Resolved
that i) The achievements and improvements in performance, be noted. ii) The strategic issues raised in section 4, be addressed. iii) Executive Committee thank staff for the outcomes of their efforts.
Executive Committee noted this item on Tuesday 17 November 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
that i) The achievements and improvements in performance, be noted. ii) The strategic issues raised in section 4, be addressed. iii) Executive Committee thank staff for the outcomes of their efforts.
APPENDIX 1a - PERFORMANCE Planning Services Previous years 2019/20 2020/21 YTD APL RAG Ref Performance Indicator 2015/16 2016/17 2017/18 2018/19 2019/20 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Major' planning applications determined within 13 weeks or agreed 1 84 84 77 87 93 83 92 100 100 88 100 94 75 extension of time (valid to decision) (%)
Minor' planning applications determined within 8 weeks or agreed 2 80 66 87 92 82 84 79 86 78 84 85 85 85 extension of time (valid to decision) (%) Other' planning applications determined within 8 weeks or agreed 3 90 86 92 97 95 88 100 97 94 97 94 96 85 extension of time (valid to decision) (%)
4 Householder (HOU) applications determined within 6 weeks (%) ¯¯ ¯¯ ¯¯ 50 44 45 30 52 51 52 47 50 50
5 Pre-Apps determined within 15 working days (%) ¯¯ ¯¯ ¯¯ ¯¯ ¯¯ ¯¯ ¯¯ ¯¯ ¯¯ 65.1 49.6 65 TBC
Validation - Applications processed within timescales (from receipt to 6 ¯¯ ¯¯ 78.9 90.7 91.9 86.8 92.1 97.2 92.1 92.3 59.7 76 95 acknowledgement, excluding invalid period) (%)
7 Enforcement - Enforcement notices issued (n) ¯¯ ¯¯ 19 8 24 3 7 7 7 6 5 11 N/A
8 Plans checked within ten days (Malvern) (%) 93 95 96 91 91 87 92 92 94 94 100 97 90
Housing Services Previous years 2019/20 2020/21 YTD APL RAG Ref Performance Indicator 2015/16 2016/17 2017/18 2018/19 2019/20 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
9 Affordable homes delivered (gross) (n) 63 95 155 86 202 54 11 71 66 16 45 61 550 (5YP)
10 Homeless families in bed and breakfast for more than 6 weeks (n) 7 6 9 6 1 0 0 1 0 0 1 1 <5
11 Homeless households accepted under the statutory homeless duty (n) 43 40 32 17 25 10 2 8 5 3 3 6 <24
Total number of cases of homelessness relieved and prevented as a 12 ¯¯ ¯¯ ¯¯ 86 46 50 45 35 54 62 55 TBC TBC proportion of all aproaches (%)
Community Services Previous years 2019/20 2020/21 YTD APL RAG Ref Performance Indicator 2015/16 2016/17 2017/18 2018/19 2019/20 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
13 Completed investigations of reported environmental crimes (%) ¯¯ 72 100 99 97 98 99 100 93 92 94 93 70
Waste & Recycling Previous years 2019/20 2020/21 YTD APL RAG Ref Performance Indicator 2015/16 2016/17 2017/18 2018/19 2019/20 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
111 per 14 Residual household waste per head (kg) 444.3 429.6 467.1 403.6 417.12 106.2 97.2 108.7 105.0 108.6 108.8 217.4 quarter 37.2 per 15 Household waste recycled and composted (%) 37.1 37.6 35.4 39.9 39.67 39.7 43.7 37.9 37.4 43.8 43.2 43.5 quarter
16 Missed bins as a proportion of all bins 0.1 0.18 0.17 0.12 0.08 0.06 0.09 0.06 0.12 0.07 0.08 0.07 0.20
17 Fly tipping clearance rate (%) ¯¯ 90 86 87 94 94 90 94 96 98 97 97 90
Page 1 of 2 Revenues & Benefits Previous years 2019/20 2020/21 YTD APL RAG Ref Performance Indicator 2015/16 2016/17 2017/18 2018/19 2019/20 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
18 Council Tax Collection rate (%) 98.69 98.91 98.4 99 99 29.85 58.10 86.38 99.00 29.50 57.76 29.50 98.60
19 Business Rates Collection rate (%) 98.18 98.84 98.66 98.4 98.4 28.92 56.60 82.87 98.40 22.71 55.47 22.71 98.00
20 Time taken to process new Housing Benefit claims (calendar days) ¯¯ ¯¯ ¯¯ ¯¯ 10.8 24.2 22.4 23.5 10.80 27.1 26.2 26.2 13.00
Council Well-being Previous years 2019/20 2020/21 YTD APL RAG Ref Performance Indicator 2015/16 2016/17 2017/18 2018/19 2019/20 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Overall sickness absence (days per person per year - rolling average) 21 6.84 8.64 9.04 8.74 7.13 9.26 8.79 7.84 7.13 7.11 6.67 6.67 7.00 (days)
Page 2 of 2
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
EC1548 APP1a: Q2 2020-21 PerformanceReport | 2 pages | DownloadRead as text |
PDF |
EC1548 APP1b: Q2 2020-21 WorkloadReport | 2 pages | Download |
PDF |
EC1548 APP2: Five Year Plan Review Q2 2020-21Report | 9 pages | Download |
PDF |
Quarterly Performance ReportReport | 8 pages | Download |
Follow Executive Committee at Malvern Hills and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... | Decided | Open |
| 15 Sep 2026 | Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... | Noted | Open |
| 15 Sep 2026 | Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... | Noted | Open |
| 15 Sep 2026 | Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... | Agreed | Open |
| 15 Sep 2026 | Street Naming and Numbering PolicyRESOLVED that the revised ‘Street Naming and Numbering Policy’, as presented in Appendix 1, be adopted. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.