacating Portland House.

3.2This move was to be initiated following the relocation of Revenues and Benefits Staff to Wychavon which was anticipated in the budget by mid year. This has now been achieved.

3.3The key drivers in the plan are:

• To save property overhead costs which are budgeted currently at £45,070. This saving has already been built in to both the Current MTFP and Efficiency plan. Immediate savings from vacating are estimated to be between £15- £20k per annum; • To avoid major repairs and renovation work to provide suitable office accommodation for staff. From the last condition survey undertaken by Worcester City there is £250,000 of capital works outstanding mainly to the roof of the building. There is no capital provision for this work to be undertaken; • To market the property to release capital funds for the Council’s capital programme. An estimated receipt of £800,000 for financial year 2010/11 has been built into the financing of the current capital programme; • To provide accommodation for staff in better conditions than are currently to be found in Portland House; • To create synergies and efficiencies in ways of working

3.4The number of Staff currently occupying Portland House, together with their desk requirements and where the teams will be located in the new proposals are contained in the table below:

Function Staff No FTE Desks Location Required Accountancy 11 10.5 11 Brunel ICT 11 11 11 Brunel Housing 6 6 6 Brunel Property 2 2 2 Council House Community & Economic 11 9.5 10 Council Development House Audit Services 4 0 3 Brunel Total 45 39 43

3.5The proposed relocations have tried as far as possible to bring existing teams together and create synergies for better joint working eg:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EC981: Future Office AccommodationReport 6 pages DownloadRead as text

More from Malvern Hills Executive Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... Decided Open
15 Sep 2026 Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... Noted Open
15 Sep 2026 Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... Noted Open
15 Sep 2026 Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... Agreed Open
15 Sep 2026 Street Naming and Numbering PolicyRESOLVED that the revised ‘Street Naming and Numbering Policy’, as presented in Appendix 1, be adopted. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies