Planning Committee, Thursday 5 September 2013 at 6.30pm

Community Infrastructure Levy: Preliminary Draft Charging Schedule for Consultation and the Updated CIL Timetable - PL243

Noted Planning 2 papers

Planning Committee noted this item on Thursday 5 September 2013. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

that (i) the work that had been undertaken to produce the CIL draft Charging Schedule, be noted; (ii) the CIL Preliminary Draft Charging Schedule, as set out in Appendix 1 to Report PL243, be approved for consultation over a 6 week period in September/October 2013, this includes an indicative Regulation 123 list (Appendix A to the Preliminary Draft Charging Schedule); (iii) delegated authority be given to the Head of Planning, Economy and Housing in consultation with the Portfolio Holder for Planning and Housing, to make minor amendments to the schedule prior to consultation; and (iv) the CIL timetable be approved as set out as Appendix D to the Preliminary Draft Charging Schedule at Appendix 1 to Report PL243.
Word for word from the decision Malvern Hills published for this meeting. Source: moderngov.malvernhills.gov.uk

Follow this further

Built from Malvern Hills's papers

What the report saysPro

Report to Planning Committee, 7 pages

Ward: All Portfolio Holder: Cllr A Penn Planning Committee

5 September 2013

Report of Head of Planning, Economy and Housing

Community Infrastructure Levy: Preliminary Draft Charging Schedule for Consultation and the Updated CIL Timetable 1. Purpose of Report 1.1 The purpose of this report is to approve the Community Infrastructure Levy (CIL) Preliminary Draft Charging Schedule for consultation and to approve the CIL timetable.

1.2The report outlines the national legislative guidance basis to CIL and the proposed timeline for progressing CIL in South Worcestershire. It then goes on to explain the first key stage in the process, the Preliminary Draft Charging Schedule (PDCS), which is recommended for consultation, with the report making reference to the evidence which has been used and the other supporting information which will be used in the consultation process this autumn.

Recommendation that -

(i) the work that has been undertaken to produce the CIL draft Charging Schedule, be noted; (ii) the CIL Preliminary Draft Charging Schedule, as set out in Appendix 1, be approved for consultation over a 6 week period in September/October 2013, this includes an indicative Regulation 123 list (Appendix A to the Preliminary Draft Charging Schedule);

(iii) delegated authority be given to the Head of Planning, Economy and Housing in consultation with the Portfolio Holder for Planning and Housing, to make minor amendments to the schedule prior to consultation; and (iv) the CIL timetable be approved as set out as Appendix D to the Preliminary Draft Charging Schedule at Appendix 1.

2. Background/Introduction 2.1 The Community Infrastructure Levy (CIL) is a locally-set standard charge that can be applied to new building developments to fund infrastructure. CIL may be used to fund a range of types of infrastructure in accordance with the Government’s CIL Regulations. This includes new or safer transport schemes,

Page 1 Report No: PL243 flood defences, schools, community, health and social care facilities, park improvements, green spaces and leisure centres.

2.2The latest national CIL guidance (May 2013) at paragraph 8, states that charging authorities should show and explain how their proposed levy rates will contribute towards the implementation of their Plan and support the development of their area. The context for this is the South Worcestershire Development Plan (SWDP), and more particularly the South Worcestershire Infrastructure Delivery Plan (SWIDP), and this explanation will be included as part of the material which goes out for consultation.

2.3The SWDP, supported by the SWIDP, was submitted to the Secretary of State on May 28th, 2013 and is to undergo the first) Hearings stage of its Examination in the first week of October. The SWDP identifies the cost of infrastructure required to support the delivery of housing and employment growth across south Worcestershire.

2.4It should be noted that the provision of affordable housing, or financial contributions towards it, cannot be secured through CIL. CIL will continue to complement planning obligations (s.106 agreements) as a means of funding contributions to infrastructure via site specific requirements. However, the Government in the near future is proposing to limit the use of planning obligations where there has been five or more obligations in respect of a specific infrastructure project or a type of infrastructure entered into on or after 6th April 2010 (Paragraph 89 of CIL Guidance). The Council will synchronise its CIL timeline with a parallel work stream to progress a Developer Contributions Supplementary Planning Document (SPD). This will help to ensure a more effective combined approach to raising monies for infrastructure via development proposals.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Community Infrastructure Levy: Preliminary Draft Charging Schedule for Consultation and the Updated CIL Timetable: PL243Report 7 pages DownloadRead as text
PDF
PL243 APP1: Preliminary Draft Charging Schedule FinalReport 22 pages Download

At this meeting

Whole meeting
10Confirmation of MinutesDecided
13Community Infrastructure Levy: Preliminary Draft Charging Schedule for Consultation and the Updated CIL Timetable - PL243This decision

On this subject at Malvern Hills

Search all
  1. Community Infrastructure Levy: Preliminary Draft Charging Schedule for Consultation and the Updated CIL Timetable - PL243This decision
  2. Community Infrastructure Investment Plan 2025-28 Progress UpdateApproved
  3. Hallow Fields Community Infrastructure Levy Project ProposalApproved
  4. Community Infrastructure Levy Draft Charging ScheduleApproved
  5. Community Infrastructure Investment Plan 2025-28Approved
  6. Community Infrastructure Levy - Principal Approval for the Funding of Areas of Informal RecreationApproved

More from Malvern Hills Planning Committee

All decisions
MeetingDecisionOutcome
30 Mar 2017 Confirmation of MinutesThat the Minutes of the previous meeting, held on 28 February 2017, be approved and signed by the Chairman as a true ... Approved Open
30 Mar 2017 Shop Front Design Guide Supplementary Planning Documenti) That the changes to the Shop Front Design Guide Supplementary Planning Document as shown in Appendix 2 to this rep... Approved Open
30 Mar 2017 Conservation Area Reviews and Character Appraisalsi) That Planning Committee note the report ii) That Subject to resource availability, priority be given to reviewing ... Noted Open
30 Mar 2017 Revision to Local Enforcement Plan Prioritiesi) That the Planning Committee recommends that the Council adopt the revised changes to the Local Enforcement Plan in... Approved Open
30 Mar 2017 Review of the draft Local Area Planning Application Validation Requirements List(i) Planning Committee approve the draft Local Validation Document for consultation purposes and to inform decisions ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies