that i) A financial energy support package to Freedom Leisure of up to £287,000 across 2022/23 and 2023/24, to be financed through a reduction in the management fee received from Freedom Leisure, of an equal amount, via a fully open book process, be approved. ii) Delegated authority be given to the Deputy Chief Executive and Director of Communities and Housing in consultation with the Portfolio Holder for Resources, to increase the level of financial support required in any financial year, up to a maximum amount that is commensurate with the value of the management fee owing in that year. iii) A report to address the impact of rising energy costs on Tenbury Community Swimming Pool be considered at the earliest opportunity. iv) A report on Sport and Leisure provision be considered in Autumn 2023.
Word for word from the decision Malvern Hills published for this meeting.Source: moderngov.malvernhills.gov.uk
Appendix 1 - Partnership approach to driving down operational costs
A key objective in the tendering of the Council’s leisure centre portfolio in 2014 was to reduce utility consumption and carbon emissions and to deliver an improved revenue position. In response, a range of measures have been implemented throughout the contract (since April 2015) and have been reviewed as part of Freedom Leisure and the Council’s response to rising energy costs. The following interventions are intended to reduce energy usage and increase income.
Council led interventions (including £2Mn refurbishment of the Splash in 2020):
• Replacement boilers and modern heat exchanger • Replacement pool pumps and improved pool plant components • Replacement of all remaining lighting units with LEDs throughout the centre • New curtain walling on the pool side of the facility • New dedicated air handling unit within the changing rooms • New low water use showers • Removal of sauna and steam rooms • Investigation being undertaken to consider installing PV/solar thermal panels • Consideration being given to additional park side curtain walling • 60% contribution towards installation of LED lighting at both dual use sites • Allocation of COMF funding (Government funding) to support delivery of Healthier Communities programmes in response to COVID
Freedom Leisure led interventions:
• Refurbishment of the main entrance including reception and café area • Fitness suite refurbishment in 2015 and an additional £200,000 investment between Aug- Nov 2022 • Installation of pool covers in 2015 and replacement in 2022 • Modification of the Air Handling Unit and improvements to the Building Management System • Automated doors to aid zonal temperature control within the changing rooms • Upgraded pool hall and reception lighting to LED units • Invertor drives added to pool pumps in 2015 • Replacement front doors • Appointment of an Environmental and Sustainability Manager • Introduction of site-specific Environmental Action Plans, which include company-wide operational non negotiables, such as: - o Air conditioning to be set no lower than 20 degrees and use natural ventilation where possible o Leisure pool water no higher than 29 degrees and air temperature no more than 1 degree warmer o Reduce boiler set points by 2 degrees and water cylinders by 1 degree o Pool covers must be used every day o Install signage to encourage shorter showers o Turn off PCs, chargers and appliances overnight and when not in use o Turn of gym equipment during off peak times o Maintain good cleaning and maintenance regimes in the plant room
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.