Resolved
That the minutes of the previous meeting, held on 22 September 2020, be approved and signed by the Chairman as a true and correct record of proceedings.
Executive Committee approved this item on Tuesday 17 November 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the previous meeting, held on 22 September 2020, be approved and signed by the Chairman as a true and correct record of proceedings.
Executive Committee Tuesday, 22 September 2020
Minutes Present: Councillors: K. Aksar, C. Baldwin, D. Chambers, D. Harrison, N. McVey, J. O'Donnell, S. Rouse (Chairman), T. Wells (Vice-Chairman) and P. Whatley
Apologies: Councillors: J. Owenson and J. Raine
8. Declarations of None Disclosable Pecuniary Interests and other Disclosable Interests
9. Confirmation of RESOLVED: That the minutes of the previous Minutes meeting, held on 26 May 2020, be approved and signed by the Chairman as a true and correct record of proceedings.
10. Chairman's None Announcements
11. Public Participation None
12. Revenue and The Committee considered the monitoring of spending Capital Budget as at the end of July against the 2020/21 revenue and Monitoring capital budgets and other key financial indicators.
RESOLVED: that the report, be noted.
13. Quarterly The Committee considered the latest council Performance Report performance and the strategic issues and risks facing the council which reflect the existing and future financial and organisational pressures on the council.
RESOLVED: that
i) The achievements and improvements in performance, be noted. ii) The strategic issues raised in section 4, be addressed. iii) The Executive Committee thank staff for the outcomes of their efforts. 14. Malvern Hills and The Committee considered the Council’s Five Year Wider Worcester Housing Land Supply (5YHLS) position at 1 April 2020 Area (Malvern Hills) when assessed against the adopted South Five Year Housing Worcestershire Development Plan (SWDP, February Land Supply 2016) housing requirement (SWDP3 Table 4b(i) refers) Reports 2020 for the two housing sub-areas within Malvern Hills District; Malvern Hills and Wider Worcester Area (Malvern Hills).
RESOLVED:
i) That it be noted that Officers consider for the period 1 April 2020 to 31 March 2025, a robust 5YHLS against the SWDP3 requirement can be demonstrated for Malvern Hills, and that the Council has continued to improve its position as a result of an increase in the number of proposed housing developments with planning permission, a sustained high level of housing completions and the latest deliverability evidence for SWDP Allocations.
ii) That it be noted that on account of Malvern Hills being able to demonstrate a 5YHLS and therefore an up-to-date Local Plan i.e. the SWDP, all associated policies for the supply of housing should be given full planning weight in the consideration and determination of planning applications.
iii) That the need to maintain a robust 5YHLS position in Malvern Hills to increase the probability of successfully defending (at appeal) planning refusals for unsustainable development proposals i.e. contrary to SWDP policies, be acknowledged.
iv) That it be noted that the Council’s updated 2020 5YHLS position of 8.17 years has not yet been formally tested at a planning inquiry.
v) That it be noted that officers consider for the period 1 April 2020 to 31 March 2025, for the Wider Worcester Area (Malvern Hills) housing sub-area, a 5YHLS against the SWDP3 requirement cannot yet be demonstrated. This is due to the delays in the formal consideration of planning applications, on account of involved and protracted development viability negotiations in respect of the planning applications for SWDP45/1 Worcester South and SWDP45/2 Worcester West.
15. Local Development The Committee considered the Local Development Scheme 2020-2023 Scheme 2020 to 2023 which sets out the proposed revised timetables for the review of the South Worcestershire Development Plan and the Travellers and Travelling Showpeople Site Allocations Development Plan Document(DPD) whose production has been materially hampered by the impacts of Covid19.
RECOMMENDED TO COUNCIL: that
i) The Local Development Scheme 2020-2023 set out at Appendix 1 to report EC1541, be approved, to come into effect from 1st October 2020.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Confirmation of MinutesReports_pack | 4 pages | DownloadRead as text |
Follow Executive Committee at Malvern Hills and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... | Decided | Open |
| 15 Sep 2026 | Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... | Noted | Open |
| 15 Sep 2026 | Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... | Noted | Open |
| 15 Sep 2026 | Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... | Agreed | Open |
| 15 Sep 2026 | Street Naming and Numbering PolicyRESOLVED that the revised ‘Street Naming and Numbering Policy’, as presented in Appendix 1, be adopted. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.